Bharat Arcade
by Pankaj Chauhan · Virar, Palghar
Possession date of Bharat Arcade: 31 March 2027, moved from 31 August 2019 (91 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000013206, and currently active. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Bharat Arcade?
How the possession date of Bharat Arcade has moved
31 August 2019
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA21022619937)
Reason the builder gave MahaRERA:
“Subject: Submission of Technical And Legal Reasons for Delay in Completion of the Project-31/3/2027, Maha RERA Reg. No P99000013206 Respected Sir, We, [Promoter/Developer Name], are the promoters of the real estate project known as "BHARAT…” Read the full reason
“Subject: Submission of Technical And Legal Reasons for Delay in Completion of the Project-31/3/2027, Maha RERA Reg. No P99000013206 Respected Sir, We, [Promoter/Developer Name], are the promoters of the real estate project known as "BHARAT ARCADE" bearing Maha RERA Registration No. P99000013206. 1.Court Stay Order on Project Construction stopped due to a stay from the High Court or Supreme Court. 2.Land Ownership/Title Dispute Ongoing litigation regarding land ownership preventing construction. 3. Environmental and Government Permission Case A case pending in court related to environmental…”
Source: Bharat Arcade’s extension records on MahaRERA (P99000013206), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Bharat Arcade
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000013206
- Status
- Registered and active
- Builder
- Pankaj Chauhan
- Location
- Virar, Palghar · 401303
- Project type
- Residential / Group Housing
- Registered on
- 21 Sep 2017
- Completion date at registration
- August 2019
- Latest completion date
- March 2027
- Delay so far
- 91 months
- Homes
- 47
- Sold or booked
- 72%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Bharat Arcade, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bharat Arcade | 100% | 100% | 40% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Bharat Arcade: covers plinth level
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bharat Arcade every month.
Bharat Arcade: buildings, flats and land, as filed on MahaRERA
- Buildings: Bharat Arcade (14 floors, 47 units)
- Land: 653 sq m (about 0.2 acres) · recreational space 223 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Bharat Arcade →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Bharat Arcade: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Bharat Arcade
What is the possession date of Bharat Arcade?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Bharat Arcade in Virar, Palghar is 31 March 2027 — 91 months later than 31 August 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Bharat Arcade?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Bharat Arcade's builder has filed on MahaRERA, the official one, is 31 March 2027, already 91 months later than the 31 August 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Bharat Arcade extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Bharat Arcade's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "Subject: Submission of Technical And Legal Reasons for Delay in Completion of the Project-31/3/2027, Maha RERA Reg. No P99000013206 Respected Sir, We, [Promoter/Developer Name], are the promoters of the real estate project known as "BHARAT ARCADE" bearing Maha RERA Registration No. P99000013206. 1.Court Stay Order on Project Construction stopped due to a stay from the High Court or Supreme Court. 2.Land Ownership/Title Dispute Ongoing litigation regarding land ownership preventing construction. 3. Environmental and Government Permission Case A case pending in court related to environmental…".
What is the RERA number of Bharat Arcade?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Bharat Arcade in Virar, Palghar is P99000013206.
Is Bharat Arcade registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bharat Arcade is registered as P99000013206 and its status is "Registered and active".
What is the construction status of Bharat Arcade?
According to GharKundli's check of MahaRERA records (updated October 2026), Bharat Arcade's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Bharat Arcade is 100% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.
Does Bharat Arcade have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Bharat Arcade safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Bharat Arcade is registered on MahaRERA as P99000013206, its completion date has moved 91 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Bharat Arcade's possession date changes?
The latest dates are on Bharat Arcade's MahaRERA page (P99000013206). GharKundli's Kundli Watch sends a free WhatsApp update on Bharat Arcade every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Bharat Arcade have?
According to GharKundli's check of MahaRERA records (updated October 2026), Bharat Arcade has one building filed: Bharat Arcade with 14 floors and 47 units.
How big is the land of Bharat Arcade?
According to GharKundli's check of MahaRERA records (updated October 2026), Bharat Arcade stands on 653 sq m of land (about 0.2 acres) and 223 sq m of recreational open space.
Where can I read reviews of Bharat Arcade?
Google Maps has reviews of Bharat Arcade written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Bharat Arcade?
Bharat Arcade by Pankaj Chauhan is in Virar, Palghar (pincode 401303), Maharashtra, and is registered on MahaRERA as P99000013206, per GharKundli's check of MahaRERA records.
How many homes are in Bharat Arcade?
According to GharKundli's check of MahaRERA records (updated October 2026), Bharat Arcade has 47 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.
When was Bharat Arcade registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bharat Arcade was registered on MahaRERA on 21 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Bharat Arcade?
No court cases are listed for Bharat Arcade on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Bharat Arcade?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pankaj Chauhan.
Check it yourself on MahaRERA
- How to check the possession date of Bharat Arcade
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Palghar →
Other projects in pincode 401303
- VIVA CITY - A5
- Bhakti Greens
- S M TOWER
- VIMALNATH Building no-2
- UNIQUE APARTMENT
- VALENCIA CHS
- Belle Vue 9
- SUPER HOMEZ-HARMONY PHASE III
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.