Gurukrupa Aster

by GURUKRUP DEVELOPERS · Wadgaon Sheri, Pune 411014Also near Kharadi, Vadgaonsheri, Dunkirk lines

What’s in the report? →

Possession date of Gurukrupa Aster (MahaRERA P52100006302): 30 December 2021, and it has already passed. It has 107 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100006302. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100006302, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2021) has passed.

What do you want to know about Gurukrupa Aster?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Gurukrupa Aster

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100006302
Status
Lapsed (registration period ended)
Builder
GURUKRUP DEVELOPERS
Location
Wadgaon Sheri, Pune · 411014
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
December 2021
Latest completion date
December 2021
Homes
107
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Gurukrupa Aster, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GURUKRUPA ASTER100%95%95%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gurukrupa Aster every 1–2 months.

Gurukrupa Aster: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Gurukrupa Aster →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Gurukrupa Aster: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Gurukrupa Aster

What is the possession date of Gurukrupa Aster?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Gurukrupa Aster in Wadgaon Sheri, Pune is 30 December 2021. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Gurukrupa Aster?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Gurukrupa Aster's builder has filed on MahaRERA, the official one, is 30 December 2021, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Gurukrupa Aster?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Gurukrupa Aster in Wadgaon Sheri, Pune is P52100006302.

Is Gurukrupa Aster registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Gurukrupa Aster is registered as P52100006302 and its status is "Lapsed (registration period ended)".

What is the current construction status of Gurukrupa Aster? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Gurukrupa Aster's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on GURUKRUPA ASTER is 95% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does Gurukrupa Aster have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Gurukrupa Aster safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Gurukrupa Aster is registered on MahaRERA as P52100006302, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Gurukrupa Aster?

Gurukrupa Aster isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Gurukrupa Aster?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Gurukrupa Aster: gharkundli.com/tools/property-cost-calculator

Has Gurukrupa Aster received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Gurukrupa Aster isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Gurukrupa Aster?

According to GharKundli's check of MahaRERA records (updated November 2026), Gurukrupa Aster's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Gurukrupa Aster uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Gurukrupa Aster was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Gurukrupa Aster's possession date changes?

The latest dates are on Gurukrupa Aster's MahaRERA page (P52100006302). GharKundli's Kundli Watch sends a free WhatsApp update on Gurukrupa Aster every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Gurukrupa Aster have?

According to GharKundli's check of MahaRERA records (updated November 2026), Gurukrupa Aster has one building filed: GURUKRUPA ASTER with 13 floors.

How big is the land of Gurukrupa Aster?

According to GharKundli's check of MahaRERA records (updated November 2026), Gurukrupa Aster stands on 9,621 sq m of land (about 2.4 acres), with 7,988 sq m of sanctioned built-up area and 962 sq m of recreational open space.

What are the reviews of Gurukrupa Aster?

Google Maps has reviews of Gurukrupa Aster written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Gurukrupa Aster?

Gurukrupa Aster by GURUKRUP DEVELOPERS is in Wadgaon Sheri, Pune, pincode 411014 (near Kharadi, Vadgaonsheri, Dunkirk lines), Maharashtra, and is registered on MahaRERA as P52100006302, per GharKundli's check of MahaRERA records. Its land is filed as 50 6 2 50 8 50 9 50 6. GharKundli lists all 323 MahaRERA projects in Kharadi (411014).

How many flats are in Gurukrupa Aster?

According to GharKundli's check of MahaRERA records (updated November 2026), Gurukrupa Aster has 107 homes in 1 tower registered on MahaRERA.

When was Gurukrupa Aster registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Gurukrupa Aster was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Does Gurukrupa Aster have any legal issues or court cases?

No court cases are listed for Gurukrupa Aster on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Gurukrupa Aster?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GURUKRUP DEVELOPERS.

Other projects in Pune City

All 323 projects in Kharadi (411014) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.