ZENONE B BUILDING
by K & T INFRASTRUCTURE · Athar Showroom Wakad, Pune
Possession date of ZENONE B BUILDING: 30 January 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100053350, and currently active. Its completion date is now January 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about ZENONE B BUILDING?
How the possession date of ZENONE B BUILDING has moved
30 September 2027
Completion date given when the project was registered
30 January 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ZENONE B BUILDING’s extension records on MahaRERA (P52100053350), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ZENONE B BUILDING
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100053350
- Status
- Registered and active
- Builder
- K & T INFRASTRUCTURE
- Location
- Athar Showroom Wakad, Pune · 411057
- Project type
- Residential / Group Housing
- Registered on
- 27 Oct 2023
- Completion date at registration
- September 2027
- Latest completion date
- January 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 94
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ZENONE B BUILDING, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| B BUILDING | 90% | 65% | 20% | 10% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ZENONE B BUILDING every month.
ZENONE B BUILDING: buildings, flats and land, as filed on MahaRERA
- Buildings: B BUILDING (14 floors)
- Land: 9,600 sq m (about 2.4 acres) · sanctioned built-up 2,905 sq m · recreational space 875 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ZENONE B BUILDING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ZENONE B BUILDING: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ZENONE B BUILDING
What is the possession date of ZENONE B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ZENONE B BUILDING in Athar Showroom Wakad, Pune is 30 January 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ZENONE B BUILDING?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ZENONE B BUILDING's builder has filed on MahaRERA, the official one, is 30 January 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ZENONE B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ZENONE B BUILDING in Athar Showroom Wakad, Pune is P52100053350.
Is ZENONE B BUILDING registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ZENONE B BUILDING is registered as P52100053350 and its status is "Registered and active".
What is the construction status of ZENONE B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), ZENONE B BUILDING's status on MahaRERA is "Registered and active". As filed by the builder, slab work on B BUILDING is 65% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.
Does ZENONE B BUILDING have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is ZENONE B BUILDING safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ZENONE B BUILDING is registered on MahaRERA as P52100053350, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ZENONE B BUILDING's possession date changes?
The latest dates are on ZENONE B BUILDING's MahaRERA page (P52100053350). GharKundli's Kundli Watch sends a free WhatsApp update on ZENONE B BUILDING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ZENONE B BUILDING have?
According to GharKundli's check of MahaRERA records (updated November 2026), ZENONE B BUILDING has one building filed: B BUILDING with 14 floors.
How big is the land of ZENONE B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), ZENONE B BUILDING stands on 9,600 sq m of land (about 2.4 acres), with 2,905 sq m of sanctioned built-up area and 875 sq m of recreational open space.
Where can I read reviews of ZENONE B BUILDING?
Google Maps has reviews of ZENONE B BUILDING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ZENONE B BUILDING?
ZENONE B BUILDING by K & T INFRASTRUCTURE is in Athar Showroom Wakad, Pune (pincode 411057), Maharashtra, and is registered on MahaRERA as P52100053350, per GharKundli's check of MahaRERA records.
How many homes are in ZENONE B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), ZENONE B BUILDING has 94 homes in 1 tower registered on MahaRERA.
When was ZENONE B BUILDING registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ZENONE B BUILDING was registered on MahaRERA on 27 October 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on ZENONE B BUILDING?
No court cases are listed for ZENONE B BUILDING on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of ZENONE B BUILDING?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is K & T INFRASTRUCTURE.
Check it yourself on MahaRERA
- How to check the possession date of ZENONE B BUILDING
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Pune →
Other projects in Mulshi
- Nirman Serenopolis
- Signature Park Phase - I
- LOTUS CREST
- Mahindra Rivenza Phase 2
- West World
- Mahindra Rivenza Phase 1
- Goodland Phase-III
- VYOMORA PHASE 1
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.