Possession date of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing (MahaRERA P52100019558): 29 August 2024, and it has already passed. It has 326 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100019558. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100019558, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (August 2024) has passed.

What do you want to know about Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Kingston Serene Phase 2 A1, A2, B1 and B2 Wing

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the August 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100019558
Status
Lapsed (registration period ended)
Builder
Vedant Realtors
Location
Autade Handewadi, Pune · 411028
Project type
Residential / Group Housing
Registered on
8 Feb 2019
Completion date at registration
August 2024
Latest completion date
August 2024
Homes
326
Towers
4
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A1 Wing0%0%0%0%
A2 Wing0%0%0%0%
B1 Wing0%0%0%0%
Proposed B2 Wing0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kingston Serene Phase 2 A1, A2, B1 and B2 Wing every 1–2 months.

Kingston Serene Phase 2 A1, A2, B1 and B2 Wing: buildings, flats and land, as filed on MahaRERA

  • Buildings: A1 Wing (14 floors) · A2 Wing (14 floors) · B1 Wing (13 floors)
  • Land: 9,039 sq m (about 2.2 acres) · sanctioned built-up 15,707 sq m · recreational space 904 sq m
  • Land, as filed: S. No. 85/1, 85/2 and 92/1
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Vedant Landmarks (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, none past the promised date yet; 2 lapsed. 58 complaints on MahaRERA across 4 projects.

Read Google reviews of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kingston Serene Phase 2 A1, A2, B1 and B2 Wing: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kingston Serene Phase 2 A1, A2, B1 and B2 Wing

What is the possession date of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Kingston Serene Phase 2 A1, A2, B1 and B2 Wing in Autade Handewadi, Pune is 29 August 2024. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kingston Serene Phase 2 A1, A2, B1 and B2 Wing's builder has filed on MahaRERA, the official one, is 29 August 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing in Autade Handewadi, Pune is P52100019558.

Is Kingston Serene Phase 2 A1, A2, B1 and B2 Wing registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kingston Serene Phase 2 A1, A2, B1 and B2 Wing is registered as P52100019558 and its status is "Lapsed (registration period ended)".

What is the current construction status of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Kingston Serene Phase 2 A1, A2, B1 and B2 Wing's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 0% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Kingston Serene Phase 2 A1, A2, B1 and B2 Wing have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Kingston Serene Phase 2 A1, A2, B1 and B2 Wing safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Kingston Serene Phase 2 A1, A2, B1 and B2 Wing is registered on MahaRERA as P52100019558, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

Kingston Serene Phase 2 A1, A2, B1 and B2 Wing isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Kingston Serene Phase 2 A1, A2, B1 and B2 Wing: gharkundli.com/tools/property-cost-calculator

Has Kingston Serene Phase 2 A1, A2, B1 and B2 Wing received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Kingston Serene Phase 2 A1, A2, B1 and B2 Wing isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 29 August 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Kingston Serene Phase 2 A1, A2, B1 and B2 Wing's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (29 August 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Kingston Serene Phase 2 A1, A2, B1 and B2 Wing uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Kingston Serene Phase 2 A1, A2, B1 and B2 Wing was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Kingston Serene Phase 2 A1, A2, B1 and B2 Wing's possession date changes?

The latest dates are on Kingston Serene Phase 2 A1, A2, B1 and B2 Wing's MahaRERA page (P52100019558). GharKundli's Kundli Watch sends a free WhatsApp update on Kingston Serene Phase 2 A1, A2, B1 and B2 Wing every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kingston Serene Phase 2 A1, A2, B1 and B2 Wing have?

According to GharKundli's check of MahaRERA records (updated November 2026), Kingston Serene Phase 2 A1, A2, B1 and B2 Wing has 3 buildings filed: A1 Wing with 14 floors; A2 Wing with 14 floors; B1 Wing with 13 floors.

How big is the land of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Kingston Serene Phase 2 A1, A2, B1 and B2 Wing stands on 9,039 sq m of land (about 2.2 acres), with 15,707 sq m of sanctioned built-up area and 904 sq m of recreational open space.

What is the track record of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Vedant Landmarks (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, none past the promised date yet; 2 lapsed. 58 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

Google Maps has reviews of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

Kingston Serene Phase 2 A1, A2, B1 and B2 Wing by Vedant Realtors is in Autade Handewadi, Pune, pincode 411028 (near Undri, Mohammadwadi, Handewadi Chowk), Maharashtra, and is registered on MahaRERA as P52100019558, per GharKundli's check of MahaRERA records. Its land is filed as S. No. 85/1, 85/2 and 92/1. GharKundli lists all 301 MahaRERA projects in Hadapsar (411028).

How many flats are in Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), Kingston Serene Phase 2 A1, A2, B1 and B2 Wing has 326 homes in 4 towers registered on MahaRERA.

When was Kingston Serene Phase 2 A1, A2, B1 and B2 Wing registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Kingston Serene Phase 2 A1, A2, B1 and B2 Wing was registered on MahaRERA on 8 February 2019. GharKundli did not find a title report on the land on file there.

Does Kingston Serene Phase 2 A1, A2, B1 and B2 Wing have any legal issues or court cases?

1 court case is listed for Kingston Serene Phase 2 A1, A2, B1 and B2 Wing on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Kingston Serene Phase 2 A1, A2, B1 and B2 Wing?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Vedant Realtors, which has 1 other project registered on MahaRERA.

Other projects in Hadapsar (411028)

All 301 projects in Hadapsar (411028) →

Other projects by Vedant Realtors

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.