by Urban Life Ventures · sahakar nagar, PuneAlso near Parvati, Gultekdi, Sahakarnagar
Possession date of Urban Life Ventures Aapli Society: 31 August 2022, moved from 31 March 2020 (29 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100006249. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (August 2022) has passed.
What do you want to know about Urban Life Ventures Aapli Society?
How the possession date of Urban Life Ventures Aapli Society has moved
31 March 2020
Completion date given when the project was registered
31 March 2021
Extended at the builder's request (MahaRERA application EXT52100005734)
Reason the builder gave MahaRERA:
“2) Explanatory note regarding the state of development works in the project and reason for not completing the development works in the project within the period declared in the declaration submitted in Form ‘B’ at the time of making applica…” Read the full reason
“2) Explanatory note regarding the state of development works in the project and reason for not completing the development works in the project within the period declared in the declaration submitted in Form ‘B’ at the time of making application for the registration of the project:- a) Sand is a critical raw material. River sand was banned by the government for environmental reasons, that created shortage and substitute material was not readily available. b) Elections were held in April 2019 (Central) and October 2019 (state) and migrant workers went on leave creating manpower shortage. c) D…”31 August 2022
Extended at the builder's request (MahaRERA application EXT52100011888)
Reason the builder gave MahaRERA:
“Explanatory note regarding the state of development works in the project and reasons for not completing the development works in the project within the period:- 1. Due to shortage of lift Material like chips, other small components etc. whi…” Read the full reason
“Explanatory note regarding the state of development works in the project and reasons for not completing the development works in the project within the period:- 1. Due to shortage of lift Material like chips, other small components etc. which delayed the delivery of material on site & thus installation of the lift were delayed by three to four months’ time. 2. Due to sudden Spike in Rates & Shortage of Aluminium & Glass material which is required for windows. 3. Due to unavailability of material of door like door handles, Digital lock etc. and also expert labours to install the same were no…”
Source: Urban Life Ventures Aapli Society’s extension records on MahaRERA (P52100006249), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Urban Life Ventures Aapli Society
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100006249
- Status
- Lapsed (registration period ended)
- Builder
- Urban Life Ventures
- Location
- sahakar nagar, Pune · 411009
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- March 2020
- Latest completion date
- August 2022
- Delay so far
- 29 months
- Homes
- 77
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Urban Life Ventures Aapli Society, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A Building | 100% | 100% | 100% | 100% |
| B Building | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Urban Life Ventures Aapli Society every month.
Urban Life Ventures Aapli Society: buildings, flats and land, as filed on MahaRERA
- Buildings: A Building (14 floors) · B Building (13 floors)
- Land: 2,691 sq m (about 0.7 acres) · sanctioned built-up 4,738 sq m · recreational space 256 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Urban Life Ventures Aapli Society →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Urban Life Ventures Aapli Society: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Urban Life Ventures Aapli Society
What is the possession date of Urban Life Ventures Aapli Society?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Urban Life Ventures Aapli Society in sahakar nagar, Pune is 31 August 2022 — 29 months later than 31 March 2020, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Urban Life Ventures Aapli Society?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Urban Life Ventures Aapli Society's builder has filed on MahaRERA, the official one, is 31 August 2022, already 29 months later than the 31 March 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Urban Life Ventures Aapli Society extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Urban Life Ventures Aapli Society's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2021, giving the reason "2) Explanatory note regarding the state of development works in the project and reason for not completing the development works in the project within the period declared in the declaration submitted in Form ‘B’ at the time of making application for the registration of the project:- a) Sand is a critical raw material. River sand was banned by the government for environmental reasons, that created shortage and substitute material was not readily available. b) Elections were held in April 2019 (Central) and October 2019 (state) and migrant workers went on leave creating manpower shortage. c) D…"; to 31 August 2022, giving the reason "Explanatory note regarding the state of development works in the project and reasons for not completing the development works in the project within the period:- 1. Due to shortage of lift Material like chips, other small components etc. which delayed the delivery of material on site & thus installation of the lift were delayed by three to four months’ time. 2. Due to sudden Spike in Rates & Shortage of Aluminium & Glass material which is required for windows. 3. Due to unavailability of material of door like door handles, Digital lock etc. and also expert labours to install the same were no…".
What is the RERA number of Urban Life Ventures Aapli Society?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Urban Life Ventures Aapli Society in sahakar nagar, Pune is P52100006249.
Is Urban Life Ventures Aapli Society registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Urban Life Ventures Aapli Society is registered as P52100006249 and its status is "Lapsed (registration period ended)".
What is the construction status of Urban Life Ventures Aapli Society?
According to GharKundli's check of MahaRERA records (updated November 2026), Urban Life Ventures Aapli Society's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Urban Life Ventures Aapli Society have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Urban Life Ventures Aapli Society safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Urban Life Ventures Aapli Society is registered on MahaRERA as P52100006249, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 29 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Urban Life Ventures Aapli Society's possession date changes?
The latest dates are on Urban Life Ventures Aapli Society's MahaRERA page (P52100006249). GharKundli's Kundli Watch sends a free WhatsApp update on Urban Life Ventures Aapli Society every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Urban Life Ventures Aapli Society have?
According to GharKundli's check of MahaRERA records (updated November 2026), Urban Life Ventures Aapli Society has 2 buildings filed: A Building with 14 floors; B Building with 13 floors.
How big is the land of Urban Life Ventures Aapli Society?
According to GharKundli's check of MahaRERA records (updated November 2026), Urban Life Ventures Aapli Society stands on 2,691 sq m of land (about 0.7 acres), with 4,738 sq m of sanctioned built-up area and 256 sq m of recreational open space.
Where can I read reviews of Urban Life Ventures Aapli Society?
Google Maps has reviews of Urban Life Ventures Aapli Society written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Urban Life Ventures Aapli Society?
Urban Life Ventures Aapli Society by Urban Life Ventures is in sahakar nagar, Pune (pincode 411009), near Parvati, Gultekdi, Sahakarnagar, Maharashtra, and is registered on MahaRERA as P52100006249, per GharKundli's check of MahaRERA records.
How many homes are in Urban Life Ventures Aapli Society?
According to GharKundli's check of MahaRERA records (updated November 2026), Urban Life Ventures Aapli Society has 77 homes in 2 towers registered on MahaRERA.
When was Urban Life Ventures Aapli Society registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Urban Life Ventures Aapli Society was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Urban Life Ventures Aapli Society?
No court cases are listed for Urban Life Ventures Aapli Society on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Urban Life Ventures Aapli Society?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Urban Life Ventures.
Check it yourself on MahaRERA
- How to check the possession date of Urban Life Ventures Aapli Society
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Haveli
- SnehKunj
- QUE 101 PHASE I
- SIDDHI AURUM
- MADHUGHAT
- DYNAMIC SOLITAIRE – PHASE II
- CULLINAN
- ATS - THE CONDOMINIUMS
- ADI PRIME
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.