Skip to content
GharKundli

Wagholikar Heritage

by WAGHOLIKAR ASSOCIATES · Wagholikar Park, Pune

Possession date of Wagholikar Heritage: 31 May 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100050000. Status: In abeyance (on hold by MahaRERA). Its completion date is now May 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Wagholikar Heritage?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Wagholikar Heritage has moved

  1. 31 January 2028

    Completion date given when the project was registered

  2. 31 May 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Wagholikar Heritage’s extension records on MahaRERA (P52100050000), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Wagholikar Heritage

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100050000
Status
In abeyance (on hold by MahaRERA)
Builder
WAGHOLIKAR ASSOCIATES
Location
Wagholikar Park, Pune · 413102
Project type
Residential / Group Housing
Registered on
6 Mar 2023
Completion date at registration
January 2028
Latest completion date
May 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
32
Sold or booked
31%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Wagholikar Heritage, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wagholikar Heritage A20%0%0%0%
Wagholikar Heritage B100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Wagholikar Heritage A: covers 0 floors
  • Wagholikar Heritage B: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Wagholikar Heritage every month.

Wagholikar Heritage: buildings, flats and land, as filed on MahaRERA

  • Buildings: Wagholikar Heritage A (7 floors, 20 units) · Wagholikar Heritage B (6 floors, 12 units)
  • Land: 1,401 sq m (about 0.3 acres) · sanctioned built-up 3,137 sq m
  • Boundaries filed include: 6m wide colony road, 9m wide colony road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Wagholikar Heritage →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Wagholikar Heritage: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Wagholikar Heritage

What is the possession date of Wagholikar Heritage?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Wagholikar Heritage in Wagholikar Park, Pune is 31 May 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Wagholikar Heritage?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Wagholikar Heritage's builder has filed on MahaRERA, the official one, is 31 May 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Wagholikar Heritage?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Wagholikar Heritage in Wagholikar Park, Pune is P52100050000.

Is Wagholikar Heritage registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Wagholikar Heritage is registered as P52100050000 and its status is "In abeyance (on hold by MahaRERA)".

What is the construction status of Wagholikar Heritage?

According to GharKundli's check of MahaRERA records (updated November 2026), Wagholikar Heritage's status on MahaRERA is "In abeyance (on hold by MahaRERA)". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Wagholikar Heritage have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Wagholikar Heritage safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Wagholikar Heritage is registered on MahaRERA as P52100050000, its MahaRERA status is "In abeyance (on hold by MahaRERA)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Wagholikar Heritage's possession date changes?

The latest dates are on Wagholikar Heritage's MahaRERA page (P52100050000). GharKundli's Kundli Watch sends a free WhatsApp update on Wagholikar Heritage every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Wagholikar Heritage have?

According to GharKundli's check of MahaRERA records (updated November 2026), Wagholikar Heritage has 2 buildings filed: Wagholikar Heritage A with 7 floors and 20 units; Wagholikar Heritage B with 6 floors and 12 units.

How big is the land of Wagholikar Heritage?

According to GharKundli's check of MahaRERA records (updated November 2026), Wagholikar Heritage stands on 1,401 sq m of land (about 0.3 acres), with 3,137 sq m of sanctioned built-up area.

Where can I read reviews of Wagholikar Heritage?

Google Maps has reviews of Wagholikar Heritage written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Wagholikar Heritage?

Wagholikar Heritage by WAGHOLIKAR ASSOCIATES is in Wagholikar Park, Pune (pincode 413102), Maharashtra, and is registered on MahaRERA as P52100050000, per GharKundli's check of MahaRERA records. Its boundaries filed there include 6m wide colony road, 9m wide colony road.

How many homes are in Wagholikar Heritage?

According to GharKundli's check of MahaRERA records (updated November 2026), Wagholikar Heritage has 32 homes in 2 towers registered on MahaRERA, and 31% of them are sold or booked.

When was Wagholikar Heritage registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Wagholikar Heritage was registered on MahaRERA on 6 March 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Wagholikar Heritage?

No court cases are listed for Wagholikar Heritage on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Wagholikar Heritage?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is WAGHOLIKAR ASSOCIATES, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Pune →

Other projects in Baramati

All 213 projects in Baramati (413102) →

Other projects by WAGHOLIKAR ASSOCIATES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.