Possession date of TRIMURTI SANTKRUPA HEIGHTS: 31 March 2027, moved from 26 August 2026 (7 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100050150, and currently active.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about TRIMURTI SANTKRUPA HEIGHTS?
How the possession date of TRIMURTI SANTKRUPA HEIGHTS has moved
26 August 2026
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA28082622417)
Reason the builder gave MahaRERA:
“Grounds for Extension 1. Delay in Approval of Revised Sanction Plan The revised building proposal remained pending before the Competent Planning Authority for a considerable period. As the execution of the balance construction activities wa…” Read the full reason
“Grounds for Extension 1. Delay in Approval of Revised Sanction Plan The revised building proposal remained pending before the Competent Planning Authority for a considerable period. As the execution of the balance construction activities was dependent upon the revised sanction, the project completion schedule was inevitably affected. 2. Consequential Statutory Approvals Pursuant to the revised sanction process, statutory approvals including TDR approval and other mandatory departmental clearances were also received after considerable time. These approvals were essential for completion of th…”
Source: TRIMURTI SANTKRUPA HEIGHTS’s extension records on MahaRERA (P52100050150), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on TRIMURTI SANTKRUPA HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100050150
- Status
- Registered and active
- Builder
- SAMBHAJI BABAN BORHADE
- Location
- Dehu, Pune · 412109
- Project type
- Others
- Registered on
- 21 Mar 2023
- Completion date at registration
- August 2026
- Latest completion date
- March 2027
- Delay so far
- 7 months
- Homes
- 20
- Sold or booked
- 35%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of TRIMURTI SANTKRUPA HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| TRIMURTI SANTKRUPA HEIGHTS | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- TRIMURTI SANTKRUPA HEIGHTS: covers 6 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on TRIMURTI SANTKRUPA HEIGHTS every month.
TRIMURTI SANTKRUPA HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: TRIMURTI SANTKRUPA HEIGHTS (7 floors, 40 units)
- Land: 1,466 sq m (about 0.4 acres) · sanctioned built-up 2,026 sq m
The builder’s record and reviews
Sambhaji Baban Borhade has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of TRIMURTI SANTKRUPA HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
TRIMURTI SANTKRUPA HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about TRIMURTI SANTKRUPA HEIGHTS
What is the possession date of TRIMURTI SANTKRUPA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for TRIMURTI SANTKRUPA HEIGHTS in Dehu, Pune is 31 March 2027 — 7 months later than 26 August 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for TRIMURTI SANTKRUPA HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date TRIMURTI SANTKRUPA HEIGHTS's builder has filed on MahaRERA, the official one, is 31 March 2027, already 7 months later than the 26 August 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of TRIMURTI SANTKRUPA HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated November 2026), TRIMURTI SANTKRUPA HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "Grounds for Extension 1. Delay in Approval of Revised Sanction Plan The revised building proposal remained pending before the Competent Planning Authority for a considerable period. As the execution of the balance construction activities was dependent upon the revised sanction, the project completion schedule was inevitably affected. 2. Consequential Statutory Approvals Pursuant to the revised sanction process, statutory approvals including TDR approval and other mandatory departmental clearances were also received after considerable time. These approvals were essential for completion of th…".
What is the RERA number of TRIMURTI SANTKRUPA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of TRIMURTI SANTKRUPA HEIGHTS in Dehu, Pune is P52100050150.
Is TRIMURTI SANTKRUPA HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), TRIMURTI SANTKRUPA HEIGHTS is registered as P52100050150 and its status is "Registered and active".
What is the construction status of TRIMURTI SANTKRUPA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), TRIMURTI SANTKRUPA HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on TRIMURTI SANTKRUPA HEIGHTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does TRIMURTI SANTKRUPA HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is TRIMURTI SANTKRUPA HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), TRIMURTI SANTKRUPA HEIGHTS is registered on MahaRERA as P52100050150, its completion date has moved 7 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if TRIMURTI SANTKRUPA HEIGHTS's possession date changes?
The latest dates are on TRIMURTI SANTKRUPA HEIGHTS's MahaRERA page (P52100050150). GharKundli's Kundli Watch sends a free WhatsApp update on TRIMURTI SANTKRUPA HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does TRIMURTI SANTKRUPA HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated November 2026), TRIMURTI SANTKRUPA HEIGHTS has one building filed: TRIMURTI SANTKRUPA HEIGHTS with 7 floors and 40 units.
How big is the land of TRIMURTI SANTKRUPA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), TRIMURTI SANTKRUPA HEIGHTS stands on 1,466 sq m of land (about 0.4 acres), with 2,026 sq m of sanctioned built-up area.
What is the track record of TRIMURTI SANTKRUPA HEIGHTS's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Sambhaji Baban Borhade has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of TRIMURTI SANTKRUPA HEIGHTS?
Google Maps has reviews of TRIMURTI SANTKRUPA HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is TRIMURTI SANTKRUPA HEIGHTS?
TRIMURTI SANTKRUPA HEIGHTS by SAMBHAJI BABAN BORHADE is in Dehu, Pune (pincode 412109), Maharashtra, and is registered on MahaRERA as P52100050150, per GharKundli's check of MahaRERA records.
How many homes are in TRIMURTI SANTKRUPA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), TRIMURTI SANTKRUPA HEIGHTS has 20 homes in 1 tower registered on MahaRERA, and 35% of them are sold or booked.
When was TRIMURTI SANTKRUPA HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), TRIMURTI SANTKRUPA HEIGHTS was registered on MahaRERA on 21 March 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on TRIMURTI SANTKRUPA HEIGHTS?
No court cases are listed for TRIMURTI SANTKRUPA HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of TRIMURTI SANTKRUPA HEIGHTS?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAMBHAJI BABAN BORHADE.
Check it yourself on MahaRERA
- How to check the possession date of TRIMURTI SANTKRUPA HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in pincode 412109
- Samarth Leela Heights Phase I
- SHIVKUNJ
- Gathagram Sector 2
- Gathagram Sector 5 Phase 1
- VRUNDAVAN RESIDENCIES
- GATHAGRAM SECTOR-3 PHASE-1
- Dwarka Heights
- Arunya A Wing
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.