SAI SNEH

by NILESH DILIP KALE · Kalepadal, Pune

Possession date of SAI SNEH: 31 December 2024, moved from 30 April 2023 (20 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100029164. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2024) has passed.

What do you want to know about SAI SNEH?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI SNEH has moved

  1. 30 April 2023

    Completion date given when the project was registered

  2. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52100016691)

    Reason the builder gave MahaRERA: “PUNE MUNICIPAL CORPORATION UNDER DELAY FOR NA ORDER”

Source: SAI SNEH’s extension records on MahaRERA (P52100029164), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI SNEH

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100029164
Status
Lapsed (registration period ended)
Builder
NILESH DILIP KALE
Location
Kalepadal, Pune · 411028
Project type
Residential / Group Housing
Registered on
3 May 2021
Completion date at registration
April 2023
Latest completion date
December 2024
Delay so far
20 months
Homes
9
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SAI SNEH, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI SNEH100%80%90%85%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI SNEH every month.

SAI SNEH: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI SNEH (4 floors)
  • Land: 400 sq m (about 0.1 acres) · sanctioned built-up 401 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAI SNEH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI SNEH: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI SNEH

What is the possession date of SAI SNEH?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI SNEH in Kalepadal, Pune is 31 December 2024 — 20 months later than 30 April 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SAI SNEH?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI SNEH's builder has filed on MahaRERA, the official one, is 31 December 2024, already 20 months later than the 30 April 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI SNEH extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SNEH's builder applied to MahaRERA to extend the completion date once: to 31 December 2024, giving the reason "PUNE MUNICIPAL CORPORATION UNDER DELAY FOR NA ORDER".

What is the RERA number of SAI SNEH?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI SNEH in Kalepadal, Pune is P52100029164.

Is SAI SNEH registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SNEH is registered as P52100029164 and its status is "Lapsed (registration period ended)".

What is the construction status of SAI SNEH?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SNEH's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SAI SNEH is 80% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does SAI SNEH have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is SAI SNEH safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SNEH is registered on MahaRERA as P52100029164, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 20 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI SNEH's possession date changes?

The latest dates are on SAI SNEH's MahaRERA page (P52100029164). GharKundli's Kundli Watch sends a free WhatsApp update on SAI SNEH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI SNEH have?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SNEH has one building filed: SAI SNEH with 4 floors.

How big is the land of SAI SNEH?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SNEH stands on 400 sq m of land (about 0.1 acres), with 401 sq m of sanctioned built-up area.

Where can I read reviews of SAI SNEH?

Google Maps has reviews of SAI SNEH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI SNEH?

SAI SNEH by NILESH DILIP KALE is in Kalepadal, Pune (pincode 411028), Maharashtra, and is registered on MahaRERA as P52100029164, per GharKundli's check of MahaRERA records.

How many homes are in SAI SNEH?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SNEH has 9 homes in 1 tower registered on MahaRERA.

When was SAI SNEH registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SAI SNEH was registered on MahaRERA on 3 May 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI SNEH?

No court cases are listed for SAI SNEH on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SAI SNEH?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NILESH DILIP KALE.