GharKundli

BHAKTI HOME ROYALS

by Jayantilal Dharamshibhai Parmar · Shirsad Phata, PalgharAlso near Virar

Possession: BHAKTI HOME ROYALS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000011844. Status: Completed. 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about BHAKTI HOME ROYALS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BHAKTI HOME ROYALS has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT99000005202)

    Reason the builder gave MahaRERA: “Because of frequent amendments in Government Policy, especially prolonged delay in notifying the DCPR 2034, there were mandatory amendments in sanctioned plans and all further permission got delayed.”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT99000012893)

    Reason the builder gave MahaRERA: “Revision in plans as approved by the authorities.”

Source: BHAKTI HOME ROYALS’s extension records on MahaRERA (P99000011844), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BHAKTI HOME ROYALS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000011844
Status
Completed
Builder
Jayantilal Dharamshibhai Parmar
Location
Shirsad Phata, Palghar · 401303
Project type
Others
Registered on
31 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2025
Delay so far
72 months
Homes
47
Towers
36
Complaints on MahaRERA
5
Court cases listed
0
Title report on file
Not found

Construction progress of BHAKTI HOME ROYALS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ROW HOUSE 1 AND 31100%75%35%0%
ROW HOUSE 2 AND 32100%100%35%0%
ROW HOUSE 3 AND 33100%100%35%0%
ROW HOUSE 4 AND 34100%100%35%0%
ROW HOUSE 5 AND 35100%100%35%0%
ROW HOUSE 6 AND 36100%100%35%0%
ROW HOUSE 7 AND 37100%100%35%0%
ROW HOUSE 8 AND 38100%100%95%90%
ROW HOUSE 9 AND 39100%100%90%95%
ROW HOUSE 10 AND 40100%100%95%30%
ROW HOUSE 11 AND 41100%100%95%30%
ROW HOUSE 12 AND 13100%100%75%30%
ROW HOUSE 42 AND 43100%100%95%30%
ROW HOUSE 14 AND 15100%100%95%30%
Holiday Hoe/Hotel100%100%95%30%
ROW HOUSE 16100%100%95%30%
ROW HOUSE 17100%100%95%30%
ROW HOUSE 18100%100%95%30%
ROW HOUSE 19100%100%95%30%
ROW HOUSE 20100%100%95%30%
ROW HOUSE 21100%100%95%50%
ROW HOUSE 22100%100%95%50%
ROW HOUSE 23100%100%95%50%
ROW HOUSE 24100%100%95%50%
ROW HOUSE 25100%100%95%50%
ROW HOUSE 26100%100%95%50%
ROW HOUSE 27100%50%0%0%
ROW HOUSE 28100%50%0%0%
ROW HOUSE 29100%100%20%0%
ROW HOUSE 30100%100%20%0%

Showing 30 of 36 towers.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BHAKTI HOME ROYALS every month.

BHAKTI HOME ROYALS: buildings, flats and land, as filed on MahaRERA

  • Buildings: ROW HOUSE 1 AND 31 (3 floors) · ROW HOUSE 2 AND 32 (3 floors) · ROW HOUSE 3 AND 33 (3 floors) · ROW HOUSE 4 AND 34 (3 floors) · ROW HOUSE 5 AND 35 (3 floors) · ROW HOUSE 6 AND 36 (3 floors) · ROW HOUSE 7 AND 37 (3 floors) · ROW HOUSE 8 AND 38 (3 floors) · and 22 more
  • Land: 7,010 sq m (about 1.7 acres) · sanctioned built-up 3,995 sq m · recreational space 3,117 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of BHAKTI HOME ROYALS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BHAKTI HOME ROYALS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BHAKTI HOME ROYALS

What is the possession date of BHAKTI HOME ROYALS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BHAKTI HOME ROYALS in Shirsad Phata, Palghar is 31 December 2025 — 72 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for BHAKTI HOME ROYALS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BHAKTI HOME ROYALS's builder has filed on MahaRERA, the official one, is 31 December 2025, already 72 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of BHAKTI HOME ROYALS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI HOME ROYALS's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "Because of frequent amendments in Government Policy, especially prolonged delay in notifying the DCPR 2034, there were mandatory amendments in sanctioned plans and all further permission got delayed."; to 31 December 2025, giving the reason "Revision in plans as approved by the authorities.".

What is the RERA number of BHAKTI HOME ROYALS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BHAKTI HOME ROYALS in Shirsad Phata, Palghar is P99000011844.

Is BHAKTI HOME ROYALS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI HOME ROYALS is registered as P99000011844 and its status is "Completed".

What is the construction status of BHAKTI HOME ROYALS?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI HOME ROYALS's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 50% to 100% across 30 towers. GharKundli's full report compares construction progress with the deadline.

Does BHAKTI HOME ROYALS have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is BHAKTI HOME ROYALS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI HOME ROYALS is registered on MahaRERA as P99000011844, its MahaRERA status is "Completed", its completion date has moved 72 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if BHAKTI HOME ROYALS's possession date changes?

The latest dates are on BHAKTI HOME ROYALS's MahaRERA page (P99000011844). GharKundli's Kundli Watch sends a free WhatsApp update on BHAKTI HOME ROYALS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BHAKTI HOME ROYALS have?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI HOME ROYALS has 30 buildings filed: ROW HOUSE 1 AND 31 with 3 floors; ROW HOUSE 2 AND 32 with 3 floors; ROW HOUSE 3 AND 33 with 3 floors; ROW HOUSE 4 AND 34 with 3 floors; ROW HOUSE 5 AND 35 with 3 floors; ROW HOUSE 6 AND 36 with 3 floors; and 24 more.

How big is the land of BHAKTI HOME ROYALS?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI HOME ROYALS stands on 7,010 sq m of land (about 1.7 acres), with 3,995 sq m of sanctioned built-up area and 3,117 sq m of recreational open space.

Where can I read reviews of BHAKTI HOME ROYALS?

Google Maps has reviews of BHAKTI HOME ROYALS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BHAKTI HOME ROYALS?

BHAKTI HOME ROYALS by Jayantilal Dharamshibhai Parmar is in Shirsad Phata, Palghar (pincode 401303), near Virar, Maharashtra, and is registered on MahaRERA as P99000011844, per GharKundli's check of MahaRERA records.

How many homes are in BHAKTI HOME ROYALS?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI HOME ROYALS has 47 homes in 36 towers registered on MahaRERA.

When was BHAKTI HOME ROYALS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BHAKTI HOME ROYALS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on BHAKTI HOME ROYALS?

No court cases are listed for BHAKTI HOME ROYALS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of BHAKTI HOME ROYALS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Jayantilal Dharamshibhai Parmar.

Other projects in Vasai

All 187 projects in Virar West (401303) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.