Saraswati Apartment
by AARIN CONSTRUCTIONS DAUND (Rajnandini) · Daund, Pune 413801
What’s in the report? →Possession date of Saraswati Apartment (MahaRERA P52100007213): 30 December 2022, moved from 31 December 2018 (48 months later), and it has already passed. It has 12 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100007213. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100007213, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2022) has passed.
What do you want to know about Saraswati Apartment?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Saraswati Apartment has moved
31 December 2018
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT52100001233)
Reason the builder gave MahaRERA:
“Due to shortage of River Sand, construction of said project was stalled. Also DHFL which has financed most flats in our project have temporarily stopped disbursement, due to which financial unstability we couldn't complete project in given…” Read the full reason
“Due to shortage of River Sand, construction of said project was stalled. Also DHFL which has financed most flats in our project have temporarily stopped disbursement, due to which financial unstability we couldn't complete project in given time. So we request you to allow extension date.”31 December 2020
Extended at the builder's request (MahaRERA application EXT52100005275)
Reason the builder gave MahaRERA: “Due to unavailability of Building material, project couldn't be completed on time.”
30 June 2022
Extended at the builder's request (MahaRERA application EXT52100010375)
Reason the builder gave MahaRERA: “1) Due to Covid-19 Pandemic, lockdown was imposed, so due to unavailibilty of material. 2) Due to Covid-19 Pandemic, lockdown was imposed, so due shortage of labour”
30 December 2022
Revised completion date on MahaRERA
Source: Saraswati Apartment’s extension records on MahaRERA (P52100007213), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Saraswati Apartment
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100007213
- Status
- Lapsed (registration period ended)
- Builder
- AARIN CONSTRUCTIONS DAUND
- Location
- Daund, Pune · 413801
- Project type
- Residential / Group Housing
- Registered on
- 17 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- December 2022
- Delay so far
- 48 months
- Homes
- 12
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Saraswati Apartment, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SARASWATI APARTMENT | 100% | 100% | 100% | 50% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Saraswati Apartment every 1–2 months.
Saraswati Apartment: buildings, flats and land, as filed on MahaRERA
- Buildings: SARASWATI APARTMENT (5 floors)
- Land: 350 sq m (about 0.1 acres) · sanctioned built-up 420 sq m
- Land, as filed: CTS No. 2561-12
- Map: Get directions
The builder’s record and reviews
Aarin Constructions Daund (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 still being built, 3 past the promised date (typically 82 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Saraswati Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Saraswati Apartment: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Saraswati Apartment
What is the possession date of Saraswati Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Saraswati Apartment in Daund, Pune is 30 December 2022 — 48 months later than 31 December 2018, the date given at registration. That date has already passed.
The date has already moved 48 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Saraswati Apartment?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Saraswati Apartment's builder has filed on MahaRERA, the official one, is 30 December 2022, already 48 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Saraswati Apartment extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Saraswati Apartment's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2020, giving the reason "Due to shortage of River Sand, construction of said project was stalled. Also DHFL which has financed most flats in our project have temporarily stopped disbursement, due to which financial unstability we couldn't complete project in given time. So we request you to allow extension date."; to 31 December 2020, giving the reason "Due to unavailability of Building material, project couldn't be completed on time."; to 30 June 2022, giving the reason "1) Due to Covid-19 Pandemic, lockdown was imposed, so due to unavailibilty of material. 2) Due to Covid-19 Pandemic, lockdown was imposed, so due shortage of labour".
What is the RERA number of Saraswati Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Saraswati Apartment in Daund, Pune is P52100007213.
Is Saraswati Apartment registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Saraswati Apartment is registered as P52100007213 and its status is "Lapsed (registration period ended)".
What is the current construction status of Saraswati Apartment? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Saraswati Apartment's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SARASWATI APARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Saraswati Apartment have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Saraswati Apartment safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Saraswati Apartment is registered on MahaRERA as P52100007213, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Saraswati Apartment?
Saraswati Apartment isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Saraswati Apartment?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Saraswati Apartment: gharkundli.com/tools/property-cost-calculator
Has Saraswati Apartment received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Saraswati Apartment isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Saraswati Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), Saraswati Apartment's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Saraswati Apartment uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Saraswati Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Saraswati Apartment's possession date changes?
The latest dates are on Saraswati Apartment's MahaRERA page (P52100007213). GharKundli's Kundli Watch sends a free WhatsApp update on Saraswati Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Saraswati Apartment have?
According to GharKundli's check of MahaRERA records (updated November 2026), Saraswati Apartment has one building filed: SARASWATI APARTMENT with 5 floors.
How big is the land of Saraswati Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), Saraswati Apartment stands on 350 sq m of land (about 0.1 acres), with 420 sq m of sanctioned built-up area.
What is the track record of Saraswati Apartment's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Aarin Constructions Daund (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 still being built, 3 past the promised date (typically 82 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Saraswati Apartment?
Google Maps has reviews of Saraswati Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Saraswati Apartment?
Saraswati Apartment by AARIN CONSTRUCTIONS DAUND (Rajnandini) is in Daund, Pune, pincode 413801, Maharashtra, and is registered on MahaRERA as P52100007213, per GharKundli's check of MahaRERA records. Its land is filed as CTS No. 2561-12. GharKundli lists all 58 MahaRERA projects in Daund (413801).
How many flats are in Saraswati Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), Saraswati Apartment has 12 homes in 1 tower registered on MahaRERA.
When was Saraswati Apartment registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Saraswati Apartment was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Does Saraswati Apartment have any legal issues or court cases?
No court cases are listed for Saraswati Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Saraswati Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is AARIN CONSTRUCTIONS DAUND, the company Rajnandini files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Saraswati Apartment
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Daund (413801)
All 58 projects in Daund (413801) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.