How the possession date of Prutha Residency has moved

  1. 16 December 2021

    Completion date given when the project was registered

  2. 15 December 2022

    Extended at the builder's request (MahaRERA application EXT99000011420)

    Reason the builder gave MahaRERA: “Continuous fears of lockdown affecting the work progress as well as the sales leading to delay”
  3. 15 December 2024

    Extended at the builder's request (MahaRERA application EXT99000015094)

    Reason the builder gave MahaRERA: “due to covid ,non availabity of material and labour”

Source: Prutha Residency’s extension records on MahaRERA (P99000014796), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Prutha Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000014796
Status
Completed
Builder
M/s Aum Jivdani Associates
Location
Near JMT High School, Palghar · 401103
Project type
Residential / Group Housing
Registered on
2 Jan 2018
Completion date at registration
December 2021
Latest completion date
December 2024
Delay so far
36 months
Homes
48
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Prutha Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Prutha Residency100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prutha Residency every month.

Prutha Residency: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Prutha Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Prutha Residency: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Prutha Residency

What is the possession date of Prutha Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Prutha Residency in Near JMT High School, Palghar is 15 December 2024 — 36 months later than 16 December 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Prutha Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Prutha Residency's builder has filed on MahaRERA, the official one, is 15 December 2024, already 36 months later than the 16 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Prutha Residency extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Prutha Residency's builder applied to MahaRERA to extend the completion date 2 times: to 15 December 2022, giving the reason "Continuous fears of lockdown affecting the work progress as well as the sales leading to delay"; to 15 December 2024, giving the reason "due to covid ,non availabity of material and labour".

What is the RERA number of Prutha Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Prutha Residency in Near JMT High School, Palghar is P99000014796.

Is Prutha Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Prutha Residency is registered as P99000014796 and its status is "Completed".

What is the construction status of Prutha Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Prutha Residency's status on MahaRERA is "Completed". As filed by the builder, slab work on Prutha Residency is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Prutha Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Prutha Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Prutha Residency is registered on MahaRERA as P99000014796, its MahaRERA status is "Completed", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Prutha Residency's possession date changes?

The latest dates are on Prutha Residency's MahaRERA page (P99000014796). GharKundli's Kundli Watch sends a free WhatsApp update on Prutha Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Prutha Residency have?

According to GharKundli's check of MahaRERA records (updated November 2026), Prutha Residency has one building filed: Prutha Residency with 4 floors.

How big is the land of Prutha Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Prutha Residency stands on 1,504 sq m of land (about 0.4 acres), with 1,508 sq m of sanctioned built-up area.

Where can I read reviews of Prutha Residency?

Google Maps has reviews of Prutha Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Prutha Residency?

Prutha Residency by M/s Aum Jivdani Associates is in Near JMT High School, Palghar (pincode 401103), near Vangaon, Maharashtra, and is registered on MahaRERA as P99000014796, per GharKundli's check of MahaRERA records. Its boundaries filed there include 30m Wide MDR ROad.

How many homes are in Prutha Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), Prutha Residency has 48 homes in 1 tower registered on MahaRERA.

When was Prutha Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Prutha Residency was registered on MahaRERA on 2 January 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Prutha Residency?

No court cases are listed for Prutha Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Prutha Residency?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/s Aum Jivdani Associates.

Other projects in Dahanu

All 6 projects in Vangaon (401103) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.