RISHABH HEIGHTS
by NANDISH CITY INFRATECH & DEVELOPERS PRIVATE LIMITED · Khotachiwadi, Palghar
Possession date of RISHABH HEIGHTS: 31 December 2027, moved from 30 December 2021 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000011841, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about RISHABH HEIGHTS?
How the possession date of RISHABH HEIGHTS has moved
30 December 2021
Completion date given when the project was registered
31 December 2023
Extended at the builder's request (MahaRERA application EXT99000016521)
Reason the builder gave MahaRERA: “COVID RESTRICTIONS”
31 December 2027
Extended at the builder's request (MahaRERA application EA20082622288)
Reason the builder gave MahaRERA:
“a) The project could not be completed within the originally approved timeline primarily due to a delay in arranging the required funds for carrying out the project activities. The financial constraints resulted in a delay in execution of ce…” Read the full reason
“a) The project could not be completed within the originally approved timeline primarily due to a delay in arranging the required funds for carrying out the project activities. The financial constraints resulted in a delay in execution of certain activities and consequentially affected the overall project completion schedule. b) The Promoter has subsequently arranged the requisite funds and completed the project work. At present, the project is substantially/fully completed and is at the stage of obtaining the requisite statutory clearances and approvals. c) The Promoter is in the process of…”
Source: RISHABH HEIGHTS’s extension records on MahaRERA (P99000011841), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RISHABH HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000011841
- Status
- Registered and active
- Builder
- NANDISH CITY INFRATECH & DEVELOPERS PRIVATE LIMITED
- Location
- Khotachiwadi, Palghar · 401303
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- December 2027
- Delay so far
- 72 months
- Homes
- 47
- Sold or booked
- 47%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of RISHABH HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RISHABH HEIGHTS | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- RISHABH HEIGHTS: covers 14 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RISHABH HEIGHTS every month.
RISHABH HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: RISHABH HEIGHTS (14 floors, 47 units)
- Car parking: 4 covered
- Land: 663 sq m (about 0.2 acres) · sanctioned built-up 2,734 sq m · recreational space 844 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of RISHABH HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RISHABH HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RISHABH HEIGHTS
What is the possession date of RISHABH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RISHABH HEIGHTS in Khotachiwadi, Palghar is 31 December 2027 — 72 months later than 30 December 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for RISHABH HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RISHABH HEIGHTS's builder has filed on MahaRERA, the official one, is 31 December 2027, already 72 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RISHABH HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), RISHABH HEIGHTS's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2023, giving the reason "COVID RESTRICTIONS"; to 31 December 2027, giving the reason "a) The project could not be completed within the originally approved timeline primarily due to a delay in arranging the required funds for carrying out the project activities. The financial constraints resulted in a delay in execution of certain activities and consequentially affected the overall project completion schedule. b) The Promoter has subsequently arranged the requisite funds and completed the project work. At present, the project is substantially/fully completed and is at the stage of obtaining the requisite statutory clearances and approvals. c) The Promoter is in the process of…".
What is the RERA number of RISHABH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RISHABH HEIGHTS in Khotachiwadi, Palghar is P99000011841.
Is RISHABH HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RISHABH HEIGHTS is registered as P99000011841 and its status is "Registered and active".
What is the construction status of RISHABH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), RISHABH HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RISHABH HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does RISHABH HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is RISHABH HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), RISHABH HEIGHTS is registered on MahaRERA as P99000011841, its completion date has moved 72 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RISHABH HEIGHTS's possession date changes?
The latest dates are on RISHABH HEIGHTS's MahaRERA page (P99000011841). GharKundli's Kundli Watch sends a free WhatsApp update on RISHABH HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RISHABH HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), RISHABH HEIGHTS has one building filed: RISHABH HEIGHTS with 14 floors and 47 units.
How much parking does RISHABH HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 4 covered car parking spaces for RISHABH HEIGHTS.
How big is the land of RISHABH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), RISHABH HEIGHTS stands on 663 sq m of land (about 0.2 acres), with 2,734 sq m of sanctioned built-up area and 844 sq m of recreational open space.
Where can I read reviews of RISHABH HEIGHTS?
Google Maps has reviews of RISHABH HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RISHABH HEIGHTS?
RISHABH HEIGHTS by NANDISH CITY INFRATECH & DEVELOPERS PRIVATE LIMITED is in Khotachiwadi, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000011841, per GharKundli's check of MahaRERA records.
How many homes are in RISHABH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), RISHABH HEIGHTS has 47 homes in 1 tower registered on MahaRERA, and 47% of them are sold or booked.
When was RISHABH HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RISHABH HEIGHTS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RISHABH HEIGHTS?
No court cases are listed for RISHABH HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of RISHABH HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NANDISH CITY INFRATECH & DEVELOPERS PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of RISHABH HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in Vasai
- VIMALNATH Building no-2
- STAR LEGACY
- Acciano Bianca
- DHANANJAY ICON
- REALTECH VALENCIA
- COMFORT AARADHYA
- GULMOHAR HERITAGE BUILDING NO 3 WING E PHASE I
- SHIVNERI
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.