Skip to content
GharKundli

B Square

by YOGESH VIJAY BHIDE · junnar, Pune 410502

What’s in the report? →

Possession: B Square (MahaRERA P52100024557) is marked completed on MahaRERA. It has 17 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100024557. Status: Completed.

Source: MahaRERA website — records for P52100024557, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about B Square?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on B Square

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100024557
Status
Completed
Builder
YOGESH VIJAY BHIDE
Location
junnar, Pune · 410502
Project type
Residential / Group Housing
Registered on
24 Feb 2020
Completion date at registration
December 2023
Latest completion date
December 2023
Homes
17
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of B Square, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B SQUARE100%95%95%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on B Square every 1–2 months.

B Square: buildings, flats and land, as filed on MahaRERA

  • Buildings: B SQUARE (6 floors)
  • Land: 376 sq m (about 0.1 acres) · sanctioned built-up 715 sq m · recreational space 376 sq m
  • Land, as filed: 1092 TO 1095
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of B Square →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

B Square: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about B Square

What is the possession date of B Square?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for B Square in junnar, Pune is 25 December 2023.

Is the builder's possession date different from the MahaRERA date for B Square?

Builders and listing sites often quote an earlier "target" date for handover. The completion date B Square's builder has filed on MahaRERA, the official one, is 25 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of B Square?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of B Square in junnar, Pune is P52100024557.

Is B Square registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), B Square is registered as P52100024557 and its status is "Completed".

What is the current construction status of B Square? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), B Square's status on MahaRERA is "Completed". As filed by the builder, slab work on B SQUARE is 95% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does B Square have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is B Square safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), B Square is registered on MahaRERA as P52100024557, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in B Square?

According to GharKundli's check of MahaRERA records (updated November 2026), B Square is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in B Square?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in B Square: gharkundli.com/tools/property-cost-calculator

Has B Square received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), B Square is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was B Square completed?

According to GharKundli's check of MahaRERA records (updated November 2026), B Square is marked completed on MahaRERA, and the completion date filed there is 25 December 2023. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has B Square uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for B Square was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if B Square's possession date changes?

The latest dates are on B Square's MahaRERA page (P52100024557). GharKundli's Kundli Watch sends a free WhatsApp update on B Square every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does B Square have?

According to GharKundli's check of MahaRERA records (updated November 2026), B Square has one building filed: B SQUARE with 6 floors.

How big is the land of B Square?

According to GharKundli's check of MahaRERA records (updated November 2026), B Square stands on 376 sq m of land (about 0.1 acres), with 715 sq m of sanctioned built-up area and 376 sq m of recreational open space.

What are the reviews of B Square?

Google Maps has reviews of B Square written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of B Square?

B Square by YOGESH VIJAY BHIDE is in junnar, Pune, pincode 410502, Maharashtra, and is registered on MahaRERA as P52100024557, per GharKundli's check of MahaRERA records. Its land is filed as 1092 TO 1095. GharKundli lists all 26 MahaRERA projects in Junnar (410502).

How many flats are in B Square?

According to GharKundli's check of MahaRERA records (updated November 2026), B Square has 17 homes in 1 tower registered on MahaRERA.

When was B Square registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), B Square was registered on MahaRERA on 24 February 2020. GharKundli did not find a title report on the land on file there.

Does B Square have any legal issues or court cases?

No court cases are listed for B Square on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of B Square?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is YOGESH VIJAY BHIDE.

Other projects in Junnar

All 26 projects in Junnar (410502) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.