Possession date of Lavthaleshwar Heights: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100049346, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Lavthaleshwar Heights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Lavthaleshwar Heights has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Lavthaleshwar Heights’s extension records on MahaRERA (P52100049346), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Lavthaleshwar Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100049346
Status
Registered and active
Builder
Sachin Balkrushn Bayas proprietor of Lavthaleshwar developers
Location
Jejuri, Pune · 412303
Project type
Residential / Group Housing
Registered on
7 Feb 2023
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
63
Sold or booked
31%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Lavthaleshwar Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Lavthaleshwar Heights100%30%10%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lavthaleshwar Heights every month.

Lavthaleshwar Heights: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Lavthaleshwar Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Lavthaleshwar Heights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Lavthaleshwar Heights

What is the possession date of Lavthaleshwar Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Lavthaleshwar Heights in Jejuri, Pune is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Lavthaleshwar Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Lavthaleshwar Heights's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Lavthaleshwar Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Lavthaleshwar Heights in Jejuri, Pune is P52100049346.

Is Lavthaleshwar Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Lavthaleshwar Heights is registered as P52100049346 and its status is "Registered and active".

What is the construction status of Lavthaleshwar Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Lavthaleshwar Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Lavthaleshwar Heights is 30% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.

Does Lavthaleshwar Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Lavthaleshwar Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Lavthaleshwar Heights is registered on MahaRERA as P52100049346, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Lavthaleshwar Heights's possession date changes?

The latest dates are on Lavthaleshwar Heights's MahaRERA page (P52100049346). GharKundli's Kundli Watch sends a free WhatsApp update on Lavthaleshwar Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Lavthaleshwar Heights have?

According to GharKundli's check of MahaRERA records (updated November 2026), Lavthaleshwar Heights has one building filed: Lavthaleshwar Heights with 10 floors.

How big is the land of Lavthaleshwar Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Lavthaleshwar Heights stands on 2,837 sq m of land (about 0.7 acres), with 6,410 sq m of sanctioned built-up area and 1 sq m of recreational open space.

Where can I read reviews of Lavthaleshwar Heights?

Google Maps has reviews of Lavthaleshwar Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Lavthaleshwar Heights?

Lavthaleshwar Heights by Sachin Balkrushn Bayas proprietor of Lavthaleshwar developers is in Jejuri, Pune (pincode 412303), Maharashtra, and is registered on MahaRERA as P52100049346, per GharKundli's check of MahaRERA records.

How many homes are in Lavthaleshwar Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), Lavthaleshwar Heights has 63 homes in 1 tower registered on MahaRERA, and 31% of them are sold or booked.

When was Lavthaleshwar Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Lavthaleshwar Heights was registered on MahaRERA on 7 February 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Lavthaleshwar Heights?

No court cases are listed for Lavthaleshwar Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Lavthaleshwar Heights?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sachin Balkrushn Bayas proprietor of Lavthaleshwar developers, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Pune →

Other projects in pincode 412303

All 9 projects in Jejuri (412303) →

Other projects by Sachin Balkrushn Bayas proprietor of Lavthaleshwar developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.