by PARINEE REALTY PRIVATE LIMITED · Andheri west, MumbaiAlso near Jogeshwari WEst, Ambivali West, Oshiwara

Possession date of Parinee i: 31 December 2028, moved from 30 June 2021 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800001904, and currently active. 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Parinee i?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Parinee i has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT51800009968)

    Reason the builder gave MahaRERA:
    ““Parinee i” is a Commercial Project being undertaken under the SRA. The RCC structure is already completed way back in 2019, but due to current pandemic situation and non-disbursal of funds by the lending institution due to their internal i…” Read the full reason““Parinee i” is a Commercial Project being undertaken under the SRA. The RCC structure is already completed way back in 2019, but due to current pandemic situation and non-disbursal of funds by the lending institution due to their internal issues, the further work couldn’t be completed within the stipulated time. The reasons/circumstances, which were beyond the control of Promoter are enlisted below:- Delay in grant of various approvals: Due to changes in the regulations, the project plans are amended in April 2017. Post that there is delay in granting various approvals like Further CC, High…”
  3. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT51800013127)

    Reason the builder gave MahaRERA:
    ““Parinee I” is a Commercial Project undertaken under the SRA. The RCC structure of the entire building is already completed way back in 2019. Due to past pandemic situation, non-disbursal of funds by the lending institution and various dela…” Read the full reason““Parinee I” is a Commercial Project undertaken under the SRA. The RCC structure of the entire building is already completed way back in 2019. Due to past pandemic situation, non-disbursal of funds by the lending institution and various delay in approvals from the competent authorities, the further work couldn’t be completed within the stipulated time and the reasons were beyond the control of Promoter 1) On 31st December 2020 SRA had issued stop work on project on baseless grounds. We had filed Writ Petition (L) 8601 in High Court, whilst the same was pending SRA withdrew the Stop Work Noti…”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800019725)

    Reason the builder gave MahaRERA:
    ““Parinee I” is a 30 storey Commercial Project undertaken under the SRA. The RCC structure of the entire building is already completed way back in 2019. Due to past pandemic situation, non-disbursal of funds by the lending institution and va…” Read the full reason““Parinee I” is a 30 storey Commercial Project undertaken under the SRA. The RCC structure of the entire building is already completed way back in 2019. Due to past pandemic situation, non-disbursal of funds by the lending institution and various delay in approvals from the competent authorities, the further work couldn’t be completed within the stipulated time and the reasons were beyond the control of Promoter 1) The finishing work uptill 23rd floor is already completed and no inventory is sold beyond 23rd Floor. 2) We have obtained Part Occupation Certificate uptill 12th Floor on 02/11/22…”
  5. 31 December 2028

    Extended at the builder's request (MahaRERA application EA21082622304)

    Reason the builder gave MahaRERA:
    “We, Parinee Realty Private Limited, the promoter of the project Parinee i (Registration No. P51800001904) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We wish to clarify that the cons…” Read the full reason“We, Parinee Realty Private Limited, the promoter of the project Parinee i (Registration No. P51800001904) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We wish to clarify that the construction of the project has been completed and we have also received Part Occupancy Certificate for a major portion of the project from the Planning Authority Slum Rehabilitation Authority. However, the Full Occupancy Certificate is yet to be received. Certain SRA compliances are pending from our side, which are required to be completed before the Plannin…”

Source: Parinee i’s extension records on MahaRERA (P51800001904), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Parinee i

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints and 1 court case, and how it ended
  • Construction pace against the December 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800001904
Status
Registered and active
Builder
PARINEE REALTY PRIVATE LIMITED
Location
Andheri west, Mumbai · 400053
Project type
Commercial
Registered on
29 Jul 2017
Completion date at registration
June 2021
Latest completion date
December 2028
Delay so far
90 months
Homes
0
Sold or booked
86%
Towers
1
Complaints on MahaRERA
7
Court cases listed
1
Appeals at the tribunal
2
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Parinee i, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Parinee i100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Parinee i: covers Brick and Masenry Work upto 29th Floor. RCC Framework upto 30th Floor.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Parinee i every month.

Parinee i: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space573 – 5,047278
Other1,776 – 3,8158

The builder’s record and reviews

Parinee Realty has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 23 months); 1 still being built, 1 past the promised date (typically 52 months late). 30 complaints on MahaRERA across 3 projects.

Read Google reviews of Parinee i →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Parinee i: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Parinee i

What is the possession date of Parinee i?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Parinee i in Andheri west, Mumbai is 31 December 2028 — 90 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Parinee i?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Parinee i's builder has filed on MahaRERA, the official one, is 31 December 2028, already 90 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Parinee i extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Parinee i's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2022, giving the reason "“Parinee i” is a Commercial Project being undertaken under the SRA. The RCC structure is already completed way back in 2019, but due to current pandemic situation and non-disbursal of funds by the lending institution due to their internal issues, the further work couldn’t be completed within the stipulated time. The reasons/circumstances, which were beyond the control of Promoter are enlisted below:- Delay in grant of various approvals: Due to changes in the regulations, the project plans are amended in April 2017. Post that there is delay in granting various approvals like Further CC, High…"; to 31 March 2024, giving the reason "“Parinee I” is a Commercial Project undertaken under the SRA. The RCC structure of the entire building is already completed way back in 2019. Due to past pandemic situation, non-disbursal of funds by the lending institution and various delay in approvals from the competent authorities, the further work couldn’t be completed within the stipulated time and the reasons were beyond the control of Promoter 1) On 31st December 2020 SRA had issued stop work on project on baseless grounds. We had filed Writ Petition (L) 8601 in High Court, whilst the same was pending SRA withdrew the Stop Work Noti…"; to 31 December 2024, giving the reason "“Parinee I” is a 30 storey Commercial Project undertaken under the SRA. The RCC structure of the entire building is already completed way back in 2019. Due to past pandemic situation, non-disbursal of funds by the lending institution and various delay in approvals from the competent authorities, the further work couldn’t be completed within the stipulated time and the reasons were beyond the control of Promoter 1) The finishing work uptill 23rd floor is already completed and no inventory is sold beyond 23rd Floor. 2) We have obtained Part Occupation Certificate uptill 12th Floor on 02/11/22…"; to 31 December 2028, giving the reason "We, Parinee Realty Private Limited, the promoter of the project Parinee i (Registration No. P51800001904) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We wish to clarify that the construction of the project has been completed and we have also received Part Occupancy Certificate for a major portion of the project from the Planning Authority Slum Rehabilitation Authority. However, the Full Occupancy Certificate is yet to be received. Certain SRA compliances are pending from our side, which are required to be completed before the Plannin…".

What is the RERA number of Parinee i?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Parinee i in Andheri west, Mumbai is P51800001904.

Is Parinee i registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Parinee i is registered as P51800001904 and its status is "Registered and active".

What is the construction status of Parinee i?

According to GharKundli's check of MahaRERA records (updated October 2026), Parinee i's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Parinee i is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Parinee i have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Parinee i safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Parinee i is registered on MahaRERA as P51800001904, its completion date has moved 90 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Parinee i's possession date changes?

The latest dates are on Parinee i's MahaRERA page (P51800001904). GharKundli's Kundli Watch sends a free WhatsApp update on Parinee i every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Parinee i have?

According to GharKundli's check of MahaRERA records (updated October 2026), Parinee i has one building filed: Parinee i with 34 floors and 286 units.

How big is the land of Parinee i?

According to GharKundli's check of MahaRERA records (updated October 2026), Parinee i stands on 3,997 sq m of land (about 1.0 acres), with 16,751 sq m of sanctioned built-up area and 402 sq m of recreational open space.

What is the track record of Parinee i's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Parinee Realty has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 23 months); 1 still being built, 1 past the promised date (typically 52 months late). 30 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Parinee i?

Google Maps has reviews of Parinee i written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Parinee i?

Parinee i by PARINEE REALTY PRIVATE LIMITED is in Andheri west, Mumbai (pincode 400053), near Jogeshwari WEst, Ambivali West, Oshiwara, Maharashtra, and is registered on MahaRERA as P51800001904, per GharKundli's check of MahaRERA records.

How many homes are in Parinee i?

According to GharKundli's check of MahaRERA records (updated October 2026), Parinee i has 0 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.

When was Parinee i registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Parinee i was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Parinee i?

1 court case is listed for Parinee i on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Parinee i?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PARINEE REALTY PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in pincode 400053

All 161 projects in Andheri West (400053) →

Other projects by PARINEE REALTY PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.