DESTINATION EL PROGRESO B BUILDING
by EL PROGRESO LANDMARKS (Gavhane) · Borhadewadi, Pune
Possession date of DESTINATION EL PROGRESO B BUILDING: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100049452, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about DESTINATION EL PROGRESO B BUILDING?
How the possession date of DESTINATION EL PROGRESO B BUILDING has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: DESTINATION EL PROGRESO B BUILDING’s extension records on MahaRERA (P52100049452), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DESTINATION EL PROGRESO B BUILDING
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100049452
- Status
- Registered and active
- Builder
- EL PROGRESO LANDMARKS
- Location
- Borhadewadi, Pune · 412105
- Project type
- Others
- Registered on
- 14 Feb 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 156
- Sold or booked
- 81%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of DESTINATION EL PROGRESO B BUILDING, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| B BUILDING | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- B BUILDING: covers 16 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DESTINATION EL PROGRESO B BUILDING every month.
DESTINATION EL PROGRESO B BUILDING: buildings, flats and land, as filed on MahaRERA
- Buildings: B BUILDING (12 floors, 170 units)
- Land: 3,950 sq m (about 1.0 acres) · sanctioned built-up 6,910 sq m · recreational space 395 sq m
The builder’s record and reviews
D R Gavhane Landmarks (a group of 4 linked companies) has 19 projects on MahaRERA since 2020, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 9 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of DESTINATION EL PROGRESO B BUILDING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DESTINATION EL PROGRESO B BUILDING: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DESTINATION EL PROGRESO B BUILDING
What is the possession date of DESTINATION EL PROGRESO B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DESTINATION EL PROGRESO B BUILDING in Borhadewadi, Pune is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for DESTINATION EL PROGRESO B BUILDING?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DESTINATION EL PROGRESO B BUILDING's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of DESTINATION EL PROGRESO B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DESTINATION EL PROGRESO B BUILDING in Borhadewadi, Pune is P52100049452.
Is DESTINATION EL PROGRESO B BUILDING registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DESTINATION EL PROGRESO B BUILDING is registered as P52100049452 and its status is "Registered and active".
What is the construction status of DESTINATION EL PROGRESO B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), DESTINATION EL PROGRESO B BUILDING's status on MahaRERA is "Registered and active". As filed by the builder, slab work on B BUILDING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does DESTINATION EL PROGRESO B BUILDING have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is DESTINATION EL PROGRESO B BUILDING safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), DESTINATION EL PROGRESO B BUILDING is registered on MahaRERA as P52100049452, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DESTINATION EL PROGRESO B BUILDING's possession date changes?
The latest dates are on DESTINATION EL PROGRESO B BUILDING's MahaRERA page (P52100049452). GharKundli's Kundli Watch sends a free WhatsApp update on DESTINATION EL PROGRESO B BUILDING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DESTINATION EL PROGRESO B BUILDING have?
According to GharKundli's check of MahaRERA records (updated November 2026), DESTINATION EL PROGRESO B BUILDING has one building filed: B BUILDING with 12 floors and 170 units.
How big is the land of DESTINATION EL PROGRESO B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), DESTINATION EL PROGRESO B BUILDING stands on 3,950 sq m of land (about 1.0 acres), with 6,910 sq m of sanctioned built-up area and 395 sq m of recreational open space.
What is the track record of DESTINATION EL PROGRESO B BUILDING's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), D R Gavhane Landmarks (a group of 4 linked companies) has 19 projects on MahaRERA since 2020, this one included. Of the 11 GharKundli has checked: 1 finished, all within the promised date; 9 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of DESTINATION EL PROGRESO B BUILDING?
Google Maps has reviews of DESTINATION EL PROGRESO B BUILDING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DESTINATION EL PROGRESO B BUILDING?
DESTINATION EL PROGRESO B BUILDING by EL PROGRESO LANDMARKS (Gavhane) is in Borhadewadi, Pune (pincode 412105), Maharashtra, and is registered on MahaRERA as P52100049452, per GharKundli's check of MahaRERA records.
How many homes are in DESTINATION EL PROGRESO B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), DESTINATION EL PROGRESO B BUILDING has 156 homes in 1 tower registered on MahaRERA, and 81% of them are sold or booked.
When was DESTINATION EL PROGRESO B BUILDING registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DESTINATION EL PROGRESO B BUILDING was registered on MahaRERA on 14 February 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on DESTINATION EL PROGRESO B BUILDING?
1 court case is listed for DESTINATION EL PROGRESO B BUILDING on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of DESTINATION EL PROGRESO B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is EL PROGRESO LANDMARKS, the company Gavhane files this project under.
Check it yourself on MahaRERA
- How to check the possession date of DESTINATION EL PROGRESO B BUILDING
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Borhadewadi
- ARIHANT WISDOM
- Rajput Ekyum
- SKYLINE PRIDE
- ANTHESIS
- DWAARKA WORLD PH 1
- KAMALRAJ DATTAVIHAR E AND H
- VTB RIVERIA
- SILVER GARDENIA
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.