Possession: HERAMB VILLA is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000010104. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about HERAMB VILLA?
How the possession date of HERAMB VILLA has moved
31 December 2019
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT99000005838)
Reason the builder gave MahaRERA:
“We underestimated the time required for completing the project & hence accordingly date of completion was committed. Also due to material & sales issue, we could not complete on time. But now works are in full progress & project will be com…” Read the full reason
“We underestimated the time required for completing the project & hence accordingly date of completion was committed. Also due to material & sales issue, we could not complete on time. But now works are in full progress & project will be completed within few months. Also, we have attached no objection certificate from the allottees who have booked units in our project.”31 March 2022
Extended at the builder's request (MahaRERA application EXT99000009986)
Reason the builder gave MahaRERA: “Last year's Lockdown, which further affected sales & labours issue. Then again this year's lockdown & restrictions led to further speed breaker. But now the project will be completed within this extended deadline.”
31 March 2023
Extended at the builder's request (MahaRERA application EXT99000011611)
Reason the builder gave MahaRERA: “Lockdown & its aftereffects affectibg the work progress and sales”
Source: HERAMB VILLA’s extension records on MahaRERA (P99000010104), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HERAMB VILLA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000010104
- Status
- Completed
- Builder
- SHILPA DEVELOPERS
- Location
- Palghar East, Palghar · 401404
- Project type
- Residential / Group Housing
- Registered on
- 24 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- March 2023
- Delay so far
- 39 months
- Homes
- 45
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of HERAMB VILLA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| HERAMB VILLA | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HERAMB VILLA every month.
HERAMB VILLA: buildings, flats and land, as filed on MahaRERA
- Buildings: HERAMB VILLA (6 floors)
- Land: 949 sq m (about 0.2 acres) · sanctioned built-up 1,214 sq m
- Boundaries filed include: KAMARE ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of HERAMB VILLA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HERAMB VILLA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HERAMB VILLA
What is the possession date of HERAMB VILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for HERAMB VILLA in Palghar East, Palghar is 31 March 2023 — 39 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for HERAMB VILLA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HERAMB VILLA's builder has filed on MahaRERA, the official one, is 31 March 2023, already 39 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of HERAMB VILLA extended?
According to GharKundli's check of MahaRERA records (updated November 2026), HERAMB VILLA's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2020, giving the reason "We underestimated the time required for completing the project & hence accordingly date of completion was committed. Also due to material & sales issue, we could not complete on time. But now works are in full progress & project will be completed within few months. Also, we have attached no objection certificate from the allottees who have booked units in our project."; to 31 March 2022, giving the reason "Last year's Lockdown, which further affected sales & labours issue. Then again this year's lockdown & restrictions led to further speed breaker. But now the project will be completed within this extended deadline."; to 31 March 2023, giving the reason "Lockdown & its aftereffects affectibg the work progress and sales".
What is the RERA number of HERAMB VILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of HERAMB VILLA in Palghar East, Palghar is P99000010104.
Is HERAMB VILLA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), HERAMB VILLA is registered as P99000010104 and its status is "Completed".
What is the construction status of HERAMB VILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), HERAMB VILLA's status on MahaRERA is "Completed". As filed by the builder, slab work on HERAMB VILLA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does HERAMB VILLA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is HERAMB VILLA safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), HERAMB VILLA is registered on MahaRERA as P99000010104, its MahaRERA status is "Completed", its completion date has moved 39 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HERAMB VILLA's possession date changes?
The latest dates are on HERAMB VILLA's MahaRERA page (P99000010104). GharKundli's Kundli Watch sends a free WhatsApp update on HERAMB VILLA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HERAMB VILLA have?
According to GharKundli's check of MahaRERA records (updated November 2026), HERAMB VILLA has one building filed: HERAMB VILLA with 6 floors.
How big is the land of HERAMB VILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), HERAMB VILLA stands on 949 sq m of land (about 0.2 acres), with 1,214 sq m of sanctioned built-up area.
Where can I read reviews of HERAMB VILLA?
Google Maps has reviews of HERAMB VILLA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HERAMB VILLA?
HERAMB VILLA by SHILPA DEVELOPERS is in Palghar East, Palghar (pincode 401404), near navali village, Maharashtra, and is registered on MahaRERA as P99000010104, per GharKundli's check of MahaRERA records. Its boundaries filed there include KAMARE ROAD.
How many homes are in HERAMB VILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), HERAMB VILLA has 45 homes in 1 tower registered on MahaRERA.
When was HERAMB VILLA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), HERAMB VILLA was registered on MahaRERA on 24 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on HERAMB VILLA?
No court cases are listed for HERAMB VILLA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of HERAMB VILLA?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHILPA DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of HERAMB VILLA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401404
Other projects by SHILPA DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.