MARIAM PARK COMPLEX

by SHAMSHAD & SONS PROPERTY PVT LTD · Papdi, Palghar

Possession date of MARIAM PARK COMPLEX: 30 April 2030, moved from 30 June 2021 (102 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000014057, and currently active. Its completion date has moved from June 2021 to April 2030: 102 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about MARIAM PARK COMPLEX?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MARIAM PARK COMPLEX has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT99000009795)

    Reason the builder gave MahaRERA:
    “it is respectfully submitted that the suo motu extension of the validity granted by Maharera is coming to an end. it is further submitted that the extension has served the limited purpose only as owing to continuation of COVID-19 pandemic w…” Read the full reason“it is respectfully submitted that the suo motu extension of the validity granted by Maharera is coming to an end. it is further submitted that the extension has served the limited purpose only as owing to continuation of COVID-19 pandemic we are suffering acute shortage of labor supply Occasionally we get the labor supply, but that is up to the extent of 50% than what is required. In circumstances like this we are not able to complete the construction on the extended date 30-06-2021. Therefore, we hereby request you to grant us extension as per online application field. Obiged”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT99000013449)

    Reason the builder gave MahaRERA: “CC Revised to 5th floor and for this reason there is delay in completion of project which we mutually taken consent from all our allottees for extension and same declaration is attach for extension.”
  4. 31 December 2029

    Extended at the builder's request (MahaRERA application EA22122518905)

    Reason the builder gave MahaRERA:
    “We respectfully submit that the construction of the project is being carried out strictly in accordance with the sanctioned plans and approved construction schedule. The execution of the project involves multiple sequential and inter-depend…” Read the full reason“We respectfully submit that the construction of the project is being carried out strictly in accordance with the sanctioned plans and approved construction schedule. The execution of the project involves multiple sequential and inter-dependent activities including structural works, internal finishing, services installations, and external site development, all of which are required to be completed in a phased and regulated manner. While major structural and finishing works have been completed / are nearing completion, certain essential services and external development works such as lifts, f…”
  5. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: MARIAM PARK COMPLEX’s extension records on MahaRERA (P99000014057), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MARIAM PARK COMPLEX

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000014057
Status
Registered and active
Builder
SHAMSHAD & SONS PROPERTY PVT LTD
Location
Papdi, Palghar · 401207
Project type
Residential / Group Housing
Registered on
7 Nov 2017
Completion date at registration
June 2021
Latest completion date
April 2030
Delay so far
102 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
116
Sold or booked
65%
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MARIAM PARK COMPLEX, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 7100%100%100%100%
Building No 8100%100%40%0%
Building No 90%0%0%0%
CFC Building0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING NO 7: covers 5 floors
  • Building No 8: covers 8 floors
  • Building No 9: covers 8 floors
  • CFC Building: covers 4 floors

Latest CC order on MahaRERA: dated 15/07/2024.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MARIAM PARK COMPLEX every month.

MARIAM PARK COMPLEX: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 7 (7 floors, 60 units) · Building No 8 (8 floors, 49 units) · Building No 9 (8 floors, 7 units) · CFC Building (4 floors, 10 units)
  • Car parking: 28 open
  • Land: 3,842 sq m (about 0.9 acres) · sanctioned built-up 6,473 sq m · recreational space 1,514 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MARIAM PARK COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MARIAM PARK COMPLEX: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MARIAM PARK COMPLEX

What is the possession date of MARIAM PARK COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MARIAM PARK COMPLEX in Papdi, Palghar is 30 April 2030 — 102 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for MARIAM PARK COMPLEX?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MARIAM PARK COMPLEX's builder has filed on MahaRERA, the official one, is 30 April 2030, already 102 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MARIAM PARK COMPLEX extended?

According to GharKundli's check of MahaRERA records (updated October 2026), MARIAM PARK COMPLEX's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2022, giving the reason "it is respectfully submitted that the suo motu extension of the validity granted by Maharera is coming to an end. it is further submitted that the extension has served the limited purpose only as owing to continuation of COVID-19 pandemic we are suffering acute shortage of labor supply Occasionally we get the labor supply, but that is up to the extent of 50% than what is required. In circumstances like this we are not able to complete the construction on the extended date 30-06-2021. Therefore, we hereby request you to grant us extension as per online application field. Obiged"; to 31 December 2025, giving the reason "CC Revised to 5th floor and for this reason there is delay in completion of project which we mutually taken consent from all our allottees for extension and same declaration is attach for extension."; to 31 December 2029, giving the reason "We respectfully submit that the construction of the project is being carried out strictly in accordance with the sanctioned plans and approved construction schedule. The execution of the project involves multiple sequential and inter-dependent activities including structural works, internal finishing, services installations, and external site development, all of which are required to be completed in a phased and regulated manner. While major structural and finishing works have been completed / are nearing completion, certain essential services and external development works such as lifts, f…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of MARIAM PARK COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MARIAM PARK COMPLEX in Papdi, Palghar is P99000014057.

Is MARIAM PARK COMPLEX registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MARIAM PARK COMPLEX is registered as P99000014057 and its status is "Registered and active".

What is the construction status of MARIAM PARK COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), MARIAM PARK COMPLEX's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does MARIAM PARK COMPLEX have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is MARIAM PARK COMPLEX safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), MARIAM PARK COMPLEX is registered on MahaRERA as P99000014057, its completion date has moved 102 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MARIAM PARK COMPLEX's possession date changes?

The latest dates are on MARIAM PARK COMPLEX's MahaRERA page (P99000014057). GharKundli's Kundli Watch sends a free WhatsApp update on MARIAM PARK COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MARIAM PARK COMPLEX have?

According to GharKundli's check of MahaRERA records (updated October 2026), MARIAM PARK COMPLEX has 4 buildings filed: BUILDING NO 7 with 7 floors and 60 units; Building No 8 with 8 floors and 49 units; Building No 9 with 8 floors and 7 units; CFC Building with 4 floors and 10 units.

How much parking does MARIAM PARK COMPLEX have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 28 open car parking spaces for MARIAM PARK COMPLEX.

How big is the land of MARIAM PARK COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), MARIAM PARK COMPLEX stands on 3,842 sq m of land (about 0.9 acres), with 6,473 sq m of sanctioned built-up area and 1,514 sq m of recreational open space.

Where can I read reviews of MARIAM PARK COMPLEX?

Google Maps has reviews of MARIAM PARK COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MARIAM PARK COMPLEX?

MARIAM PARK COMPLEX by SHAMSHAD & SONS PROPERTY PVT LTD is in Papdi, Palghar (pincode 401207), Maharashtra, and is registered on MahaRERA as P99000014057, per GharKundli's check of MahaRERA records.

How many homes are in MARIAM PARK COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), MARIAM PARK COMPLEX has 116 homes in 4 towers registered on MahaRERA, and 65% of them are sold or booked.

When was MARIAM PARK COMPLEX registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), MARIAM PARK COMPLEX was registered on MahaRERA on 7 November 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on MARIAM PARK COMPLEX?

No court cases are listed for MARIAM PARK COMPLEX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of MARIAM PARK COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHAMSHAD & SONS PROPERTY PVT LTD.

All projects with possession due in 2030 in Palghar →

Other projects in pincode 401207

All 22 projects in Papdi (401207) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.