How the possession date of NISHIGANDH has moved

  1. 26 January 2018

    Completion date given when the project was registered

  2. 26 January 2019

    Extended at the builder's request (MahaRERA application EXT52100000843)

    Reason the builder gave MahaRERA:
    “DEAR SIR, I am PRASHANT CHANDRAKANT KHEDEKAR . We are inform you. nishigandha is a four floor building plan .that has permission for three floor building plan.we got the permission of fourth floor in may 2018 .due to the delay in the fourth…” Read the full reason“DEAR SIR, I am PRASHANT CHANDRAKANT KHEDEKAR . We are inform you. nishigandha is a four floor building plan .that has permission for three floor building plan.we got the permission of fourth floor in may 2018 .due to the delay in the fourth floor permission of the corporation side .we want to increase the extended date of project.please humble request to extend the duration of project date.”
  3. 15 April 2019

    Extended at the builder's request (MahaRERA application EXT52100012509)

    Reason the builder gave MahaRERA: “Residential Project is not completed within time”

Source: NISHIGANDH’s extension records on MahaRERA (P52100004986), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NISHIGANDH

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100004986
Status
Completed
Builder
PRASHANT CHANDRAKANT KHEDEKAR
Location
gondhale nagar, Pune · 411015
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
January 2018
Latest completion date
April 2019
Delay so far
15 months
Homes
16
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of NISHIGANDH, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NISHIGANDH100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NISHIGANDH every month.

NISHIGANDH: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of NISHIGANDH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NISHIGANDH: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NISHIGANDH

What is the possession date of NISHIGANDH?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for NISHIGANDH in gondhale nagar, Pune is 15 April 2019 — 15 months later than 26 January 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for NISHIGANDH?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NISHIGANDH's builder has filed on MahaRERA, the official one, is 15 April 2019, already 15 months later than the 26 January 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NISHIGANDH extended?

According to GharKundli's check of MahaRERA records (updated November 2026), NISHIGANDH's builder applied to MahaRERA to extend the completion date 2 times: to 26 January 2019, giving the reason "DEAR SIR, I am PRASHANT CHANDRAKANT KHEDEKAR . We are inform you. nishigandha is a four floor building plan .that has permission for three floor building plan.we got the permission of fourth floor in may 2018 .due to the delay in the fourth floor permission of the corporation side .we want to increase the extended date of project.please humble request to extend the duration of project date."; to 15 April 2019, giving the reason "Residential Project is not completed within time".

What is the RERA number of NISHIGANDH?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of NISHIGANDH in gondhale nagar, Pune is P52100004986.

Is NISHIGANDH registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NISHIGANDH is registered as P52100004986 and its status is "Completed".

What is the construction status of NISHIGANDH?

According to GharKundli's check of MahaRERA records (updated November 2026), NISHIGANDH's status on MahaRERA is "Completed". As filed by the builder, slab work on NISHIGANDH is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does NISHIGANDH have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is NISHIGANDH safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), NISHIGANDH is registered on MahaRERA as P52100004986, its MahaRERA status is "Completed", its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NISHIGANDH's possession date changes?

The latest dates are on NISHIGANDH's MahaRERA page (P52100004986). GharKundli's Kundli Watch sends a free WhatsApp update on NISHIGANDH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NISHIGANDH have?

According to GharKundli's check of MahaRERA records (updated November 2026), NISHIGANDH has one building filed: NISHIGANDH with 6 floors.

How big is the land of NISHIGANDH?

According to GharKundli's check of MahaRERA records (updated November 2026), NISHIGANDH stands on 478 sq m of land (about 0.1 acres), with 522 sq m of sanctioned built-up area.

Where can I read reviews of NISHIGANDH?

Google Maps has reviews of NISHIGANDH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NISHIGANDH?

NISHIGANDH by PRASHANT CHANDRAKANT KHEDEKAR is in gondhale nagar, Pune (pincode 411015), near Dhanori, Shivaji Nagar, Maharashtra, and is registered on MahaRERA as P52100004986, per GharKundli's check of MahaRERA records.

How many homes are in NISHIGANDH?

According to GharKundli's check of MahaRERA records (updated November 2026), NISHIGANDH has 16 homes in 1 tower registered on MahaRERA.

When was NISHIGANDH registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), NISHIGANDH was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on NISHIGANDH?

No court cases are listed for NISHIGANDH on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of NISHIGANDH?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PRASHANT CHANDRAKANT KHEDEKAR.

Other projects in Haveli