GALAXEE APARTMENT

by HASMUKH INDRADEV GUPTA · Lonavala, Pune

Possession: GALAXEE APARTMENT is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100014995. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about GALAXEE APARTMENT?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GALAXEE APARTMENT has moved

  1. 30 June 2019

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT52100012102)

    Reason the builder gave MahaRERA: “Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis”

Source: GALAXEE APARTMENT’s extension records on MahaRERA (P52100014995), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GALAXEE APARTMENT

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100014995
Status
Completed
Builder
HASMUKH INDRADEV GUPTA
Location
Lonavala, Pune · 410401
Project type
Residential / Group Housing
Registered on
22 Jan 2018
Completion date at registration
June 2019
Latest completion date
June 2023
Delay so far
48 months
Homes
6
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of GALAXEE APARTMENT, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
GALAXEE APARTMENT100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GALAXEE APARTMENT every month.

GALAXEE APARTMENT: buildings, flats and land, as filed on MahaRERA

  • Buildings: GALAXEE APARTMENT (15 floors)
  • Land: 1,620 sq m (about 0.4 acres) · sanctioned built-up 810 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GALAXEE APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GALAXEE APARTMENT: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GALAXEE APARTMENT

What is the possession date of GALAXEE APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GALAXEE APARTMENT in Lonavala, Pune is 30 June 2023 — 48 months later than 30 June 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for GALAXEE APARTMENT?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GALAXEE APARTMENT's builder has filed on MahaRERA, the official one, is 30 June 2023, already 48 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GALAXEE APARTMENT extended?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXEE APARTMENT's builder applied to MahaRERA to extend the completion date once: to 30 June 2023, giving the reason "Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis".

What is the RERA number of GALAXEE APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GALAXEE APARTMENT in Lonavala, Pune is P52100014995.

Is GALAXEE APARTMENT registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXEE APARTMENT is registered as P52100014995 and its status is "Completed".

What is the construction status of GALAXEE APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXEE APARTMENT's status on MahaRERA is "Completed". As filed by the builder, slab work on GALAXEE APARTMENT is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does GALAXEE APARTMENT have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is GALAXEE APARTMENT safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXEE APARTMENT is registered on MahaRERA as P52100014995, its MahaRERA status is "Completed", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if GALAXEE APARTMENT's possession date changes?

The latest dates are on GALAXEE APARTMENT's MahaRERA page (P52100014995). GharKundli's Kundli Watch sends a free WhatsApp update on GALAXEE APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GALAXEE APARTMENT have?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXEE APARTMENT has one building filed: GALAXEE APARTMENT with 15 floors.

How big is the land of GALAXEE APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXEE APARTMENT stands on 1,620 sq m of land (about 0.4 acres), with 810 sq m of sanctioned built-up area.

Where can I read reviews of GALAXEE APARTMENT?

Google Maps has reviews of GALAXEE APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GALAXEE APARTMENT?

GALAXEE APARTMENT by HASMUKH INDRADEV GUPTA is in Lonavala, Pune (pincode 410401), Maharashtra, and is registered on MahaRERA as P52100014995, per GharKundli's check of MahaRERA records.

How many homes are in GALAXEE APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXEE APARTMENT has 6 homes in 1 tower registered on MahaRERA.

When was GALAXEE APARTMENT registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GALAXEE APARTMENT was registered on MahaRERA on 22 January 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on GALAXEE APARTMENT?

No court cases are listed for GALAXEE APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of GALAXEE APARTMENT?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HASMUKH INDRADEV GUPTA.