by NIRMITI VASTU CREATION LLP · Erandwana, PuneAlso near Prabhat Road, Shivajinagar Bhamburda, Deccan Gymkhana

Possession date of NIRMITI ELITE: 30 July 2023, moved from 31 July 2022 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100004507. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2023) has passed.

What do you want to know about NIRMITI ELITE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NIRMITI ELITE has moved

  1. 31 July 2022

    Completion date given when the project was registered

  2. 30 July 2023

    Extended at the builder's request (MahaRERA application EXT52100012452)

    Reason the builder gave MahaRERA:
    “Due to Covid-19 pandemic which caused the slow-down in the construction industry we were not able to complete the project as per the stipulated time. Also, the rise in the cost of materials, labours, etc. made it difficult to complete the p…” Read the full reason“Due to Covid-19 pandemic which caused the slow-down in the construction industry we were not able to complete the project as per the stipulated time. Also, the rise in the cost of materials, labours, etc. made it difficult to complete the project in the decided cost for the project.”

Source: NIRMITI ELITE’s extension records on MahaRERA (P52100004507), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NIRMITI ELITE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100004507
Status
Lapsed (registration period ended)
Builder
NIRMITI VASTU CREATION LLP
Location
Erandwana, Pune · 411004
Project type
Others
Registered on
9 Aug 2017
Completion date at registration
July 2022
Latest completion date
July 2023
Delay so far
12 months
Homes
5
Sold or booked
91%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of NIRMITI ELITE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NIRMITI ELITE0%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • NIRMITI ELITE: covers 8 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NIRMITI ELITE every month.

NIRMITI ELITE: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Nirmiti Vastu Creation has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of NIRMITI ELITE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NIRMITI ELITE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NIRMITI ELITE

What is the possession date of NIRMITI ELITE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NIRMITI ELITE in Erandwana, Pune is 30 July 2023 — 12 months later than 31 July 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for NIRMITI ELITE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NIRMITI ELITE's builder has filed on MahaRERA, the official one, is 30 July 2023, already 12 months later than the 31 July 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NIRMITI ELITE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI ELITE's builder applied to MahaRERA to extend the completion date once: to 30 July 2023, giving the reason "Due to Covid-19 pandemic which caused the slow-down in the construction industry we were not able to complete the project as per the stipulated time. Also, the rise in the cost of materials, labours, etc. made it difficult to complete the project in the decided cost for the project.".

What is the RERA number of NIRMITI ELITE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NIRMITI ELITE in Erandwana, Pune is P52100004507.

Is NIRMITI ELITE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI ELITE is registered as P52100004507 and its status is "Lapsed (registration period ended)".

What is the construction status of NIRMITI ELITE?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI ELITE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NIRMITI ELITE is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does NIRMITI ELITE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is NIRMITI ELITE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI ELITE is registered on MahaRERA as P52100004507, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NIRMITI ELITE's possession date changes?

The latest dates are on NIRMITI ELITE's MahaRERA page (P52100004507). GharKundli's Kundli Watch sends a free WhatsApp update on NIRMITI ELITE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NIRMITI ELITE have?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI ELITE has one building filed: NIRMITI ELITE with 8 floors and 22 units.

How big is the land of NIRMITI ELITE?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI ELITE stands on 953 sq m of land (about 0.2 acres), with 867 sq m of sanctioned built-up area.

What is the track record of NIRMITI ELITE's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Vastu Creation has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NIRMITI ELITE?

Google Maps has reviews of NIRMITI ELITE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NIRMITI ELITE?

NIRMITI ELITE by NIRMITI VASTU CREATION LLP is in Erandwana, Pune (pincode 411004), near Prabhat Road, Shivajinagar Bhamburda, Deccan Gymkhana, Maharashtra, and is registered on MahaRERA as P52100004507, per GharKundli's check of MahaRERA records. Its boundaries filed there include LAW COLLEGE ROAD.

How many homes are in NIRMITI ELITE?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI ELITE has 5 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.

When was NIRMITI ELITE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NIRMITI ELITE was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NIRMITI ELITE?

No court cases are listed for NIRMITI ELITE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of NIRMITI ELITE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NIRMITI VASTU CREATION LLP, which has 1 other project registered on MahaRERA.

Other projects in Erandwana

All 157 projects in Erandwane (411004) →

Other projects by NIRMITI VASTU CREATION LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.