VARADH RESIDENCY - PHASE 2

by RADIANTS PROPERTIES · Malimala, Pune

Possession date of VARADH RESIDENCY - PHASE 2: 30 April 2027, moved from 30 March 2023 (45 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100016872, and currently active. Its completion date has moved from March 2023 to April 2027: 45 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about VARADH RESIDENCY - PHASE 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VARADH RESIDENCY - PHASE 2 has moved

  1. 30 March 2023

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT52100011271)

    Reason the builder gave MahaRERA:
    “The reason for extension of the date of completion of the project is primarily based on unavailability of the standard material which is to be used in the construction of the said project & non-availability/ delay of finance, due to COVID-1…” Read the full reason“The reason for extension of the date of completion of the project is primarily based on unavailability of the standard material which is to be used in the construction of the said project & non-availability/ delay of finance, due to COVID-19 lockdown.”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: VARADH RESIDENCY - PHASE 2’s extension records on MahaRERA (P52100016872), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VARADH RESIDENCY - PHASE 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100016872
Status
Registered and active
Builder
RADIANTS PROPERTIES
Location
Malimala, Pune · 410505
Project type
Residential / Group Housing
Registered on
20 Jun 2018
Completion date at registration
March 2023
Latest completion date
April 2027
Delay so far
45 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
47
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of VARADH RESIDENCY - PHASE 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING B100%100%100%0%
BUILDING C100%100%100%0%
BUILDING D100%100%100%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VARADH RESIDENCY - PHASE 2 every month.

VARADH RESIDENCY - PHASE 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING B (6 floors) · BUILDING C (6 floors) · BUILDING D (5 floors)
  • Land: 1,891 sq m (about 0.5 acres) · sanctioned built-up 1,891 sq m
  • Boundaries filed include: SHRI VIJAY SITARAMGUMATKAR SOCIETY

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of VARADH RESIDENCY - PHASE 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VARADH RESIDENCY - PHASE 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VARADH RESIDENCY - PHASE 2

What is the possession date of VARADH RESIDENCY - PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VARADH RESIDENCY - PHASE 2 in Malimala, Pune is 30 April 2027 — 45 months later than 30 March 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for VARADH RESIDENCY - PHASE 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VARADH RESIDENCY - PHASE 2's builder has filed on MahaRERA, the official one, is 30 April 2027, already 45 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VARADH RESIDENCY - PHASE 2 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), VARADH RESIDENCY - PHASE 2's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The reason for extension of the date of completion of the project is primarily based on unavailability of the standard material which is to be used in the construction of the said project & non-availability/ delay of finance, due to COVID-19 lockdown.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of VARADH RESIDENCY - PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VARADH RESIDENCY - PHASE 2 in Malimala, Pune is P52100016872.

Is VARADH RESIDENCY - PHASE 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VARADH RESIDENCY - PHASE 2 is registered as P52100016872 and its status is "Registered and active".

What is the construction status of VARADH RESIDENCY - PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), VARADH RESIDENCY - PHASE 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does VARADH RESIDENCY - PHASE 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is VARADH RESIDENCY - PHASE 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), VARADH RESIDENCY - PHASE 2 is registered on MahaRERA as P52100016872, its completion date has moved 45 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does VARADH RESIDENCY - PHASE 2 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: VARADH RESIDENCY - PHASE 1 (P52100016877). Check that your agreement names the registration of your own wing.

How can I get updates if VARADH RESIDENCY - PHASE 2's possession date changes?

The latest dates are on VARADH RESIDENCY - PHASE 2's MahaRERA page (P52100016872). GharKundli's Kundli Watch sends a free WhatsApp update on VARADH RESIDENCY - PHASE 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VARADH RESIDENCY - PHASE 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), VARADH RESIDENCY - PHASE 2 has 3 buildings filed: BUILDING B with 6 floors; BUILDING C with 6 floors; BUILDING D with 5 floors.

How big is the land of VARADH RESIDENCY - PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), VARADH RESIDENCY - PHASE 2 stands on 1,891 sq m of land (about 0.5 acres), with 1,891 sq m of sanctioned built-up area.

Where can I read reviews of VARADH RESIDENCY - PHASE 2?

Google Maps has reviews of VARADH RESIDENCY - PHASE 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VARADH RESIDENCY - PHASE 2?

VARADH RESIDENCY - PHASE 2 by RADIANTS PROPERTIES is in Malimala, Pune (pincode 410505), Maharashtra, and is registered on MahaRERA as P52100016872, per GharKundli's check of MahaRERA records. Its boundaries filed there include SHRI VIJAY SITARAMGUMATKAR SOCIETY.

How many homes are in VARADH RESIDENCY - PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), VARADH RESIDENCY - PHASE 2 has 47 homes in 3 towers registered on MahaRERA.

When was VARADH RESIDENCY - PHASE 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VARADH RESIDENCY - PHASE 2 was registered on MahaRERA on 20 June 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on VARADH RESIDENCY - PHASE 2?

No court cases are listed for VARADH RESIDENCY - PHASE 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of VARADH RESIDENCY - PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RADIANTS PROPERTIES, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Pune →

Other projects in Khed

All 41 projects in Rajgurunagar (410505) →

Other projects by RADIANTS PROPERTIES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.