OLIVE BLISS
by KOHINOOR DEVELOPERS · PuneAlso near Swargate, Kasba Peth, Parvati
Possession date of OLIVE BLISS: 31 December 2023, moved from 30 April 2019 (56 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100014682. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2023) has passed.
What do you want to know about OLIVE BLISS?
How the possession date of OLIVE BLISS has moved
30 April 2019
Completion date given when the project was registered
30 June 2021
Extended at the builder's request (MahaRERA application EXT52100008885)
Reason the builder gave MahaRERA: “NO SINGLE BOOKING YET RECEIVED. FUNDS INSUFFICIENT FOR COMPLETION”
31 December 2022
Extended at the builder's request (MahaRERA application EXT52100011279)
Reason the builder gave MahaRERA: “Non availability of construction raw material and labour due to Covid 19 pandemic”
31 December 2023
Extended at the builder's request (MahaRERA application EXT52100013643)
Reason the builder gave MahaRERA: “Non availability of the raw material and labor due to Covid 19 pandemic.”
Source: OLIVE BLISS’s extension records on MahaRERA (P52100014682), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on OLIVE BLISS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100014682
- Status
- Lapsed (registration period ended)
- Builder
- KOHINOOR DEVELOPERS
- Location
- Pune · 411001
- Project type
- Residential / Group Housing
- Registered on
- 20 Dec 2017
- Completion date at registration
- April 2019
- Latest completion date
- December 2023
- Delay so far
- 56 months
- Homes
- 17
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of OLIVE BLISS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| OLIVE BLISS | 100% | 100% | 100% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on OLIVE BLISS every month.
OLIVE BLISS: buildings, flats and land, as filed on MahaRERA
- Buildings: OLIVE BLISS (6 floors)
- Land: 766 sq m (about 0.2 acres) · sanctioned built-up 1,120 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of OLIVE BLISS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
OLIVE BLISS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about OLIVE BLISS
What is the possession date of OLIVE BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for OLIVE BLISS in Pune is 31 December 2023 — 56 months later than 30 April 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for OLIVE BLISS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date OLIVE BLISS's builder has filed on MahaRERA, the official one, is 31 December 2023, already 56 months later than the 30 April 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of OLIVE BLISS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), OLIVE BLISS's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2021, giving the reason "NO SINGLE BOOKING YET RECEIVED. FUNDS INSUFFICIENT FOR COMPLETION"; to 31 December 2022, giving the reason "Non availability of construction raw material and labour due to Covid 19 pandemic"; to 31 December 2023, giving the reason "Non availability of the raw material and labor due to Covid 19 pandemic.".
What is the RERA number of OLIVE BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of OLIVE BLISS in Pune is P52100014682.
Is OLIVE BLISS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OLIVE BLISS is registered as P52100014682 and its status is "Lapsed (registration period ended)".
What is the construction status of OLIVE BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), OLIVE BLISS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on OLIVE BLISS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does OLIVE BLISS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is OLIVE BLISS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), OLIVE BLISS is registered on MahaRERA as P52100014682, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 56 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if OLIVE BLISS's possession date changes?
The latest dates are on OLIVE BLISS's MahaRERA page (P52100014682). GharKundli's Kundli Watch sends a free WhatsApp update on OLIVE BLISS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does OLIVE BLISS have?
According to GharKundli's check of MahaRERA records (updated November 2026), OLIVE BLISS has one building filed: OLIVE BLISS with 6 floors.
How big is the land of OLIVE BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), OLIVE BLISS stands on 766 sq m of land (about 0.2 acres), with 1,120 sq m of sanctioned built-up area.
Where can I read reviews of OLIVE BLISS?
Google Maps has reviews of OLIVE BLISS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is OLIVE BLISS?
OLIVE BLISS by KOHINOOR DEVELOPERS is in Pune (pincode 411001), near Swargate, Kasba Peth, Parvati, Maharashtra, and is registered on MahaRERA as P52100014682, per GharKundli's check of MahaRERA records.
How many homes are in OLIVE BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), OLIVE BLISS has 17 homes in 1 tower registered on MahaRERA.
When was OLIVE BLISS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), OLIVE BLISS was registered on MahaRERA on 20 December 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on OLIVE BLISS?
No court cases are listed for OLIVE BLISS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of OLIVE BLISS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KOHINOOR DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of OLIVE BLISS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 411001
- GAGAN UNO
- IVY BY VISTAARA HOMES
- UNITY COURT
- F5 SKYRA
- ANIKA ESSENTIA
- Mayfair
- GANGA DHAM TOWER C BIBVEWADI PUNE
- Empress Greens
Other projects by KOHINOOR DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.