by VISHWA DEVELOPER & PROMOTER · Sus, Pune 410503Also near Manchar, Mordewadi

What’s in the report? →

Possession date of Vishwavihar (MahaRERA P52100006484): 23 July 2023, and it has already passed. It has 136 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100006484. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100006484, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (July 2023) has passed.

What do you want to know about Vishwavihar?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Vishwavihar

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100006484
Status
Lapsed (registration period ended)
Builder
VISHWA DEVELOPER & PROMOTER
Location
Sus, Pune · 410503
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
July 2023
Latest completion date
July 2023
Homes
136
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Vishwavihar, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING A100%100%100%100%
WING B100%100%100%100%
WING C100%100%60%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vishwavihar every 1–2 months.

Vishwavihar: buildings, flats and land, as filed on MahaRERA

  • Buildings: WING A (5 floors) · WING B (5 floors) · WING C (5 floors)
  • Land: 8,800 sq m (about 2.2 acres) · sanctioned built-up 6,724 sq m · recreational space 2,200 sq m
  • Land, as filed: 12/ 9A 10 11/1A, 12/12A/1, 12/12B/1, 12/13A
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Vishwa Developer & Promoter has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Vishwavihar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vishwavihar: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Vishwavihar

What is the possession date of Vishwavihar?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Vishwavihar in Sus, Pune is 23 July 2023. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Vishwavihar?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vishwavihar's builder has filed on MahaRERA, the official one, is 23 July 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Vishwavihar?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Vishwavihar in Sus, Pune is P52100006484.

Is Vishwavihar registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vishwavihar is registered as P52100006484 and its status is "Lapsed (registration period ended)".

What is the current construction status of Vishwavihar? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Vishwavihar's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Vishwavihar have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Vishwavihar safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Vishwavihar is registered on MahaRERA as P52100006484, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Vishwavihar?

Vishwavihar isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Vishwavihar?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vishwavihar: gharkundli.com/tools/property-cost-calculator

Has Vishwavihar received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Vishwavihar isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 23 July 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Vishwavihar?

According to GharKundli's check of MahaRERA records (updated November 2026), Vishwavihar's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (23 July 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Vishwavihar uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Vishwavihar was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Vishwavihar have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: VISHWAVIHAR (P52100047735, possession 1 Sep 2025). Check that your agreement names the registration of your own wing.

How can I get updates if Vishwavihar's possession date changes?

The latest dates are on Vishwavihar's MahaRERA page (P52100006484). GharKundli's Kundli Watch sends a free WhatsApp update on Vishwavihar every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vishwavihar have?

According to GharKundli's check of MahaRERA records (updated November 2026), Vishwavihar has 3 buildings filed: WING A with 5 floors; WING B with 5 floors; WING C with 5 floors.

How big is the land of Vishwavihar?

According to GharKundli's check of MahaRERA records (updated November 2026), Vishwavihar stands on 8,800 sq m of land (about 2.2 acres), with 6,724 sq m of sanctioned built-up area and 2,200 sq m of recreational open space.

What is the track record of Vishwavihar's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Vishwa Developer & Promoter has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Vishwavihar?

Google Maps has reviews of Vishwavihar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Vishwavihar?

Vishwavihar by VISHWA DEVELOPER & PROMOTER is in Sus, Pune, pincode 410503 (near Manchar, Mordewadi), Maharashtra, and is registered on MahaRERA as P52100006484, per GharKundli's check of MahaRERA records. Its land is filed as 12/ 9A 10 11/1A, 12/12A/1, 12/12B/1, 12/13A. GharKundli lists all 36 MahaRERA projects in Manchar (410503).

How many flats are in Vishwavihar?

According to GharKundli's check of MahaRERA records (updated November 2026), Vishwavihar has 136 homes in 3 towers registered on MahaRERA.

When was Vishwavihar registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vishwavihar was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Does Vishwavihar have any legal issues or court cases?

No court cases are listed for Vishwavihar on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Vishwavihar?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VISHWA DEVELOPER & PROMOTER, which has 1 other project registered on MahaRERA.

Other projects in Manchar (410503)

All 36 projects in Manchar (410503) →

Other projects by VISHWA DEVELOPER & PROMOTER

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.