Kiran Swastik Building A

by KIRAN CREATORS AND DEVELOPERS PRIVATE LIMITED · Armament, Pune 411021Also near N.C.L. Pune

What’s in the report? →

Possession date of Kiran Swastik Building A (MahaRERA P52100047619): 31 March 2027, moved from 30 June 2026 (9 months later). It has 240 homes, 92% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100047619, and currently active.

Source: MahaRERA website — records for P52100047619, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Kiran Swastik Building A?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Kiran Swastik Building A has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 31 March 2027

    Extended at the builder's request (MahaRERA application EA29062621583)

    Reason the builder gave MahaRERA:
    “The Promoter respectfully submits that the project was duly registered with MahaRERA on 14/11/2022, with the scheduled date of completion being 30/06/2026. As on the date of this application, approximately 97% of the construction work of Ki…” Read the full reason“The Promoter respectfully submits that the project was duly registered with MahaRERA on 14/11/2022, with the scheduled date of completion being 30/06/2026. As on the date of this application, approximately 97% of the construction work of Kiran Swastik Building A stands completed, and only minor finishing works remain in progress. Accordingly, the Promoter seeks an extension of the project registration up to 31/03/2027 to complete the balance work and obtain the Completion Certificate and/or Occupancy Certificate, and therefore humbly prays that this Hon'ble Authority be pleased to grant the…”

Source: Kiran Swastik Building A’s extension records on MahaRERA (P52100047619), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Kiran Swastik Building A

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100047619
Status
Registered and active
Builder
KIRAN CREATORS AND DEVELOPERS PRIVATE LIMITED
Location
Armament, Pune · 411021
Project type
Residential / Group Housing
Registered on
14 Nov 2022
Completion date at registration
June 2026
Latest completion date
March 2027
Delay so far
9 months
Homes
240
Sold or booked
92%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Kiran Swastik Building A, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING A100%100%85%53%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING A: covers 27 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kiran Swastik Building A every 1–2 months.

Kiran Swastik Building A: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING A (27 floors, 240 units)
  • Car parking: 120 covered
  • Land: 784 sq m (about 0.2 acres) · sanctioned built-up 22,536 sq m · recreational space 911 sq m
  • Land, as filed: SURVEY NO 210/1, 210/2
  • Map: Get directions

The builder’s record and reviews

Kiran Creators & Developers Through Proprietor MR Kashinath Ganesh Nehete (a group of 4 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 10 finished, 8 within the promised date and 2 needed more time (typically 9 months); 7 still being built, 2 past the promised date (typically 14 months late). 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Kiran Swastik Building A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Kiran Swastik Building A: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Kiran Swastik Building A

What is the possession date of Kiran Swastik Building A?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kiran Swastik Building A in Armament, Pune is 31 March 2027 — 9 months later than 30 June 2026, the date given at registration.

The date has already moved 9 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Kiran Swastik Building A?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Kiran Swastik Building A's builder has filed on MahaRERA, the official one, is 31 March 2027, already 9 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Kiran Swastik Building A extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Swastik Building A's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The Promoter respectfully submits that the project was duly registered with MahaRERA on 14/11/2022, with the scheduled date of completion being 30/06/2026. As on the date of this application, approximately 97% of the construction work of Kiran Swastik Building A stands completed, and only minor finishing works remain in progress. Accordingly, the Promoter seeks an extension of the project registration up to 31/03/2027 to complete the balance work and obtain the Completion Certificate and/or Occupancy Certificate, and therefore humbly prays that this Hon'ble Authority be pleased to grant the…".

What is the RERA number of Kiran Swastik Building A?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kiran Swastik Building A in Armament, Pune is P52100047619.

Is Kiran Swastik Building A registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Swastik Building A is registered as P52100047619 and its status is "Registered and active".

What is the current construction status of Kiran Swastik Building A? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Swastik Building A's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING A is 100% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.

Does Kiran Swastik Building A have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Kiran Swastik Building A safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Swastik Building A is registered on MahaRERA as P52100047619, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Kiran Swastik Building A?

Kiran Swastik Building A is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Kiran Swastik Building A?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Kiran Swastik Building A: gharkundli.com/tools/property-cost-calculator

Has Kiran Swastik Building A received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Swastik Building A is still under construction, with 31 March 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Kiran Swastik Building A uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Kiran Swastik Building A was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Kiran Swastik Building A have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: KIRAN SWASTIK BUILDING B (PC1261012400016, possession 28 Feb 2029). Check that your agreement names the registration of your own wing.

How can I get updates if Kiran Swastik Building A's possession date changes?

The latest dates are on Kiran Swastik Building A's MahaRERA page (P52100047619). GharKundli's Kundli Watch sends a free WhatsApp update on Kiran Swastik Building A every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Kiran Swastik Building A have?

According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Swastik Building A has one building filed: BUILDING A with 27 floors and 240 units.

How much parking does Kiran Swastik Building A have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 120 covered car parking spaces for Kiran Swastik Building A.

How big is the land of Kiran Swastik Building A?

According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Swastik Building A stands on 784 sq m of land (about 0.2 acres), with 22,536 sq m of sanctioned built-up area and 911 sq m of recreational open space.

What is the track record of Kiran Swastik Building A's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Creators & Developers Through Proprietor MR Kashinath Ganesh Nehete (a group of 4 linked companies) has 17 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 10 finished, 8 within the promised date and 2 needed more time (typically 9 months); 7 still being built, 2 past the promised date (typically 14 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Kiran Swastik Building A?

Google Maps has reviews of Kiran Swastik Building A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Kiran Swastik Building A?

Kiran Swastik Building A by KIRAN CREATORS AND DEVELOPERS PRIVATE LIMITED is in Armament, Pune, pincode 411021 (near N.C.L. Pune), Maharashtra, and is registered on MahaRERA as P52100047619, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 210/1, 210/2. GharKundli lists all 332 MahaRERA projects in Armament (411021).

How many flats are in Kiran Swastik Building A, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Swastik Building A has 240 homes in 1 tower registered on MahaRERA, and 92% of them are sold or booked.

When was Kiran Swastik Building A registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Kiran Swastik Building A was registered on MahaRERA on 14 November 2022. GharKundli did not find a title report on the land on file there.

Does Kiran Swastik Building A have any legal issues or court cases?

No court cases are listed for Kiran Swastik Building A on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Kiran Swastik Building A?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KIRAN CREATORS AND DEVELOPERS PRIVATE LIMITED, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2027 in Pune →

Other projects in Armament (411021)

All 332 projects in Armament (411021) →

Other projects by KIRAN CREATORS AND DEVELOPERS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.