GharKundli

Satav Mayuri Sunrise

by V Satav Developers · Wagholi, Pune 412207Registered on MahaRERA as “Mayuri Sunrise”

What’s in the report? →

Possession date of Satav Mayuri Sunrise (MahaRERA P52100004296): 30 December 2021, moved from 31 December 2019 (24 months later), and it has already passed. It has 194 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100004296. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100004296, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2021) has passed.

What do you want to know about Satav Mayuri Sunrise?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Satav Mayuri Sunrise has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT52100005205)

    Reason the builder gave MahaRERA: “We have attached Developer self-explanatory letter along with Independent Site engineering Report also Attached Actual site condition photographs for you reference.”
  3. 30 December 2021

    Revised completion date on MahaRERA

Source: Satav Mayuri Sunrise’s extension records on MahaRERA (P52100004296), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Satav Mayuri Sunrise

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100004296
Status
Lapsed (registration period ended)
Builder
V Satav Developers
Location
Wagholi, Pune · 412207
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2021
Delay so far
24 months
Homes
194
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Satav Mayuri Sunrise, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A wing100%100%100%100%
B wing100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Satav Mayuri Sunrise every 1–2 months.

Satav Mayuri Sunrise: buildings, flats and land, as filed on MahaRERA

  • Buildings: A wing (15 floors) · B wing (14 floors)
  • Land: 8,093 sq m (about 2.0 acres) · sanctioned built-up 7,352 sq m · recreational space 809 sq m
  • Land, as filed: Gat no 640 and 642
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Satav Mayuri Sunrise →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Satav Mayuri Sunrise: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Satav Mayuri Sunrise

What is the possession date of Satav Mayuri Sunrise?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Satav Mayuri Sunrise in Wagholi, Pune is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration. That date has already passed.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Satav Mayuri Sunrise?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Satav Mayuri Sunrise's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Satav Mayuri Sunrise extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Satav Mayuri Sunrise's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "We have attached Developer self-explanatory letter along with Independent Site engineering Report also Attached Actual site condition photographs for you reference.".

What is the RERA number of Satav Mayuri Sunrise?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Satav Mayuri Sunrise in Wagholi, Pune is P52100004296.

Is Satav Mayuri Sunrise registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Satav Mayuri Sunrise is registered as P52100004296 and its status is "Lapsed (registration period ended)".

What is the current construction status of Satav Mayuri Sunrise? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Satav Mayuri Sunrise's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Satav Mayuri Sunrise have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Satav Mayuri Sunrise safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Satav Mayuri Sunrise is registered on MahaRERA as P52100004296, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Satav Mayuri Sunrise?

Satav Mayuri Sunrise isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Satav Mayuri Sunrise?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Satav Mayuri Sunrise: gharkundli.com/tools/property-cost-calculator

Has Satav Mayuri Sunrise received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Satav Mayuri Sunrise isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 December 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Satav Mayuri Sunrise?

According to GharKundli's check of MahaRERA records (updated November 2026), Satav Mayuri Sunrise's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 December 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Satav Mayuri Sunrise uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Satav Mayuri Sunrise was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Satav Mayuri Sunrise's possession date changes?

The latest dates are on Satav Mayuri Sunrise's MahaRERA page (P52100004296). GharKundli's Kundli Watch sends a free WhatsApp update on Satav Mayuri Sunrise every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Satav Mayuri Sunrise have?

According to GharKundli's check of MahaRERA records (updated November 2026), Satav Mayuri Sunrise has 2 buildings filed: A wing with 15 floors; B wing with 14 floors.

How big is the land of Satav Mayuri Sunrise?

According to GharKundli's check of MahaRERA records (updated November 2026), Satav Mayuri Sunrise stands on 8,093 sq m of land (about 2.0 acres), with 7,352 sq m of sanctioned built-up area and 809 sq m of recreational open space.

What are the reviews of Satav Mayuri Sunrise?

Google Maps has reviews of Satav Mayuri Sunrise written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Satav Mayuri Sunrise?

Satav Mayuri Sunrise by V Satav Developers is in Wagholi, Pune, pincode 412207, Maharashtra, and is registered on MahaRERA as P52100004296, per GharKundli's check of MahaRERA records. Its land is filed as Gat no 640 and 642. GharKundli lists all 379 MahaRERA projects in Wagholi (412207).

How many flats are in Satav Mayuri Sunrise?

According to GharKundli's check of MahaRERA records (updated November 2026), Satav Mayuri Sunrise has 194 homes in 2 towers registered on MahaRERA.

When was Satav Mayuri Sunrise registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Satav Mayuri Sunrise was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Does Satav Mayuri Sunrise have any legal issues or court cases?

No court cases are listed for Satav Mayuri Sunrise on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Satav Mayuri Sunrise?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is V Satav Developers.