47 East - C Mhada
by Kumar Properties and Developers LLP · Mundhwa, PuneAlso near Hadapsar, kharadi, Amanora Park Town
Possession date of 47 East - C Mhada: 30 August 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100053775, and currently active. Its completion date is now August 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about 47 East - C Mhada?
How the possession date of 47 East - C Mhada has moved
30 April 2027
Completion date given when the project was registered
30 August 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: 47 East - C Mhada’s extension records on MahaRERA (P52100053775), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 47 East - C Mhada
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the August 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100053775
- Status
- Registered and active
- Builder
- Kumar Properties and Developers LLP
- Location
- Mundhwa, Pune · 411028
- Project type
- Residential / Group Housing
- Registered on
- 28 Nov 2023
- Completion date at registration
- April 2027
- Latest completion date
- August 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 69
- Sold or booked
- 84%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of 47 East - C Mhada, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C | 100% | 76% | 27% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- C: covers 21 floors
Latest CC order on MahaRERA: dated 22/12/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 47 East - C Mhada every month.
47 East - C Mhada: buildings, flats and land, as filed on MahaRERA
- Buildings: C (21 floors, 69 units)
- Car parking: 37 covered
- Land: 1,456 sq m (about 0.4 acres) · sanctioned built-up 4,178 sq m · recreational space 1,900 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of 47 East - C Mhada →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
47 East - C Mhada: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about 47 East - C Mhada
What is the possession date of 47 East - C Mhada?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 47 East - C Mhada in Mundhwa, Pune is 30 August 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for 47 East - C Mhada?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 47 East - C Mhada's builder has filed on MahaRERA, the official one, is 30 August 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of 47 East - C Mhada?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 47 East - C Mhada in Mundhwa, Pune is P52100053775.
Is 47 East - C Mhada registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 47 East - C Mhada is registered as P52100053775 and its status is "Registered and active".
What is the construction status of 47 East - C Mhada?
According to GharKundli's check of MahaRERA records (updated November 2026), 47 East - C Mhada's status on MahaRERA is "Registered and active". As filed by the builder, slab work on C is 76% done and internal work 27%. GharKundli's full report compares construction progress with the deadline.
Does 47 East - C Mhada have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is 47 East - C Mhada safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), 47 East - C Mhada is registered on MahaRERA as P52100053775, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if 47 East - C Mhada's possession date changes?
The latest dates are on 47 East - C Mhada's MahaRERA page (P52100053775). GharKundli's Kundli Watch sends a free WhatsApp update on 47 East - C Mhada every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 47 East - C Mhada have?
According to GharKundli's check of MahaRERA records (updated November 2026), 47 East - C Mhada has one building filed: C with 21 floors and 69 units.
How much parking does 47 East - C Mhada have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 37 covered car parking spaces for 47 East - C Mhada.
How big is the land of 47 East - C Mhada?
According to GharKundli's check of MahaRERA records (updated November 2026), 47 East - C Mhada stands on 1,456 sq m of land (about 0.4 acres), with 4,178 sq m of sanctioned built-up area and 1,900 sq m of recreational open space.
Where can I read reviews of 47 East - C Mhada?
Google Maps has reviews of 47 East - C Mhada written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is 47 East - C Mhada?
47 East - C Mhada by Kumar Properties and Developers LLP is in Mundhwa, Pune (pincode 411028), near Hadapsar, kharadi, Amanora Park Town, Maharashtra, and is registered on MahaRERA as P52100053775, per GharKundli's check of MahaRERA records.
How many homes are in 47 East - C Mhada?
According to GharKundli's check of MahaRERA records (updated November 2026), 47 East - C Mhada has 69 homes in 1 tower registered on MahaRERA, and 84% of them are sold or booked.
When was 47 East - C Mhada registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 47 East - C Mhada was registered on MahaRERA on 28 November 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on 47 East - C Mhada?
1 court case is listed for 47 East - C Mhada on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of 47 East - C Mhada?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Kumar Properties and Developers LLP, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of 47 East - C Mhada
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Mundhwa
- 47 East- B (Wing B)
- Jhamtani BizCore
- Atulyam-Inclusive Housing
- Jhamtani Elevate
- Indeco Tech Park
- Indeco SB73
- Mayfair Residences Phase 2
- Clover Business Center
Other projects by Kumar Properties and Developers LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.