ARC VISTA - PHASE 2
by Chaitanya Realty · Munjoba Vasti, Pune
Possession: ARC VISTA - PHASE 2 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100016473. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about ARC VISTA - PHASE 2?
How the possession date of ARC VISTA - PHASE 2 has moved
30 June 2023
Completion date given when the project was registered
29 June 2024
Extended at the builder's request (MahaRERA application EXT52100012477)
Reason the builder gave MahaRERA: “Due to Covid-19, there has been a substantial drop in demand of our category of product, hence the project has slowed down hence requesting the grace period to complete the project as 29/06/2024 instead of 30/06/2023”
Source: ARC VISTA - PHASE 2’s extension records on MahaRERA (P52100016473), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ARC VISTA - PHASE 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100016473
- Status
- Completed
- Builder
- Chaitanya Realty
- Location
- Munjoba Vasti, Pune · 411015
- Project type
- Residential / Group Housing
- Registered on
- 18 May 2018
- Completion date at registration
- June 2023
- Latest completion date
- June 2024
- Delay so far
- 12 months
- Homes
- 85
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of ARC VISTA - PHASE 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C | 100% | 100% | 100% | 95% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARC VISTA - PHASE 2 every month.
ARC VISTA - PHASE 2: buildings, flats and land, as filed on MahaRERA
- Buildings: C (13 floors)
- Land: 870 sq m (about 0.2 acres) · sanctioned built-up 4,051 sq m
The builder’s record and reviews
New World Landmark (a group of 7 linked companies) has 16 projects on MahaRERA since 2018, this one included. Of the 15 GharKundli has checked: 4 finished, all within the promised date; 11 still being built, 2 past the promised date (typically 14 months late). 6 complaints on MahaRERA across 2 projects.
Read Google reviews of ARC VISTA - PHASE 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ARC VISTA - PHASE 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ARC VISTA - PHASE 2
What is the possession date of ARC VISTA - PHASE 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ARC VISTA - PHASE 2 in Munjoba Vasti, Pune is 29 June 2024 — 12 months later than 30 June 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ARC VISTA - PHASE 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ARC VISTA - PHASE 2's builder has filed on MahaRERA, the official one, is 29 June 2024, already 12 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ARC VISTA - PHASE 2 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), ARC VISTA - PHASE 2's builder applied to MahaRERA to extend the completion date once: to 29 June 2024, giving the reason "Due to Covid-19, there has been a substantial drop in demand of our category of product, hence the project has slowed down hence requesting the grace period to complete the project as 29/06/2024 instead of 30/06/2023".
What is the RERA number of ARC VISTA - PHASE 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ARC VISTA - PHASE 2 in Munjoba Vasti, Pune is P52100016473.
Is ARC VISTA - PHASE 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ARC VISTA - PHASE 2 is registered as P52100016473 and its status is "Completed".
What is the construction status of ARC VISTA - PHASE 2?
According to GharKundli's check of MahaRERA records (updated November 2026), ARC VISTA - PHASE 2's status on MahaRERA is "Completed". As filed by the builder, slab work on C is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does ARC VISTA - PHASE 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is ARC VISTA - PHASE 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ARC VISTA - PHASE 2 is registered on MahaRERA as P52100016473, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ARC VISTA - PHASE 2's possession date changes?
The latest dates are on ARC VISTA - PHASE 2's MahaRERA page (P52100016473). GharKundli's Kundli Watch sends a free WhatsApp update on ARC VISTA - PHASE 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ARC VISTA - PHASE 2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), ARC VISTA - PHASE 2 has one building filed: C with 13 floors.
How big is the land of ARC VISTA - PHASE 2?
According to GharKundli's check of MahaRERA records (updated November 2026), ARC VISTA - PHASE 2 stands on 870 sq m of land (about 0.2 acres), with 4,051 sq m of sanctioned built-up area.
What is the track record of ARC VISTA - PHASE 2's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), New World Landmark (a group of 7 linked companies) has 16 projects on MahaRERA since 2018, this one included. Of the 15 GharKundli has checked: 4 finished, all within the promised date; 11 still being built, 2 past the promised date (typically 14 months late). 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ARC VISTA - PHASE 2?
Google Maps has reviews of ARC VISTA - PHASE 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ARC VISTA - PHASE 2?
ARC VISTA - PHASE 2 by Chaitanya Realty is in Munjoba Vasti, Pune (pincode 411015), Maharashtra, and is registered on MahaRERA as P52100016473, per GharKundli's check of MahaRERA records.
How many homes are in ARC VISTA - PHASE 2?
According to GharKundli's check of MahaRERA records (updated November 2026), ARC VISTA - PHASE 2 has 85 homes in 1 tower registered on MahaRERA.
When was ARC VISTA - PHASE 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ARC VISTA - PHASE 2 was registered on MahaRERA on 18 May 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on ARC VISTA - PHASE 2?
No court cases are listed for ARC VISTA - PHASE 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of ARC VISTA - PHASE 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Chaitanya Realty, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ARC VISTA - PHASE 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data