Shravan Corner
by Suraj Buildcon · Rahatani, Pune
Possession: Shravan Corner is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100013651. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Shravan Corner?
How the possession date of Shravan Corner has moved
31 October 2018
Completion date given when the project was registered
31 July 2024
Extended at the builder's request (MahaRERA application EXT52100017144)
Reason the builder gave MahaRERA: “Delay In Revise process & Then After Due To The Pandemic Covid 19 Shortage Of Labour During & After Covid period All The Banking Process & Transactions Got Slower Which Result In Shortage Of Finance.”
Source: Shravan Corner’s extension records on MahaRERA (P52100013651), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shravan Corner
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100013651
- Status
- Completed
- Builder
- Suraj Buildcon
- Location
- Rahatani, Pune · 412105
- Project type
- Residential / Group Housing
- Registered on
- 16 Oct 2017
- Completion date at registration
- October 2018
- Latest completion date
- July 2024
- Delay so far
- 69 months
- Homes
- 24
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shravan Corner, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shravan Corner | 100% | 100% | 50% | 20% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shravan Corner every month.
Shravan Corner: buildings, flats and land, as filed on MahaRERA
- Buildings: Shravan Corner (4 floors)
- Land: 850 sq m (about 0.2 acres) · sanctioned built-up 718 sq m
- Boundaries filed include: 20 fts road
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shravan Corner →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shravan Corner: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shravan Corner
What is the possession date of Shravan Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shravan Corner in Rahatani, Pune is 31 July 2024 — 69 months later than 31 October 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Shravan Corner?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shravan Corner's builder has filed on MahaRERA, the official one, is 31 July 2024, already 69 months later than the 31 October 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shravan Corner extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shravan Corner's builder applied to MahaRERA to extend the completion date once: to 31 July 2024, giving the reason "Delay In Revise process & Then After Due To The Pandemic Covid 19 Shortage Of Labour During & After Covid period All The Banking Process & Transactions Got Slower Which Result In Shortage Of Finance.".
What is the RERA number of Shravan Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shravan Corner in Rahatani, Pune is P52100013651.
Is Shravan Corner registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shravan Corner is registered as P52100013651 and its status is "Completed".
What is the construction status of Shravan Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), Shravan Corner's status on MahaRERA is "Completed". As filed by the builder, slab work on Shravan Corner is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does Shravan Corner have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shravan Corner safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shravan Corner is registered on MahaRERA as P52100013651, its MahaRERA status is "Completed", its completion date has moved 69 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shravan Corner's possession date changes?
The latest dates are on Shravan Corner's MahaRERA page (P52100013651). GharKundli's Kundli Watch sends a free WhatsApp update on Shravan Corner every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shravan Corner have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shravan Corner has one building filed: Shravan Corner with 4 floors.
How big is the land of Shravan Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), Shravan Corner stands on 850 sq m of land (about 0.2 acres), with 718 sq m of sanctioned built-up area.
Where can I read reviews of Shravan Corner?
Google Maps has reviews of Shravan Corner written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shravan Corner?
Shravan Corner by Suraj Buildcon is in Rahatani, Pune (pincode 412105), Maharashtra, and is registered on MahaRERA as P52100013651, per GharKundli's check of MahaRERA records. Its boundaries filed there include 20 fts road.
How many homes are in Shravan Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), Shravan Corner has 24 homes in 1 tower registered on MahaRERA.
When was Shravan Corner registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shravan Corner was registered on MahaRERA on 16 October 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Shravan Corner?
No court cases are listed for Shravan Corner on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Shravan Corner?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Suraj Buildcon.
Check it yourself on MahaRERA
- How to check the possession date of Shravan Corner
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Rahatani
- KK Mangalam Emerald
- Legacy Kairos C and D Building
- Kaka Sapphire
- 45 Sai Avenue
- The Statement by Legacy
- RAMA ELLENZA
- Legacy Kairos A and B Building
- Adi Amma Insperia
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.