KUTUMB PRIME
by NAIKNAVARE BUILDCON PVT LTD · Shivajinagar, Pune
Possession: KUTUMB PRIME is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100003209. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about KUTUMB PRIME?
How the possession date of KUTUMB PRIME has moved
31 March 2019
Completion date given when the project was registered
30 March 2020
Extended at the builder's request (MahaRERA application EXT52100001652)
Reason the builder gave MahaRERA:
“Date of completion of the project need to be extended for one year for following reasons; 1. Since last 3-4 years Real Estate industry is experiencing significant recessionary trends, which resulted in a severe working capital finance crunc…” Read the full reason
“Date of completion of the project need to be extended for one year for following reasons; 1. Since last 3-4 years Real Estate industry is experiencing significant recessionary trends, which resulted in a severe working capital finance crunch. Sale of Apartments has been slowed down and also some of the customers haven’t paid due amounts as on date. We were trying to get finance from financial institutions to complete the project, however, in order to mitigate risks of other defaulting projects from each other, financial institutions are preferring formation of Special Purpose Vehicle Compan…”31 December 2020
Extended at the builder's request (MahaRERA application EXT52100006278)
Reason the builder gave MahaRERA:
“1. The development of the Project has been slow owing to various factors beyond the control of the Promoter such as slowdown in market, inconsistent material supply, difficulties in availing finance. Since last 3-4 years Real Estate industr…” Read the full reason
“1. The development of the Project has been slow owing to various factors beyond the control of the Promoter such as slowdown in market, inconsistent material supply, difficulties in availing finance. Since last 3-4 years Real Estate industry is experiencing significant recessionary trends, which resulted in a severe working capital finance crunch. Sale of Apartments has been slowed down and also some of the customers haven’t paid due amounts as on date. 2. In addition to this, since prior to March, 2020 the Promoter is experiencing a severe pandemic COVID-19, which is adversely affecting Re…”30 December 2021
Extended at the builder's request (MahaRERA application EXT52100008794)
Reason the builder gave MahaRERA:
“1. The development of the Project has been slow owing to various factors beyond the control of the Promoter such as slowdown in market, inconsistent material supply, difficulties in availing finance. Since last 3-4 years Real Estate industr…” Read the full reason
“1. The development of the Project has been slow owing to various factors beyond the control of the Promoter such as slowdown in market, inconsistent material supply, difficulties in availing finance. Since last 3-4 years Real Estate industry is experiencing significant recessionary trends, which resulted in a severe working capital finance crunch. Sale of Apartments has been slowed down and also some of the customers haven’t paid due amounts as on date. 2. In addition to this, since prior to March, 2020 the Promoter is experiencing a severe pandemic COVID-19, which is adversely affecting Re…”29 June 2023
Extended at the builder's request (MahaRERA application EXT52100012219)
Reason the builder gave MahaRERA:
“Date : 04.07.2022 To The Chief Engineer, RERA OFFICE, MUMBAI. Subject : Application for the Extension of "Eagle's Nest" Project – 3 P52100003209 in RERA. Dear Sir, We have registered our "Eagle's Nest" Project -3 P52100003209 under RERA. Th…” Read the full reason
“Date : 04.07.2022 To The Chief Engineer, RERA OFFICE, MUMBAI. Subject : Application for the Extension of "Eagle's Nest" Project – 3 P52100003209 in RERA. Dear Sir, We have registered our "Eagle's Nest" Project -3 P52100003209 under RERA. The completion date for the project is 30th June 2022. But we are unable to complete our project due to various reasons mentioned as under. As you are aware, due to Covid-19 lockdown announced by the Government of Maharashtra 2 years back, the labours moved from site to their native places. Mostly the labours are from other States like UP, Bihar, Orissa, As…”
Source: KUTUMB PRIME’s extension records on MahaRERA (P52100003209), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KUTUMB PRIME
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 court cases, and how it ended
- Construction pace against the June 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- KUTUMB PRIMEP52100002348 · possession 26 Jun 2024
- KUTUMB PRIMEP52100002090 · possession 29 Jun 2023
- MahaRERA registration
- P52100003209
- Status
- Completed
- Builder
- NAIKNAVARE BUILDCON PVT LTD
- Location
- Shivajinagar, Pune · 412106
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- June 2023
- Delay so far
- 51 months
- Homes
- 36
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 4
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of KUTUMB PRIME, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A1 BUILDING | 100% | 85% | 50% | 0% |
| CLUB HOUSE | 100% | 100% | 100% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KUTUMB PRIME every month.
KUTUMB PRIME: buildings, flats and land, as filed on MahaRERA
- Buildings: A1 BUILDING (10 floors) · CLUB HOUSE (2 floors)
- Land: 4,796 sq m (about 1.2 acres) · sanctioned built-up 5,986 sq m · recreational space 479 sq m
The builder’s record and reviews
Naiknavare Buildcon (a group of 4 linked companies) has 27 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 8 finished, 2 within the promised date and 6 needed more time (typically 40 months); 9 still being built, 2 past the promised date (typically 52 months late); 7 lapsed. 34 complaints on MahaRERA across 7 projects.
Read Google reviews of KUTUMB PRIME →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KUTUMB PRIME: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KUTUMB PRIME
What is the possession date of KUTUMB PRIME?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KUTUMB PRIME in Shivajinagar, Pune is 29 June 2023 — 51 months later than 31 March 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for KUTUMB PRIME?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KUTUMB PRIME's builder has filed on MahaRERA, the official one, is 29 June 2023, already 51 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KUTUMB PRIME extended?
According to GharKundli's check of MahaRERA records (updated November 2026), KUTUMB PRIME's builder applied to MahaRERA to extend the completion date 4 times: to 30 March 2020, giving the reason "Date of completion of the project need to be extended for one year for following reasons; 1. Since last 3-4 years Real Estate industry is experiencing significant recessionary trends, which resulted in a severe working capital finance crunch. Sale of Apartments has been slowed down and also some of the customers haven’t paid due amounts as on date. We were trying to get finance from financial institutions to complete the project, however, in order to mitigate risks of other defaulting projects from each other, financial institutions are preferring formation of Special Purpose Vehicle Compan…"; to 31 December 2020, giving the reason "1. The development of the Project has been slow owing to various factors beyond the control of the Promoter such as slowdown in market, inconsistent material supply, difficulties in availing finance. Since last 3-4 years Real Estate industry is experiencing significant recessionary trends, which resulted in a severe working capital finance crunch. Sale of Apartments has been slowed down and also some of the customers haven’t paid due amounts as on date. 2. In addition to this, since prior to March, 2020 the Promoter is experiencing a severe pandemic COVID-19, which is adversely affecting Re…"; to 30 December 2021, giving the reason "1. The development of the Project has been slow owing to various factors beyond the control of the Promoter such as slowdown in market, inconsistent material supply, difficulties in availing finance. Since last 3-4 years Real Estate industry is experiencing significant recessionary trends, which resulted in a severe working capital finance crunch. Sale of Apartments has been slowed down and also some of the customers haven’t paid due amounts as on date. 2. In addition to this, since prior to March, 2020 the Promoter is experiencing a severe pandemic COVID-19, which is adversely affecting Re…"; to 29 June 2023, giving the reason "Date : 04.07.2022 To The Chief Engineer, RERA OFFICE, MUMBAI. Subject : Application for the Extension of "Eagle's Nest" Project – 3 P52100003209 in RERA. Dear Sir, We have registered our "Eagle's Nest" Project -3 P52100003209 under RERA. The completion date for the project is 30th June 2022. But we are unable to complete our project due to various reasons mentioned as under. As you are aware, due to Covid-19 lockdown announced by the Government of Maharashtra 2 years back, the labours moved from site to their native places. Mostly the labours are from other States like UP, Bihar, Orissa, As…".
What is the RERA number of KUTUMB PRIME?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KUTUMB PRIME in Shivajinagar, Pune is P52100003209.
Is KUTUMB PRIME registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KUTUMB PRIME is registered as P52100003209 and its status is "Completed".
What is the construction status of KUTUMB PRIME?
According to GharKundli's check of MahaRERA records (updated November 2026), KUTUMB PRIME's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 85% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does KUTUMB PRIME have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is KUTUMB PRIME safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), KUTUMB PRIME is registered on MahaRERA as P52100003209, its MahaRERA status is "Completed", its completion date has moved 51 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does KUTUMB PRIME have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: KUTUMB PRIME (P52100002348, possession 26 Jun 2024); KUTUMB PRIME (P52100002090, possession 29 Jun 2023). Check that your agreement names the registration of your own wing.
How can I get updates if KUTUMB PRIME's possession date changes?
The latest dates are on KUTUMB PRIME's MahaRERA page (P52100003209). GharKundli's Kundli Watch sends a free WhatsApp update on KUTUMB PRIME every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KUTUMB PRIME have?
According to GharKundli's check of MahaRERA records (updated November 2026), KUTUMB PRIME has 2 buildings filed: A1 BUILDING with 10 floors; CLUB HOUSE with 2 floors.
How big is the land of KUTUMB PRIME?
According to GharKundli's check of MahaRERA records (updated November 2026), KUTUMB PRIME stands on 4,796 sq m of land (about 1.2 acres), with 5,986 sq m of sanctioned built-up area and 479 sq m of recreational open space.
What is the track record of KUTUMB PRIME's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Naiknavare Buildcon (a group of 4 linked companies) has 27 projects on MahaRERA since 2017, this one included. Of the 24 GharKundli has checked: 8 finished, 2 within the promised date and 6 needed more time (typically 40 months); 9 still being built, 2 past the promised date (typically 52 months late); 7 lapsed. 34 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of KUTUMB PRIME?
Google Maps has reviews of KUTUMB PRIME written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KUTUMB PRIME?
KUTUMB PRIME by NAIKNAVARE BUILDCON PVT LTD is in Shivajinagar, Pune (pincode 412106), Maharashtra, and is registered on MahaRERA as P52100003209, per GharKundli's check of MahaRERA records.
How many homes are in KUTUMB PRIME?
According to GharKundli's check of MahaRERA records (updated November 2026), KUTUMB PRIME has 36 homes in 2 towers registered on MahaRERA.
When was KUTUMB PRIME registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KUTUMB PRIME was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on KUTUMB PRIME?
4 court cases are listed for KUTUMB PRIME on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of KUTUMB PRIME?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NAIKNAVARE BUILDCON PVT LTD, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of KUTUMB PRIME
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Shivajinagar
- 7 BUSINESS SQUARE
- MADHUSAGAR
- MADHUMATI CHSL
- ASHIYANA
- SAI CHAMBERS
- NARENDRA HOUSING SOCIETY
- VENKATESH LAUREL
- PRIME PROSPERA
Other projects by NAIKNAVARE BUILDCON PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.