Skip to content
GharKundli

YASHRAJ PRADAKSHINA

by RAJENDRA MURLIDHAR GODBOLE · Dehu, Pune

Possession: YASHRAJ PRADAKSHINA is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100000633. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about YASHRAJ PRADAKSHINA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of YASHRAJ PRADAKSHINA has moved

  1. 1 January 2021

    Completion date given when the project was registered

  2. 1 July 2021

    Extended at the builder's request (MahaRERA application EXT52100008865)

    Reason the builder gave MahaRERA:
    “We have completed 100% work of the residential area and 95% work of the commercial area, received part occupancy certificate for the same. due to covid-19, there is some delay in installing lift and fire equipment on account of shortage of…” Read the full reason“We have completed 100% work of the residential area and 95% work of the commercial area, received part occupancy certificate for the same. due to covid-19, there is some delay in installing lift and fire equipment on account of shortage of labour and materials and therefore could not complete the work of commercial premises. Need extension for a period of 12 months for installation of lift and fire fighting as well as to receive full occupancy certificate. Further our project was falling under town planning, Pune and thereafter it is transferred to PMRDA, Pune and now the same is transferre…”
  3. 30 June 2022

    Extended at the builder's request (MahaRERA application EXT52100010101)

    Reason the builder gave MahaRERA:
    “We have completed 100% work of the residential area and 100% work of the commercial area, received part occupancy certificate for the residential area and in the process of applying for Occupancy Certificate for commercial area. We have alr…” Read the full reason“We have completed 100% work of the residential area and 100% work of the commercial area, received part occupancy certificate for the residential area and in the process of applying for Occupancy Certificate for commercial area. We have already installed two lifts, only 1 lift is pending for installation and solar system in 1 building. Fire fighting system is yet to be installed. Due to covid-19, there is delay in installing lift and fire equipment on account of shortage of labour and materials and therefore could not complete the work of commercial premises. Need extension for a period of…”
  4. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT52100015330)

    Reason the builder gave MahaRERA:
    “Dear Sir/Madam, We have received the Occupancy Certificate on 30th December 2022. Since the form 4 required Outward number of Occupancy Certificate, the Form 4 was not uploaded within the time frame, as 31st Dec 2022 and 1st Jan 2023 were S…” Read the full reason“Dear Sir/Madam, We have received the Occupancy Certificate on 30th December 2022. Since the form 4 required Outward number of Occupancy Certificate, the Form 4 was not uploaded within the time frame, as 31st Dec 2022 and 1st Jan 2023 were Saturday and Sunday, and the architect’s office were closed and I could not arrange form 4. A notice was issued to us on 29th advising us to file for extension of the project before submitting form 4, and that is the reason for extension. We have obtained the necessary consent. Please grant us extension only for the submission of form 4, the project is com…”

Source: YASHRAJ PRADAKSHINA’s extension records on MahaRERA (P52100000633), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on YASHRAJ PRADAKSHINA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100000633
Status
Completed
Builder
RAJENDRA MURLIDHAR GODBOLE
Location
Dehu, Pune · 412109
Project type
Others
Registered on
19 Jul 2017
Completion date at registration
January 2021
Latest completion date
June 2023
Delay so far
29 months
Homes
62
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of YASHRAJ PRADAKSHINA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
YASHRAJ PRADAKSHINA100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on YASHRAJ PRADAKSHINA every month.

YASHRAJ PRADAKSHINA: buildings, flats and land, as filed on MahaRERA

  • Buildings: YASHRAJ PRADAKSHINA (7 floors)
  • Land: 1,167 sq m (about 0.3 acres) · sanctioned built-up 2,329 sq m
  • Boundaries filed include: Common Road, Nagar Pradakshina Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of YASHRAJ PRADAKSHINA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

YASHRAJ PRADAKSHINA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about YASHRAJ PRADAKSHINA

What is the possession date of YASHRAJ PRADAKSHINA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for YASHRAJ PRADAKSHINA in Dehu, Pune is 30 June 2023 — 29 months later than 1 January 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for YASHRAJ PRADAKSHINA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date YASHRAJ PRADAKSHINA's builder has filed on MahaRERA, the official one, is 30 June 2023, already 29 months later than the 1 January 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of YASHRAJ PRADAKSHINA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), YASHRAJ PRADAKSHINA's builder applied to MahaRERA to extend the completion date 3 times: to 1 July 2021, giving the reason "We have completed 100% work of the residential area and 95% work of the commercial area, received part occupancy certificate for the same. due to covid-19, there is some delay in installing lift and fire equipment on account of shortage of labour and materials and therefore could not complete the work of commercial premises. Need extension for a period of 12 months for installation of lift and fire fighting as well as to receive full occupancy certificate. Further our project was falling under town planning, Pune and thereafter it is transferred to PMRDA, Pune and now the same is transferre…"; to 30 June 2022, giving the reason "We have completed 100% work of the residential area and 100% work of the commercial area, received part occupancy certificate for the residential area and in the process of applying for Occupancy Certificate for commercial area. We have already installed two lifts, only 1 lift is pending for installation and solar system in 1 building. Fire fighting system is yet to be installed. Due to covid-19, there is delay in installing lift and fire equipment on account of shortage of labour and materials and therefore could not complete the work of commercial premises. Need extension for a period of…"; to 30 June 2023, giving the reason "Dear Sir/Madam, We have received the Occupancy Certificate on 30th December 2022. Since the form 4 required Outward number of Occupancy Certificate, the Form 4 was not uploaded within the time frame, as 31st Dec 2022 and 1st Jan 2023 were Saturday and Sunday, and the architect’s office were closed and I could not arrange form 4. A notice was issued to us on 29th advising us to file for extension of the project before submitting form 4, and that is the reason for extension. We have obtained the necessary consent. Please grant us extension only for the submission of form 4, the project is com…".

What is the RERA number of YASHRAJ PRADAKSHINA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of YASHRAJ PRADAKSHINA in Dehu, Pune is P52100000633.

Is YASHRAJ PRADAKSHINA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), YASHRAJ PRADAKSHINA is registered as P52100000633 and its status is "Completed".

What is the construction status of YASHRAJ PRADAKSHINA?

According to GharKundli's check of MahaRERA records (updated November 2026), YASHRAJ PRADAKSHINA's status on MahaRERA is "Completed". As filed by the builder, slab work on YASHRAJ PRADAKSHINA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does YASHRAJ PRADAKSHINA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is YASHRAJ PRADAKSHINA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), YASHRAJ PRADAKSHINA is registered on MahaRERA as P52100000633, its MahaRERA status is "Completed", its completion date has moved 29 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if YASHRAJ PRADAKSHINA's possession date changes?

The latest dates are on YASHRAJ PRADAKSHINA's MahaRERA page (P52100000633). GharKundli's Kundli Watch sends a free WhatsApp update on YASHRAJ PRADAKSHINA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does YASHRAJ PRADAKSHINA have?

According to GharKundli's check of MahaRERA records (updated November 2026), YASHRAJ PRADAKSHINA has one building filed: YASHRAJ PRADAKSHINA with 7 floors.

How big is the land of YASHRAJ PRADAKSHINA?

According to GharKundli's check of MahaRERA records (updated November 2026), YASHRAJ PRADAKSHINA stands on 1,167 sq m of land (about 0.3 acres), with 2,329 sq m of sanctioned built-up area.

Where can I read reviews of YASHRAJ PRADAKSHINA?

Google Maps has reviews of YASHRAJ PRADAKSHINA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is YASHRAJ PRADAKSHINA?

YASHRAJ PRADAKSHINA by RAJENDRA MURLIDHAR GODBOLE is in Dehu, Pune (pincode 412109), Maharashtra, and is registered on MahaRERA as P52100000633, per GharKundli's check of MahaRERA records. Its boundaries filed there include Common Road, Nagar Pradakshina Road.

How many homes are in YASHRAJ PRADAKSHINA?

According to GharKundli's check of MahaRERA records (updated November 2026), YASHRAJ PRADAKSHINA has 62 homes in 1 tower registered on MahaRERA.

When was YASHRAJ PRADAKSHINA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), YASHRAJ PRADAKSHINA was registered on MahaRERA on 19 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on YASHRAJ PRADAKSHINA?

No court cases are listed for YASHRAJ PRADAKSHINA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of YASHRAJ PRADAKSHINA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RAJENDRA MURLIDHAR GODBOLE, which has 1 other project registered on MahaRERA.

Other projects in pincode 412109

All 53 projects in Dehu (412109) →

Other projects by RAJENDRA MURLIDHAR GODBOLE

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.