PRABHU RESIDENCY

by P W DEVELOPERS · Dighi, Pune

Possession date of PRABHU RESIDENCY: 31 March 2025, moved from 1 August 2021 (43 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100018849. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (March 2025) has passed.

What do you want to know about PRABHU RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PRABHU RESIDENCY has moved

  1. 1 August 2021

    Completion date given when the project was registered

  2. 11 August 2021

    Extended at the builder's request (MahaRERA application EXT52100010717)

    Reason the builder gave MahaRERA: “Due to covid pandemic work on site was very slow”
  3. 1 August 2022

    Extended at the builder's request (MahaRERA application EXT52100010890)

    Reason the builder gave MahaRERA: “due to pandemic”
  4. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT52100015185)

    Reason the builder gave MahaRERA: “NOC PENDING”

Source: PRABHU RESIDENCY’s extension records on MahaRERA (P52100018849), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PRABHU RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100018849
Status
Lapsed (registration period ended)
Builder
P W DEVELOPERS
Location
Dighi, Pune · 411015
Project type
Residential / Group Housing
Registered on
6 Dec 2018
Completion date at registration
August 2021
Latest completion date
March 2025
Delay so far
43 months
Homes
11
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of PRABHU RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A BUILDING100%100%95%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PRABHU RESIDENCY every month.

PRABHU RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: A BUILDING (5 floors)
  • Land: 233 sq m (about 0.1 acres) · sanctioned built-up 444 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of PRABHU RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PRABHU RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PRABHU RESIDENCY

What is the possession date of PRABHU RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PRABHU RESIDENCY in Dighi, Pune is 31 March 2025 — 43 months later than 1 August 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for PRABHU RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PRABHU RESIDENCY's builder has filed on MahaRERA, the official one, is 31 March 2025, already 43 months later than the 1 August 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PRABHU RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), PRABHU RESIDENCY's builder applied to MahaRERA to extend the completion date 3 times: to 11 August 2021, giving the reason "Due to covid pandemic work on site was very slow"; to 1 August 2022, giving the reason "due to pandemic"; to 31 March 2025, giving the reason "NOC PENDING".

What is the RERA number of PRABHU RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PRABHU RESIDENCY in Dighi, Pune is P52100018849.

Is PRABHU RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PRABHU RESIDENCY is registered as P52100018849 and its status is "Lapsed (registration period ended)".

What is the construction status of PRABHU RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), PRABHU RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on A BUILDING is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does PRABHU RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is PRABHU RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PRABHU RESIDENCY is registered on MahaRERA as P52100018849, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 43 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PRABHU RESIDENCY's possession date changes?

The latest dates are on PRABHU RESIDENCY's MahaRERA page (P52100018849). GharKundli's Kundli Watch sends a free WhatsApp update on PRABHU RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PRABHU RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated November 2026), PRABHU RESIDENCY has one building filed: A BUILDING with 5 floors.

How big is the land of PRABHU RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), PRABHU RESIDENCY stands on 233 sq m of land (about 0.1 acres), with 444 sq m of sanctioned built-up area.

Where can I read reviews of PRABHU RESIDENCY?

Google Maps has reviews of PRABHU RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PRABHU RESIDENCY?

PRABHU RESIDENCY by P W DEVELOPERS is in Dighi, Pune (pincode 411015), Maharashtra, and is registered on MahaRERA as P52100018849, per GharKundli's check of MahaRERA records.

How many homes are in PRABHU RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), PRABHU RESIDENCY has 11 homes in 1 tower registered on MahaRERA.

When was PRABHU RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PRABHU RESIDENCY was registered on MahaRERA on 6 December 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on PRABHU RESIDENCY?

No court cases are listed for PRABHU RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PRABHU RESIDENCY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is P W DEVELOPERS.