Palmtree Palm World One

by PALMTREE DEVELOPMENTS PVT. LTD. · Near Eon It Park, Pune 411014Also near Kharadi, Wagholi, Pune CampRegistered on MahaRERA as “PALM WORLD ONE”

What’s in the report? →

Possession date of Palmtree Palm World One (MahaRERA P52100012101): 31 July 2022, moved from 31 December 2018 (43 months later), and it has already passed. It has 66 homes, 96% sold or booked. 57 complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100012101. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100012101, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (July 2022) has passed.

What do you want to know about Palmtree Palm World One?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Palmtree Palm World One has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT52100000958)

    Reason the builder gave MahaRERA:
    “Dear Sir / Madam, We, Palmtree Developments Pvt Ltd are developing residential project, PALM WORLD ONE in Survey No 63/2& 63/3, Kharadi, Haveli, Pune 411014 and we were due to complete the project on 31/12/18. Unfortunately, the project has…” Read the full reason“Dear Sir / Madam, We, Palmtree Developments Pvt Ltd are developing residential project, PALM WORLD ONE in Survey No 63/2& 63/3, Kharadi, Haveli, Pune 411014 and we were due to complete the project on 31/12/18. Unfortunately, the project has to be stalled / stopped due to insufficient FSI sanctions to complete the project. The subject project is in joint venture with landowners i.e. Bhujbal Brothers Constructions Company & Mahaveer Properties through registered Joint Development Agreement document no 8227- 2014 dated 10th October 2014. In the mentioned agreement, the landowners have committe…”
  3. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT52100003763)

    Reason the builder gave MahaRERA:
    “Due to non corporation from the landowners, in December 2018 we decided to use our powers handed through power of Attorney to handover the Amenity space to Pune Mucipal Corporation, liaison with the Land Development and other relevant autho…” Read the full reason“Due to non corporation from the landowners, in December 2018 we decided to use our powers handed through power of Attorney to handover the Amenity space to Pune Mucipal Corporation, liaison with the Land Development and other relevant authorities and submit all the documentation required by Pune Municipal Corporation for the remembering FSI approvals. As of today we completed the full RCC till the 11th floor along with the block work and also have various agencies simultaneously working i.e. waterproofing, electrical, plumbing, gypsum, filing etc. at the site. We currently have around 40 sk…”
  4. 31 July 2021

    Extended at the builder's request (MahaRERA application EXT52100006317)

    Reason the builder gave MahaRERA: “Construction work is stalled due to COVID pandamic. Lockdown and non availability of labour force has made it impossible for us to complete the work before the due date.”
  5. 31 July 2022

    Extended at the builder's request (MahaRERA application EXT52100011591)

    Reason the builder gave MahaRERA: “due to covid”

Source: Palmtree Palm World One’s extension records on MahaRERA (P52100012101), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Palmtree Palm World One

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 57 complaints, and how it ended
  • Construction pace against the July 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100012101
Status
Lapsed (registration period ended)
Builder
PALMTREE DEVELOPMENTS PVT. LTD.
Location
Near Eon It Park, Pune · 411014
Project type
Residential / Group Housing
Registered on
1 Sep 2017
Completion date at registration
December 2018
Latest completion date
July 2022
Delay so far
43 months
Homes
66
Sold or booked
96%
Towers
1
Complaints on MahaRERA
57
Court cases listed
0
Appeals at the tribunal
58
Title report on file
Not found

Construction progress of Palmtree Palm World One, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
PALM WORLD ONE100%75%60%0%

Commencement certificate (CC), as filed on MahaRERA

  • PALM WORLD ONE: covers 14 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Palmtree Palm World One every 1–2 months.

Palmtree Palm World One: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Palmtree Palm World One →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Palmtree Palm World One: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Palmtree Palm World One

What is the possession date of Palmtree Palm World One?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Palmtree Palm World One in Near Eon It Park, Pune is 31 July 2022 — 43 months later than 31 December 2018, the date given at registration. That date has already passed.

The date has already moved 43 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Palmtree Palm World One?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Palmtree Palm World One's builder has filed on MahaRERA, the official one, is 31 July 2022, already 43 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Palmtree Palm World One extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Palmtree Palm World One's builder applied to MahaRERA to extend the completion date 4 times: to 30 April 2020, giving the reason "Dear Sir / Madam, We, Palmtree Developments Pvt Ltd are developing residential project, PALM WORLD ONE in Survey No 63/2& 63/3, Kharadi, Haveli, Pune 411014 and we were due to complete the project on 31/12/18. Unfortunately, the project has to be stalled / stopped due to insufficient FSI sanctions to complete the project. The subject project is in joint venture with landowners i.e. Bhujbal Brothers Constructions Company & Mahaveer Properties through registered Joint Development Agreement document no 8227- 2014 dated 10th October 2014. In the mentioned agreement, the landowners have committe…"; to 30 April 2020, giving the reason "Due to non corporation from the landowners, in December 2018 we decided to use our powers handed through power of Attorney to handover the Amenity space to Pune Mucipal Corporation, liaison with the Land Development and other relevant authorities and submit all the documentation required by Pune Municipal Corporation for the remembering FSI approvals. As of today we completed the full RCC till the 11th floor along with the block work and also have various agencies simultaneously working i.e. waterproofing, electrical, plumbing, gypsum, filing etc. at the site. We currently have around 40 sk…"; to 31 July 2021, giving the reason "Construction work is stalled due to COVID pandamic. Lockdown and non availability of labour force has made it impossible for us to complete the work before the due date."; to 31 July 2022, giving the reason "due to covid".

What is the RERA number of Palmtree Palm World One?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Palmtree Palm World One in Near Eon It Park, Pune is P52100012101.

Is Palmtree Palm World One registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Palmtree Palm World One is registered as P52100012101 and its status is "Lapsed (registration period ended)".

What is the current construction status of Palmtree Palm World One? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Palmtree Palm World One's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on PALM WORLD ONE is 75% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does Palmtree Palm World One have complaints on MahaRERA?

57 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

57 complaints are filed on this project. Know what went wrong before you pay a token. See how each complaint ended →

Is Palmtree Palm World One safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Palmtree Palm World One is registered on MahaRERA as P52100012101, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 43 months since registration and 57 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Palmtree Palm World One?

Palmtree Palm World One isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Palmtree Palm World One?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Palmtree Palm World One: gharkundli.com/tools/property-cost-calculator

Has Palmtree Palm World One received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Palmtree Palm World One isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Palmtree Palm World One?

According to GharKundli's check of MahaRERA records (updated November 2026), Palmtree Palm World One's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Palmtree Palm World One uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Palmtree Palm World One was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Palmtree Palm World One's possession date changes?

The latest dates are on Palmtree Palm World One's MahaRERA page (P52100012101). GharKundli's Kundli Watch sends a free WhatsApp update on Palmtree Palm World One every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Palmtree Palm World One have?

According to GharKundli's check of MahaRERA records (updated November 2026), Palmtree Palm World One has one building filed: PALM WORLD ONE with 14 floors and 66 units.

How big is the land of Palmtree Palm World One?

According to GharKundli's check of MahaRERA records (updated November 2026), Palmtree Palm World One stands on 4,151 sq m of land (about 1.0 acres), with 3,022 sq m of sanctioned built-up area and 415 sq m of recreational open space.

What are the reviews of Palmtree Palm World One?

Google Maps has reviews of Palmtree Palm World One written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 57 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Palmtree Palm World One?

Palmtree Palm World One by PALMTREE DEVELOPMENTS PVT. LTD. is in Near Eon It Park, Pune, pincode 411014 (near Kharadi, Wagholi, Pune Camp), Maharashtra, and is registered on MahaRERA as P52100012101, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO. 63/2, 63/3. GharKundli lists all 323 MahaRERA projects in Kharadi (411014).

How many flats are in Palmtree Palm World One, and how many are sold?

According to GharKundli's check of MahaRERA records (updated November 2026), Palmtree Palm World One has 66 homes in 1 tower registered on MahaRERA, and 96% of them are sold or booked.

When was Palmtree Palm World One registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Palmtree Palm World One was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Does Palmtree Palm World One have any legal issues or court cases?

No court cases are listed for Palmtree Palm World One on MahaRERA, and 58 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Palmtree Palm World One?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PALMTREE DEVELOPMENTS PVT. LTD..