GAGAN UNNATII PHASE 3

by GAGAN UNNATI VENTURES · Opposite Shatrunjay Mandir, PuneAlso near Kondhwa BK, Kondhwa- Budruk, Katraj

Possession date of GAGAN UNNATII PHASE 3: 31 December 2024, moved from 31 December 2020 (48 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100016561. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about GAGAN UNNATII PHASE 3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of GAGAN UNNATII PHASE 3 has moved

  1. 31 December 2020

    Completion date given when the project was registered

  2. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT52100005459)

    Reason the builder gave MahaRERA:
    “Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. any notice, orde…” Read the full reason“Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. any notice, order, rule, notification of the Government and/or other public or competent authority/court c. Delay in grant of any NOC/permission/license/ connection installation of any services such as lifts, electricity & water connections & meters to the scheme/unit /road NOC or completion certificate from Appropriate Authority the Promoters/Owners having complied with…”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52100012609)

    Reason the builder gave MahaRERA:
    “Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay on the par…” Read the full reason“Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay on the part of the Local Authority or any other Public Body or Authority including the M.S.E.D.C.L, in issuing or granting necessary Certificates / Noc’s / Permissions / Licenses / Connections of any service such as Electricity, Drains and Water Connections and Meters to the said Project under construction by the Promoters on the said Land. c. Compliances with the…”

Source: GAGAN UNNATII PHASE 3’s extension records on MahaRERA (P52100016561), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on GAGAN UNNATII PHASE 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100016561
Status
Lapsed (registration period ended)
Builder
GAGAN UNNATI VENTURES
Location
Opposite Shatrunjay Mandir, Pune · 411048
Project type
Residential / Group Housing
Registered on
23 May 2018
Completion date at registration
December 2020
Latest completion date
December 2024
Delay so far
48 months
Homes
23
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of GAGAN UNNATII PHASE 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING E100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on GAGAN UNNATII PHASE 3 every month.

GAGAN UNNATII PHASE 3: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of GAGAN UNNATII PHASE 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

GAGAN UNNATII PHASE 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about GAGAN UNNATII PHASE 3

What is the possession date of GAGAN UNNATII PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GAGAN UNNATII PHASE 3 in Opposite Shatrunjay Mandir, Pune is 31 December 2024 — 48 months later than 31 December 2020, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for GAGAN UNNATII PHASE 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date GAGAN UNNATII PHASE 3's builder has filed on MahaRERA, the official one, is 31 December 2024, already 48 months later than the 31 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of GAGAN UNNATII PHASE 3 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), GAGAN UNNATII PHASE 3's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2021, giving the reason "Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. any notice, order, rule, notification of the Government and/or other public or competent authority/court c. Delay in grant of any NOC/permission/license/ connection installation of any services such as lifts, electricity & water connections & meters to the scheme/unit /road NOC or completion certificate from Appropriate Authority the Promoters/Owners having complied with…"; to 31 December 2024, giving the reason "Reason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay on the part of the Local Authority or any other Public Body or Authority including the M.S.E.D.C.L, in issuing or granting necessary Certificates / Noc’s / Permissions / Licenses / Connections of any service such as Electricity, Drains and Water Connections and Meters to the said Project under construction by the Promoters on the said Land. c. Compliances with the…".

What is the RERA number of GAGAN UNNATII PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GAGAN UNNATII PHASE 3 in Opposite Shatrunjay Mandir, Pune is P52100016561.

Is GAGAN UNNATII PHASE 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GAGAN UNNATII PHASE 3 is registered as P52100016561 and its status is "Lapsed (registration period ended)".

What is the construction status of GAGAN UNNATII PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), GAGAN UNNATII PHASE 3's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on BUILDING E is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does GAGAN UNNATII PHASE 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is GAGAN UNNATII PHASE 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), GAGAN UNNATII PHASE 3 is registered on MahaRERA as P52100016561, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does GAGAN UNNATII PHASE 3 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: GAGAN UNNATII PHASE 2 (P52100001818). Check that your agreement names the registration of your own wing.

How can I get updates if GAGAN UNNATII PHASE 3's possession date changes?

The latest dates are on GAGAN UNNATII PHASE 3's MahaRERA page (P52100016561). GharKundli's Kundli Watch sends a free WhatsApp update on GAGAN UNNATII PHASE 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does GAGAN UNNATII PHASE 3 have?

According to GharKundli's check of MahaRERA records (updated November 2026), GAGAN UNNATII PHASE 3 has one building filed: BUILDING E with 7 floors.

How big is the land of GAGAN UNNATII PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), GAGAN UNNATII PHASE 3 stands on 1,605 sq m of land (about 0.4 acres), with 1,980 sq m of sanctioned built-up area.

Where can I read reviews of GAGAN UNNATII PHASE 3?

Google Maps has reviews of GAGAN UNNATII PHASE 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is GAGAN UNNATII PHASE 3?

GAGAN UNNATII PHASE 3 by GAGAN UNNATI VENTURES is in Opposite Shatrunjay Mandir, Pune (pincode 411048), near Kondhwa BK, Kondhwa- Budruk, Katraj, Maharashtra, and is registered on MahaRERA as P52100016561, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 METRE SERVICE ROAD.

How many homes are in GAGAN UNNATII PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), GAGAN UNNATII PHASE 3 has 23 homes in 1 tower registered on MahaRERA.

When was GAGAN UNNATII PHASE 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), GAGAN UNNATII PHASE 3 was registered on MahaRERA on 23 May 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on GAGAN UNNATII PHASE 3?

No court cases are listed for GAGAN UNNATII PHASE 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of GAGAN UNNATII PHASE 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GAGAN UNNATI VENTURES, which has 1 other project registered on MahaRERA.

Other projects in Haveli

All 234 projects in N I B M (411048) →

Other projects by GAGAN UNNATI VENTURES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.