Skip to content
GharKundli

Hornbill Heights at Riverview City

by Riverview City Constructions Ltd (Magarpatta) · Kadamwakwasti, PuneAlso near Loni Kalbhor

Possession date of Hornbill Heights at Riverview City: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100053795, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Hornbill Heights at Riverview City?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Hornbill Heights at Riverview City has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Hornbill Heights at Riverview City’s extension records on MahaRERA (P52100053795), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Hornbill Heights at Riverview City

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100053795
Status
Registered and active
Builder
Riverview City Constructions Ltd
Location
Kadamwakwasti, Pune · 412201
Project type
Residential / Group Housing
Registered on
30 Nov 2023
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
672
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Hornbill Heights at Riverview City, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A100%0%0%25%
B100%0%0%25%
C100%0%0%25%
D100%0%0%25%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hornbill Heights at Riverview City every month.

Hornbill Heights at Riverview City: buildings, flats and land, as filed on MahaRERA

  • Buildings: A (23 floors) · B (23 floors) · C (23 floors) · D (23 floors)
  • Land: 27,245 sq m (about 6.7 acres) · sanctioned built-up 69,235 sq m · recreational space 2,725 sq m

The builder’s record and reviews

Nanded City Development & Construction (a group of 4 linked companies) has 29 projects on MahaRERA since 2021, this one included. Of the 12 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 1 months); 9 still being built, none past the promised date yet. 9 complaints on MahaRERA across 3 projects.

Read Google reviews of Hornbill Heights at Riverview City →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Hornbill Heights at Riverview City: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Hornbill Heights at Riverview City

What is the possession date of Hornbill Heights at Riverview City?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Hornbill Heights at Riverview City in Kadamwakwasti, Pune is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Hornbill Heights at Riverview City?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Hornbill Heights at Riverview City's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Hornbill Heights at Riverview City?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Hornbill Heights at Riverview City in Kadamwakwasti, Pune is P52100053795.

Is Hornbill Heights at Riverview City registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Hornbill Heights at Riverview City is registered as P52100053795 and its status is "Registered and active".

What is the construction status of Hornbill Heights at Riverview City?

According to GharKundli's check of MahaRERA records (updated November 2026), Hornbill Heights at Riverview City's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Hornbill Heights at Riverview City have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Hornbill Heights at Riverview City safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Hornbill Heights at Riverview City is registered on MahaRERA as P52100053795, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Hornbill Heights at Riverview City's possession date changes?

The latest dates are on Hornbill Heights at Riverview City's MahaRERA page (P52100053795). GharKundli's Kundli Watch sends a free WhatsApp update on Hornbill Heights at Riverview City every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Hornbill Heights at Riverview City have?

According to GharKundli's check of MahaRERA records (updated November 2026), Hornbill Heights at Riverview City has 4 buildings filed: A with 23 floors; B with 23 floors; C with 23 floors; D with 23 floors.

How big is the land of Hornbill Heights at Riverview City?

According to GharKundli's check of MahaRERA records (updated November 2026), Hornbill Heights at Riverview City stands on 27,245 sq m of land (about 6.7 acres), with 69,235 sq m of sanctioned built-up area and 2,725 sq m of recreational open space.

What is the track record of Hornbill Heights at Riverview City's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Nanded City Development & Construction (a group of 4 linked companies) has 29 projects on MahaRERA since 2021, this one included. Of the 12 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 1 months); 9 still being built, none past the promised date yet. 9 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Hornbill Heights at Riverview City?

Google Maps has reviews of Hornbill Heights at Riverview City written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Hornbill Heights at Riverview City?

Hornbill Heights at Riverview City by Riverview City Constructions Ltd (Magarpatta) is in Kadamwakwasti, Pune (pincode 412201), near Loni Kalbhor, Maharashtra, and is registered on MahaRERA as P52100053795, per GharKundli's check of MahaRERA records.

How many homes are in Hornbill Heights at Riverview City?

According to GharKundli's check of MahaRERA records (updated November 2026), Hornbill Heights at Riverview City has 672 homes in 4 towers registered on MahaRERA.

When was Hornbill Heights at Riverview City registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Hornbill Heights at Riverview City was registered on MahaRERA on 30 November 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Hornbill Heights at Riverview City?

No court cases are listed for Hornbill Heights at Riverview City on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Hornbill Heights at Riverview City?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Riverview City Constructions Ltd, the company Magarpatta files this project under, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2028 in Pune →

Other projects in pincode 412201

All 29 projects in Loni Kalbhor (412201) →

Other projects by Riverview City Constructions Ltd

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.