Possession date of Skyi Star City Phase VII: 31 May 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100053471, and currently active.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Skyi Star City Phase VII?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Skyi Star City Phase VII

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the May 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100053471
Status
Registered and active
Builder
Skyi Property Ventures LLP
Location
Kirkatwadi, Pune · 411024
Project type
Residential / Group Housing
Registered on
6 Nov 2023
Completion date at registration
May 2027
Homes
72
Sold or booked
97%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Skyi Star City Phase VII, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Tower K100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Tower K: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Skyi Star City Phase VII every month.

Skyi Star City Phase VII: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Enerrgia Skyi Developers (a group of 8 linked companies) has 48 projects on MahaRERA since 2017, this one included. Of the 30 GharKundli has checked: 1 finished, all within the promised date; 23 still being built, 4 past the promised date (typically 13 months late); 6 lapsed. 19 complaints on MahaRERA across 9 projects.

Read Google reviews of Skyi Star City Phase VII →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Skyi Star City Phase VII: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Skyi Star City Phase VII

What is the possession date of Skyi Star City Phase VII?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Skyi Star City Phase VII in Kirkatwadi, Pune is 31 May 2027.

Is the builder's possession date different from the MahaRERA date for Skyi Star City Phase VII?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Skyi Star City Phase VII's builder has filed on MahaRERA, the official one, is 31 May 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Skyi Star City Phase VII?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Skyi Star City Phase VII in Kirkatwadi, Pune is P52100053471.

Is Skyi Star City Phase VII registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star City Phase VII is registered as P52100053471 and its status is "Registered and active".

What is the construction status of Skyi Star City Phase VII?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star City Phase VII's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Tower K is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Skyi Star City Phase VII have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Skyi Star City Phase VII safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star City Phase VII is registered on MahaRERA as P52100053471, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Skyi Star City Phase VII have other wings or phases?

Yes. MahaRERA lists 7 other registrations of the same project, each with its own possession date: Skyi Star City Phase I (P52100026727, possession 29 Mar 2025); Skyi Star City Phase II (P52100029481, possession 31 Mar 2025); Skyi Star City Phase III (P52100029474, possession 31 Dec 2025); Skyi Star City Phase IV (P52100034274, possession 31 Mar 2027); Skyi Star City Phase V (P52100050099, possession 30 Sep 2027); Skyi Star City Phase VI (P52100053428, possession 31 Mar 2028); and 1 more. Check that your agreement names the registration of your own wing.

How can I get updates if Skyi Star City Phase VII's possession date changes?

The latest dates are on Skyi Star City Phase VII's MahaRERA page (P52100053471). GharKundli's Kundli Watch sends a free WhatsApp update on Skyi Star City Phase VII every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Skyi Star City Phase VII have?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star City Phase VII has one building filed: Tower K with 9 floors and 72 units.

How big is the land of Skyi Star City Phase VII?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star City Phase VII stands on 4,263 sq m of land (about 1.1 acres), with 4,362 sq m of sanctioned built-up area and 6,850 sq m of recreational open space.

What is the track record of Skyi Star City Phase VII's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Enerrgia Skyi Developers (a group of 8 linked companies) has 48 projects on MahaRERA since 2017, this one included. Of the 30 GharKundli has checked: 1 finished, all within the promised date; 23 still being built, 4 past the promised date (typically 13 months late); 6 lapsed. 19 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Skyi Star City Phase VII?

Google Maps has reviews of Skyi Star City Phase VII written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Skyi Star City Phase VII?

Skyi Star City Phase VII by Skyi Property Ventures LLP (Enerrgia) is in Kirkatwadi, Pune (pincode 411024), near Dhayari, Khadakwasla R.S, Maharashtra, and is registered on MahaRERA as P52100053471, per GharKundli's check of MahaRERA records.

How many homes are in Skyi Star City Phase VII?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star City Phase VII has 72 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.

When was Skyi Star City Phase VII registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Skyi Star City Phase VII was registered on MahaRERA on 6 November 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Skyi Star City Phase VII?

1 court case is listed for Skyi Star City Phase VII on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Skyi Star City Phase VII?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Skyi Property Ventures LLP, the company Enerrgia files this project under, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2027 in Pune →

Other projects in Kirkatwadi

All 39 projects in Kirkatwadi (411024) →

Other projects by Skyi Property Ventures LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.