by SAISTHAPATYA BUILDWELL · Narayangaon, Pune 410504Also near ParvatiRegistered on MahaRERA as “SAIKAMAL”
What’s in the report? →Possession date of Saisthapatya Saikamal (MahaRERA P52100004185): 31 July 2019, moved from 31 July 2018 (12 months later), and it has already passed. It has 88 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100004185. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100004185, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2019) has passed.
What do you want to know about Saisthapatya Saikamal?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Saisthapatya Saikamal has moved
31 July 2018
Completion date given when the project was registered
31 July 2019
Extended at the builder's request (MahaRERA application EXT52100000530)
Reason the builder gave MahaRERA: “The prime reason for non completion is the scarcity of potential buyers in the market.”
Source: Saisthapatya Saikamal’s extension records on MahaRERA (P52100004185), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Saisthapatya Saikamal
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100004185
- Status
- Lapsed (registration period ended)
- Builder
- SAISTHAPATYA BUILDWELL
- Location
- Narayangaon, Pune · 410504
- Project type
- Residential / Group Housing
- Registered on
- 8 Aug 2017
- Completion date at registration
- July 2018
- Latest completion date
- July 2019
- Delay so far
- 12 months
- Homes
- 88
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Saisthapatya Saikamal, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| saikamal wing A | 0% | 100% | 50% | 0% |
| saikamal wing B | 0% | 100% | 50% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Saisthapatya Saikamal every 1–2 months.
Saisthapatya Saikamal: buildings, flats and land, as filed on MahaRERA
- Buildings: saikamal wing A (5 floors) · saikamal wing B (5 floors)
- Land: 3,600 sq m (about 0.9 acres) · sanctioned built-up 3,543 sq m · recreational space 331 sq m
- Boundaries filed include: Pune Nashik National Highway 60
- Land, as filed: 312/3 312/4
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Saisthapatya Saikamal →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Saisthapatya Saikamal: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Saisthapatya Saikamal
What is the possession date of Saisthapatya Saikamal?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Saisthapatya Saikamal in Narayangaon, Pune is 31 July 2019 — 12 months later than 31 July 2018, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Saisthapatya Saikamal?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Saisthapatya Saikamal's builder has filed on MahaRERA, the official one, is 31 July 2019, already 12 months later than the 31 July 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Saisthapatya Saikamal extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Saisthapatya Saikamal's builder applied to MahaRERA to extend the completion date once: to 31 July 2019, giving the reason "The prime reason for non completion is the scarcity of potential buyers in the market.".
What is the RERA number of Saisthapatya Saikamal?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Saisthapatya Saikamal in Narayangaon, Pune is P52100004185.
Is Saisthapatya Saikamal registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Saisthapatya Saikamal is registered as P52100004185 and its status is "Lapsed (registration period ended)".
What is the current construction status of Saisthapatya Saikamal? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Saisthapatya Saikamal's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Saisthapatya Saikamal have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Saisthapatya Saikamal safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Saisthapatya Saikamal is registered on MahaRERA as P52100004185, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Saisthapatya Saikamal?
Saisthapatya Saikamal isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Saisthapatya Saikamal?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Saisthapatya Saikamal: gharkundli.com/tools/property-cost-calculator
Has Saisthapatya Saikamal received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Saisthapatya Saikamal isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2019 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Saisthapatya Saikamal?
According to GharKundli's check of MahaRERA records (updated November 2026), Saisthapatya Saikamal's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2019) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Saisthapatya Saikamal uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Saisthapatya Saikamal was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Saisthapatya Saikamal's possession date changes?
The latest dates are on Saisthapatya Saikamal's MahaRERA page (P52100004185). GharKundli's Kundli Watch sends a free WhatsApp update on Saisthapatya Saikamal every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Saisthapatya Saikamal have?
According to GharKundli's check of MahaRERA records (updated November 2026), Saisthapatya Saikamal has 2 buildings filed: saikamal wing A with 5 floors; saikamal wing B with 5 floors.
How big is the land of Saisthapatya Saikamal?
According to GharKundli's check of MahaRERA records (updated November 2026), Saisthapatya Saikamal stands on 3,600 sq m of land (about 0.9 acres), with 3,543 sq m of sanctioned built-up area and 331 sq m of recreational open space.
What are the reviews of Saisthapatya Saikamal?
Google Maps has reviews of Saisthapatya Saikamal written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Saisthapatya Saikamal?
Saisthapatya Saikamal by SAISTHAPATYA BUILDWELL is in Narayangaon, Pune, pincode 410504 (near Parvati), Maharashtra, and is registered on MahaRERA as P52100004185, per GharKundli's check of MahaRERA records. Its boundaries filed there include Pune Nashik National Highway 60. Its land is filed as 312/3 312/4. GharKundli lists all 54 MahaRERA projects in Narayangaon (410504).
How many flats are in Saisthapatya Saikamal?
According to GharKundli's check of MahaRERA records (updated November 2026), Saisthapatya Saikamal has 88 homes in 2 towers registered on MahaRERA.
When was Saisthapatya Saikamal registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Saisthapatya Saikamal was registered on MahaRERA on 8 August 2017. GharKundli did not find a title report on the land on file there.
Does Saisthapatya Saikamal have any legal issues or court cases?
No court cases are listed for Saisthapatya Saikamal on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Saisthapatya Saikamal?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAISTHAPATYA BUILDWELL.
Check it yourself on MahaRERA
- How to check the possession date of Saisthapatya Saikamal
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Narayangaon (410504)
- Vizion Bliss
- Crystal Tower Phase 2
- Shree Muktai Heights
- Florina Phase II
- Shivkunj
- Sai Savli
- Divyata Park
- Rajlaxmi Prestige
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.