Jai Malhar
by JAI MALHAR BUILDERS · Vasai, Palghar 401201
What’s in the report? →Possession date of Jai Malhar (MahaRERA P99000007443): 30 June 2023, moved from 30 June 2019 (48 months later), and it has already passed. It has 38 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000007443. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P99000007443, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2023) has passed.
What do you want to know about Jai Malhar?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Jai Malhar has moved
30 June 2019
Completion date given when the project was registered
29 June 2020
Extended at the builder's request (MahaRERA application EXT99000002436)
Reason the builder gave MahaRERA:
“. The project got delayed because of the following reasons: 1. Delay in procurement of Building construction material ( Sand – reti ) due to Government restrictions/laws. 2. Shortfall in supply of Cement/concrete/bricks in our area at numbe…” Read the full reason
“. The project got delayed because of the following reasons: 1. Delay in procurement of Building construction material ( Sand – reti ) due to Government restrictions/laws. 2. Shortfall in supply of Cement/concrete/bricks in our area at number of occasions during the construction period. 3. Delay in granting of permissions by Local authority resulting in stoppage of construction at number of occasions. 4. Change in Government rules ( safety norms- Fire ) creating many hurdles such as taking approvals from respective authorities due to lack of clarity of new laws , changes to be made in constr…”31 December 2022
Extended at the builder's request (MahaRERA application EXT99000011007)
Reason the builder gave MahaRERA:
“DUE TO COVID-19 PENDAMIC & VARIOUS RESTRICTIONS IMPOSED BY THE STATE AND CENTRAL COVERNMENT ON MOVEMENT OF PEOPLE AND BUSINESS ACTIVITIES, CONSTRUCTION WORK HAD STAYED SLOW. IT CAN BE SEEN FROM THE DOCUMENTS UPLOADED THAT THE PROJECT IS ALM…” Read the full reason
“DUE TO COVID-19 PENDAMIC & VARIOUS RESTRICTIONS IMPOSED BY THE STATE AND CENTRAL COVERNMENT ON MOVEMENT OF PEOPLE AND BUSINESS ACTIVITIES, CONSTRUCTION WORK HAD STAYED SLOW. IT CAN BE SEEN FROM THE DOCUMENTS UPLOADED THAT THE PROJECT IS ALMOST COMPLETE AND IS IN ITS ENDING STAGE. WE REQUEST YOU TO GRANT US AN EXTENSION TILL 31/12/2022 TO HANDOVER FLATS TO ALL BUYERS WITHOUT ANY DIFFICULTY. PART OC HAS ALREADY BEEN RECIVED FOR THE PROJECT AND THE SAME HAS ALSO BEEN UPLOADED ON THE WEBISTE. WE HAVE APPROVAL OF MORE THAN 50% OF THE ALLOTTEES .”30 June 2023
Revised completion date on MahaRERA
Source: Jai Malhar’s extension records on MahaRERA (P99000007443), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Jai Malhar
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000007443
- Status
- Lapsed (registration period ended)
- Builder
- JAI MALHAR BUILDERS
- Location
- Vasai, Palghar · 401201
- Project type
- Others
- Registered on
- 17 Aug 2017
- Completion date at registration
- June 2019
- Latest completion date
- June 2023
- Delay so far
- 48 months
- Homes
- 38
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Jai Malhar, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| JAI MALHAR | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jai Malhar every 1–2 months.
Jai Malhar: buildings, flats and land, as filed on MahaRERA
- Buildings: JAI MALHAR (7 floors)
- Land: 1,263 sq m (about 0.3 acres) · sanctioned built-up 1,134 sq m · recreational space 115 sq m
- Boundaries filed include: 90 MT MUNICIPAL ROAD
- Land, as filed: CTS S NO 1666
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Jai Malhar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Jai Malhar: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Jai Malhar
What is the possession date of Jai Malhar?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Jai Malhar in Vasai, Palghar is 30 June 2023 — 48 months later than 30 June 2019, the date given at registration. That date has already passed.
The date has already moved 48 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Jai Malhar?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Jai Malhar's builder has filed on MahaRERA, the official one, is 30 June 2023, already 48 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Jai Malhar extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Jai Malhar's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2020, giving the reason ". The project got delayed because of the following reasons: 1. Delay in procurement of Building construction material ( Sand – reti ) due to Government restrictions/laws. 2. Shortfall in supply of Cement/concrete/bricks in our area at number of occasions during the construction period. 3. Delay in granting of permissions by Local authority resulting in stoppage of construction at number of occasions. 4. Change in Government rules ( safety norms- Fire ) creating many hurdles such as taking approvals from respective authorities due to lack of clarity of new laws , changes to be made in constr…"; to 31 December 2022, giving the reason "DUE TO COVID-19 PENDAMIC & VARIOUS RESTRICTIONS IMPOSED BY THE STATE AND CENTRAL COVERNMENT ON MOVEMENT OF PEOPLE AND BUSINESS ACTIVITIES, CONSTRUCTION WORK HAD STAYED SLOW. IT CAN BE SEEN FROM THE DOCUMENTS UPLOADED THAT THE PROJECT IS ALMOST COMPLETE AND IS IN ITS ENDING STAGE. WE REQUEST YOU TO GRANT US AN EXTENSION TILL 31/12/2022 TO HANDOVER FLATS TO ALL BUYERS WITHOUT ANY DIFFICULTY. PART OC HAS ALREADY BEEN RECIVED FOR THE PROJECT AND THE SAME HAS ALSO BEEN UPLOADED ON THE WEBISTE. WE HAVE APPROVAL OF MORE THAN 50% OF THE ALLOTTEES .".
What is the RERA number of Jai Malhar?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Jai Malhar in Vasai, Palghar is P99000007443.
Is Jai Malhar registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Jai Malhar is registered as P99000007443 and its status is "Lapsed (registration period ended)".
What is the current construction status of Jai Malhar? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Jai Malhar's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on JAI MALHAR is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Jai Malhar have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Jai Malhar safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Jai Malhar is registered on MahaRERA as P99000007443, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Jai Malhar?
Jai Malhar isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Jai Malhar?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Jai Malhar: gharkundli.com/tools/property-cost-calculator
Has Jai Malhar received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Jai Malhar isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2023 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Jai Malhar?
According to GharKundli's check of MahaRERA records (updated November 2026), Jai Malhar's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2023) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Jai Malhar uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Jai Malhar was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Jai Malhar's possession date changes?
The latest dates are on Jai Malhar's MahaRERA page (P99000007443). GharKundli's Kundli Watch sends a free WhatsApp update on Jai Malhar every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Jai Malhar have?
According to GharKundli's check of MahaRERA records (updated November 2026), Jai Malhar has one building filed: JAI MALHAR with 7 floors.
How big is the land of Jai Malhar?
According to GharKundli's check of MahaRERA records (updated November 2026), Jai Malhar stands on 1,263 sq m of land (about 0.3 acres), with 1,134 sq m of sanctioned built-up area and 115 sq m of recreational open space.
What are the reviews of Jai Malhar?
Google Maps has reviews of Jai Malhar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Jai Malhar?
Jai Malhar by JAI MALHAR BUILDERS is in Vasai, Palghar, pincode 401201, Maharashtra, and is registered on MahaRERA as P99000007443, per GharKundli's check of MahaRERA records. Its boundaries filed there include 90 MT MUNICIPAL ROAD. Its land is filed as CTS S NO 1666. GharKundli lists all 95 MahaRERA projects in Bassein (401201).
How many flats are in Jai Malhar?
According to GharKundli's check of MahaRERA records (updated November 2026), Jai Malhar has 38 homes in 1 tower registered on MahaRERA.
When was Jai Malhar registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Jai Malhar was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Does Jai Malhar have any legal issues or court cases?
No court cases are listed for Jai Malhar on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Jai Malhar?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is JAI MALHAR BUILDERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Jai Malhar
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Bassein (401201)
- Sereno
- Altura Umele
- Patil Arcade
- Yashwant County
- Aai Chandika Hills
- Sanskruti Emerald
- Vishwakarma Heights
- Deep Sky F Wing
Other projects by JAI MALHAR BUILDERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.