LABH HEIGHTS

by LABH ASSOCIATES · Virar West, Palghar

Possession: LABH HEIGHTS is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000003792. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about LABH HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of LABH HEIGHTS has moved

  1. 31 March 2019

    Completion date given when the project was registered

  2. 30 March 2020

    Extended at the builder's request (MahaRERA application EXT99000001599)

    Reason the builder gave MahaRERA:
    “WE HAVE APPLIED FOR OCCUPATION CERTIFICATE FOR THE BUILDING NO.6, WING K & L IN VVCMC OOFICE, WHICH IS EXPECTED TO RECEIVED AFTER END ELECTION IN OUR STATE OR WE SHALL RECEIVED BEFORE DECEMBER 2019. THE WORK OF BUILDING NO.7 WING A IS IN PR…” Read the full reason“WE HAVE APPLIED FOR OCCUPATION CERTIFICATE FOR THE BUILDING NO.6, WING K & L IN VVCMC OOFICE, WHICH IS EXPECTED TO RECEIVED AFTER END ELECTION IN OUR STATE OR WE SHALL RECEIVED BEFORE DECEMBER 2019. THE WORK OF BUILDING NO.7 WING A IS IN PROGRESS & EXPECTED TO BE COMPLETE BY DECEMBER 2019 AND IMMEDIATELY WE WILL PROCESS FOR OCCUPATION APPLICATION TO VVCMC OFFICE. SO WE REQUEST YOU TO GRANT EXTENSION TO OUR ABOVE PROJECT.”
  3. 30 June 2021

    Extended at the builder's request (MahaRERA application EXT99000008766)

    Reason the builder gave MahaRERA: “WE HAVE APPLIED FOR FIRE NOC ,BUT TO COVID PANDEMIC THE WORK FORCE IN VVCMC IS LIMITED SO IT WILL TAKE SOME MORE MONTHS TO GET THE FIRE NOC ,AFTER THAT WE CAN APPLY FOR OC .SO WE REQUEST YOU TO EXTEND OUR RERA CERTIFICATE UPTO 31/03/2022”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT99000011488)

    Reason the builder gave MahaRERA: “some flats are still not sold.”

Source: LABH HEIGHTS’s extension records on MahaRERA (P99000003792), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on LABH HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000003792
Status
Completed
Builder
LABH ASSOCIATES
Location
Virar West, Palghar · 401303
Project type
Others
Registered on
6 Aug 2017
Completion date at registration
March 2019
Latest completion date
December 2025
Delay so far
81 months
Homes
180
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of LABH HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LABH HEIGHTS BLDG NO 6 WING K AND L100%100%100%100%
LABH HEIGHTS BLDG NO 7 WING A100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on LABH HEIGHTS every month.

LABH HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: LABH HEIGHTS BLDG NO 6 WING K AND L (14 floors) · LABH HEIGHTS BLDG NO 7 WING A (14 floors)
  • Land: 2,869 sq m (about 0.7 acres) · sanctioned built-up 10,082 sq m · recreational space 208 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of LABH HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

LABH HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about LABH HEIGHTS

What is the possession date of LABH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for LABH HEIGHTS in Virar West, Palghar is 31 December 2025 — 81 months later than 31 March 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for LABH HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date LABH HEIGHTS's builder has filed on MahaRERA, the official one, is 31 December 2025, already 81 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of LABH HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), LABH HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2020, giving the reason "WE HAVE APPLIED FOR OCCUPATION CERTIFICATE FOR THE BUILDING NO.6, WING K & L IN VVCMC OOFICE, WHICH IS EXPECTED TO RECEIVED AFTER END ELECTION IN OUR STATE OR WE SHALL RECEIVED BEFORE DECEMBER 2019. THE WORK OF BUILDING NO.7 WING A IS IN PROGRESS & EXPECTED TO BE COMPLETE BY DECEMBER 2019 AND IMMEDIATELY WE WILL PROCESS FOR OCCUPATION APPLICATION TO VVCMC OFFICE. SO WE REQUEST YOU TO GRANT EXTENSION TO OUR ABOVE PROJECT."; to 30 June 2021, giving the reason "WE HAVE APPLIED FOR FIRE NOC ,BUT TO COVID PANDEMIC THE WORK FORCE IN VVCMC IS LIMITED SO IT WILL TAKE SOME MORE MONTHS TO GET THE FIRE NOC ,AFTER THAT WE CAN APPLY FOR OC .SO WE REQUEST YOU TO EXTEND OUR RERA CERTIFICATE UPTO 31/03/2022"; to 31 December 2025, giving the reason "some flats are still not sold.".

What is the RERA number of LABH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of LABH HEIGHTS in Virar West, Palghar is P99000003792.

Is LABH HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), LABH HEIGHTS is registered as P99000003792 and its status is "Completed".

What is the construction status of LABH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), LABH HEIGHTS's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does LABH HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is LABH HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), LABH HEIGHTS is registered on MahaRERA as P99000003792, its MahaRERA status is "Completed", its completion date has moved 81 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if LABH HEIGHTS's possession date changes?

The latest dates are on LABH HEIGHTS's MahaRERA page (P99000003792). GharKundli's Kundli Watch sends a free WhatsApp update on LABH HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does LABH HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), LABH HEIGHTS has 2 buildings filed: LABH HEIGHTS BLDG NO 6 WING K AND L with 14 floors; LABH HEIGHTS BLDG NO 7 WING A with 14 floors.

How big is the land of LABH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), LABH HEIGHTS stands on 2,869 sq m of land (about 0.7 acres), with 10,082 sq m of sanctioned built-up area and 208 sq m of recreational open space.

Where can I read reviews of LABH HEIGHTS?

Google Maps has reviews of LABH HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is LABH HEIGHTS?

LABH HEIGHTS by LABH ASSOCIATES is in Virar West, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000003792, per GharKundli's check of MahaRERA records.

How many homes are in LABH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), LABH HEIGHTS has 180 homes in 2 towers registered on MahaRERA.

When was LABH HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), LABH HEIGHTS was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on LABH HEIGHTS?

No court cases are listed for LABH HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of LABH HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is LABH ASSOCIATES.

Other projects in pincode 401303

All 200 projects in Virar West (401303) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.