VITHAL HARI TOWER
by VITHAL ENTERPRISES · Virar West, Palghar
Possession: VITHAL HARI TOWER is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000006107. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about VITHAL HARI TOWER?
How the possession date of VITHAL HARI TOWER has moved
20 March 2023
Completion date given when the project was registered
19 March 2024
Extended at the builder's request (MahaRERA application EXT99000011518)
Reason the builder gave MahaRERA: “Work in progress as per Architect and Engineer and CA certificate pl check”
Source: VITHAL HARI TOWER’s extension records on MahaRERA (P99000006107), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VITHAL HARI TOWER
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000006107
- Status
- Completed
- Builder
- VITHAL ENTERPRISES
- Location
- Virar West, Palghar · 401303
- Project type
- Others
- Registered on
- 14 Aug 2017
- Completion date at registration
- March 2023
- Latest completion date
- March 2024
- Delay so far
- 12 months
- Homes
- 110
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VITHAL HARI TOWER, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VITHAL HARI TOWER | 100% | 50% | 15% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VITHAL HARI TOWER every month.
VITHAL HARI TOWER: buildings, flats and land, as filed on MahaRERA
- Buildings: VITHAL HARI TOWER (9 floors)
- Land: 2,122 sq m (about 0.5 acres) · sanctioned built-up 2,111 sq m · recreational space 212 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VITHAL HARI TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VITHAL HARI TOWER: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VITHAL HARI TOWER
What is the possession date of VITHAL HARI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VITHAL HARI TOWER in Virar West, Palghar is 19 March 2024 — 12 months later than 20 March 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for VITHAL HARI TOWER?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VITHAL HARI TOWER's builder has filed on MahaRERA, the official one, is 19 March 2024, already 12 months later than the 20 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VITHAL HARI TOWER extended?
According to GharKundli's check of MahaRERA records (updated November 2026), VITHAL HARI TOWER's builder applied to MahaRERA to extend the completion date once: to 19 March 2024, giving the reason "Work in progress as per Architect and Engineer and CA certificate pl check".
What is the RERA number of VITHAL HARI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VITHAL HARI TOWER in Virar West, Palghar is P99000006107.
Is VITHAL HARI TOWER registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VITHAL HARI TOWER is registered as P99000006107 and its status is "Completed".
What is the construction status of VITHAL HARI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), VITHAL HARI TOWER's status on MahaRERA is "Completed". As filed by the builder, slab work on VITHAL HARI TOWER is 50% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.
Does VITHAL HARI TOWER have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is VITHAL HARI TOWER safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), VITHAL HARI TOWER is registered on MahaRERA as P99000006107, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VITHAL HARI TOWER's possession date changes?
The latest dates are on VITHAL HARI TOWER's MahaRERA page (P99000006107). GharKundli's Kundli Watch sends a free WhatsApp update on VITHAL HARI TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VITHAL HARI TOWER have?
According to GharKundli's check of MahaRERA records (updated November 2026), VITHAL HARI TOWER has one building filed: VITHAL HARI TOWER with 9 floors.
How big is the land of VITHAL HARI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), VITHAL HARI TOWER stands on 2,122 sq m of land (about 0.5 acres), with 2,111 sq m of sanctioned built-up area and 212 sq m of recreational open space.
Where can I read reviews of VITHAL HARI TOWER?
Google Maps has reviews of VITHAL HARI TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VITHAL HARI TOWER?
VITHAL HARI TOWER by VITHAL ENTERPRISES is in Virar West, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000006107, per GharKundli's check of MahaRERA records.
How many homes are in VITHAL HARI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), VITHAL HARI TOWER has 110 homes in 1 tower registered on MahaRERA.
When was VITHAL HARI TOWER registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), VITHAL HARI TOWER was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on VITHAL HARI TOWER?
No court cases are listed for VITHAL HARI TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of VITHAL HARI TOWER?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VITHAL ENTERPRISES.
Check it yourself on MahaRERA
- How to check the possession date of VITHAL HARI TOWER
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401303
- VIVA CITY - A5
- Bhakti Greens
- S M TOWER
- VIMALNATH Building no-2
- UNIQUE APARTMENT
- VALENCIA CHS
- Belle Vue 9
- SUPER HOMEZ-HARMONY PHASE III
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.