Skip to content
GharKundli

Jaai Phase II

by VERSATILEREALTORSPRIVATELIMITED · Ostwal Nagari, Palghar 401209Also near Nallasopara West, Nilemore, Nallasopara East

What’s in the report? →

Possession: Jaai Phase II (MahaRERA P99000016273) is marked completed on MahaRERA. It has 14 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000016273. Status: Completed.

Source: MahaRERA website — records for P99000016273, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Jaai Phase II?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Jaai Phase II has moved

  1. 30 September 2020

    Completion date given when the project was registered

  2. 30 September 2021

    Extended at the builder's request (MahaRERA application EXT99000006269)

    Reason the builder gave MahaRERA:
    “We have already completed Phase 1 with O.C. In JAAI phase 2 lift installation work. However NOC from PWD department for lift is Recd. Due to non receipt of fire NOC is also not issued to us. And due to non receipt of Fire NOC, occupancy cer…” Read the full reason“We have already completed Phase 1 with O.C. In JAAI phase 2 lift installation work. However NOC from PWD department for lift is Recd. Due to non receipt of fire NOC is also not issued to us. And due to non receipt of Fire NOC, occupancy certificate is not issued to us.”
  3. 30 March 2022

    Revised completion date on MahaRERA

Source: Jaai Phase II’s extension records on MahaRERA (P99000016273), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Jaai Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the March 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000016273
Status
Completed
Builder
VERSATILEREALTORSPRIVATELIMITED
Location
Ostwal Nagari, Palghar · 401209
Project type
Residential / Group Housing
Registered on
2 May 2018
Completion date at registration
September 2020
Latest completion date
March 2022
Delay so far
18 months
Homes
14
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Jaai Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
JAAI D WING100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jaai Phase II every 1–2 months.

Jaai Phase II: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Versatilerealtorsprivatelimited has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 12 months); 3 still being built, 3 past the promised date (typically 34 months late). No complaints on MahaRERA.

Read Google reviews of Jaai Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Jaai Phase II: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Jaai Phase II

What is the possession date of Jaai Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Jaai Phase II in Ostwal Nagari, Palghar is 30 March 2022 — 18 months later than 30 September 2020, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Jaai Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Jaai Phase II's builder has filed on MahaRERA, the official one, is 30 March 2022, already 18 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Jaai Phase II extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II's builder applied to MahaRERA to extend the completion date once: to 30 September 2021, giving the reason "We have already completed Phase 1 with O.C. In JAAI phase 2 lift installation work. However NOC from PWD department for lift is Recd. Due to non receipt of fire NOC is also not issued to us. And due to non receipt of Fire NOC, occupancy certificate is not issued to us.".

What is the RERA number of Jaai Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Jaai Phase II in Ostwal Nagari, Palghar is P99000016273.

Is Jaai Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II is registered as P99000016273 and its status is "Completed".

What is the current construction status of Jaai Phase II? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II's status on MahaRERA is "Completed". As filed by the builder, slab work on JAAI D WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Jaai Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Jaai Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II is registered on MahaRERA as P99000016273, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Jaai Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Jaai Phase II?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Jaai Phase II: gharkundli.com/tools/property-cost-calculator

Has Jaai Phase II received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Jaai Phase II completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II is marked completed on MahaRERA, and the completion date filed there is 30 March 2022. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Jaai Phase II uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Jaai Phase II was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Jaai Phase II's possession date changes?

The latest dates are on Jaai Phase II's MahaRERA page (P99000016273). GharKundli's Kundli Watch sends a free WhatsApp update on Jaai Phase II every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Jaai Phase II have?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II has one building filed: JAAI D WING with 9 floors.

How big is the land of Jaai Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II stands on 153 sq m of land (about 0.0 acres), with 798 sq m of sanctioned built-up area and 160 sq m of recreational open space.

What is the track record of Jaai Phase II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Versatilerealtorsprivatelimited has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 12 months); 3 still being built, 3 past the promised date (typically 34 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Jaai Phase II?

Google Maps has reviews of Jaai Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Jaai Phase II?

Jaai Phase II by VERSATILEREALTORSPRIVATELIMITED is in Ostwal Nagari, Palghar, pincode 401209 (near Nallasopara West, Nilemore, Nallasopara East), Maharashtra, and is registered on MahaRERA as P99000016273, per GharKundli's check of MahaRERA records. Its boundaries filed there include WESTERN RAILWAY. Its land is filed as 26/4PT. GharKundli lists all 152 MahaRERA projects in Nallasopara East (401209).

How many flats are in Jaai Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II has 14 homes in 1 tower registered on MahaRERA.

When was Jaai Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Jaai Phase II was registered on MahaRERA on 2 May 2018. GharKundli did not find a title report on the land on file there.

Does Jaai Phase II have any legal issues or court cases?

1 court case is listed for Jaai Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Jaai Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VERSATILEREALTORSPRIVATELIMITED, which has 4 other projects registered on MahaRERA.

Other projects in Vasai

All 152 projects in Nallasopara East (401209) →

Other projects by VERSATILEREALTORSPRIVATELIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.