Vighnaharta Sai Datta Vihar
by Vighnaharta Promoters and Developers · Dighi, Pune 411039Registered on MahaRERA as “SAI DATTA VIHAR”
What’s in the report? →Possession date of Vighnaharta Sai Datta Vihar (MahaRERA P52100011638): 30 October 2020, moved from 31 December 2018 (22 months later), and it has already passed. It has 24 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100011638. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100011638, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2020) has passed.
What do you want to know about Vighnaharta Sai Datta Vihar?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vighnaharta Sai Datta Vihar has moved
31 December 2018
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT52100002564)
Reason the builder gave MahaRERA: “TDR application was delayed by the PCMC government, hence the project got delayed.”
30 October 2020
Revised completion date on MahaRERA
Source: Vighnaharta Sai Datta Vihar’s extension records on MahaRERA (P52100011638), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vighnaharta Sai Datta Vihar
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100011638
- Status
- Lapsed (registration period ended)
- Builder
- Vighnaharta Promoters and Developers
- Location
- Dighi, Pune · 411039
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- October 2020
- Delay so far
- 22 months
- Homes
- 24
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Vighnaharta Sai Datta Vihar, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAI DATTA VIHAR | 100% | 70% | 10% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vighnaharta Sai Datta Vihar every 1–2 months.
Vighnaharta Sai Datta Vihar: buildings, flats and land, as filed on MahaRERA
- Buildings: SAI DATTA VIHAR (6 floors)
- Land: 756 sq m (about 0.2 acres) · sanctioned built-up 580 sq m
- Land, as filed: CTS NO 4378/SURVEY NO 216/HISSA NO 1C/1
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Vighnaharta Sai Datta Vihar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vighnaharta Sai Datta Vihar: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vighnaharta Sai Datta Vihar
What is the possession date of Vighnaharta Sai Datta Vihar?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Vighnaharta Sai Datta Vihar in Dighi, Pune is 30 October 2020 — 22 months later than 31 December 2018, the date given at registration. That date has already passed.
The date has already moved 22 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Vighnaharta Sai Datta Vihar?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vighnaharta Sai Datta Vihar's builder has filed on MahaRERA, the official one, is 30 October 2020, already 22 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vighnaharta Sai Datta Vihar extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Vighnaharta Sai Datta Vihar's builder applied to MahaRERA to extend the completion date once: to 30 April 2020, giving the reason "TDR application was delayed by the PCMC government, hence the project got delayed.".
What is the RERA number of Vighnaharta Sai Datta Vihar?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Vighnaharta Sai Datta Vihar in Dighi, Pune is P52100011638.
Is Vighnaharta Sai Datta Vihar registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Vighnaharta Sai Datta Vihar is registered as P52100011638 and its status is "Lapsed (registration period ended)".
What is the current construction status of Vighnaharta Sai Datta Vihar? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Vighnaharta Sai Datta Vihar's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI DATTA VIHAR is 70% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does Vighnaharta Sai Datta Vihar have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Vighnaharta Sai Datta Vihar safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Vighnaharta Sai Datta Vihar is registered on MahaRERA as P52100011638, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 22 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vighnaharta Sai Datta Vihar?
Vighnaharta Sai Datta Vihar isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vighnaharta Sai Datta Vihar?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vighnaharta Sai Datta Vihar: gharkundli.com/tools/property-cost-calculator
Has Vighnaharta Sai Datta Vihar received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Vighnaharta Sai Datta Vihar isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 October 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Vighnaharta Sai Datta Vihar?
According to GharKundli's check of MahaRERA records (updated November 2026), Vighnaharta Sai Datta Vihar's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 October 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Vighnaharta Sai Datta Vihar uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Vighnaharta Sai Datta Vihar was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vighnaharta Sai Datta Vihar's possession date changes?
The latest dates are on Vighnaharta Sai Datta Vihar's MahaRERA page (P52100011638). GharKundli's Kundli Watch sends a free WhatsApp update on Vighnaharta Sai Datta Vihar every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vighnaharta Sai Datta Vihar have?
According to GharKundli's check of MahaRERA records (updated November 2026), Vighnaharta Sai Datta Vihar has one building filed: SAI DATTA VIHAR with 6 floors.
How big is the land of Vighnaharta Sai Datta Vihar?
According to GharKundli's check of MahaRERA records (updated November 2026), Vighnaharta Sai Datta Vihar stands on 756 sq m of land (about 0.2 acres), with 580 sq m of sanctioned built-up area.
What are the reviews of Vighnaharta Sai Datta Vihar?
Google Maps has reviews of Vighnaharta Sai Datta Vihar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vighnaharta Sai Datta Vihar?
Vighnaharta Sai Datta Vihar by Vighnaharta Promoters and Developers is in Dighi, Pune, pincode 411039, Maharashtra, and is registered on MahaRERA as P52100011638, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 4378/SURVEY NO 216/HISSA NO 1C/1. GharKundli lists all 60 MahaRERA projects in Bhosari (411039).
How many flats are in Vighnaharta Sai Datta Vihar?
According to GharKundli's check of MahaRERA records (updated November 2026), Vighnaharta Sai Datta Vihar has 24 homes in 1 tower registered on MahaRERA.
When was Vighnaharta Sai Datta Vihar registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Vighnaharta Sai Datta Vihar was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Vighnaharta Sai Datta Vihar have any legal issues or court cases?
No court cases are listed for Vighnaharta Sai Datta Vihar on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Vighnaharta Sai Datta Vihar?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Vighnaharta Promoters and Developers.
Check it yourself on MahaRERA
- How to check the possession date of Vighnaharta Sai Datta Vihar
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Bhosari (411039)
- Sparkle Enclave
- Siddhaaya Park
- Kamalraj Prayag C
- Infinity Spaces
- Krishnai Residency
- Shri Swami Samarth Residency
- Sunrise Grand
- Sai Dham
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.