VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)

by VIVANTA SPACES · Sbi Undri Branch, Pune

Possession date of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C): 30 June 2024, moved from 30 December 2020 (42 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100001309. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2024) has passed.

What do you want to know about VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) has moved

  1. 30 December 2020

    Completion date given when the project was registered

  2. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT52100008541)

    Reason the builder gave MahaRERA: “Due to no sale & poor market condition we were unable to complete the project within the due time.”
  3. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT52100011923)

    Reason the builder gave MahaRERA:
    “As we know Covid 19 has impacted all the sectors and real estate is not an exception from them. Many hurdles emerged with the beginning of the pandemic. We faced difficulty as there was a lack of essential raw material and unavailabiilty of…” Read the full reason“As we know Covid 19 has impacted all the sectors and real estate is not an exception from them. Many hurdles emerged with the beginning of the pandemic. We faced difficulty as there was a lack of essential raw material and unavailabiilty of manufacturing equipment has halted the construction activity. With imposition of international trade restrictions amid pandemic ,supply lines have been struck short and as a consequence inflation hit high and resulted in increasing the price of inputs required for project. As a result project under construction experienced a delay .So please grant us the…”

Source: VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)’s extension records on MahaRERA (P52100001309), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100001309
Status
Lapsed (registration period ended)
Builder
VIVANTA SPACES
Location
Sbi Undri Branch, Pune · 412208
Project type
Residential / Group Housing
Registered on
27 Jul 2017
Completion date at registration
December 2020
Latest completion date
June 2024
Delay so far
42 months
Homes
96
Sold or booked
35%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C), as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VIVANTA SARTHAK BLDG A- RIDDHI0%100%100%100%
BLDG B - ADITI0%100%90%0%
BLDG C - SIDDHI0%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • VIVANTA SARTHAK BLDG A- RIDDHI: covers 6 floors
  • BLDG B - ADITI: covers 6 floors
  • BLDG C - SIDDHI: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) every month.

VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C): buildings, flats and land, as filed on MahaRERA

  • Buildings: VIVANTA SARTHAK BLDG A- RIDDHI (6 floors, 32 units) · BLDG B - ADITI (6 floors, 32 units) · BLDG C - SIDDHI (6 floors, 32 units)
  • Land: 3,486 sq m (about 0.9 acres) · sanctioned built-up 3,481 sq m · recreational space 348 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C): buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)

What is the possession date of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) in Sbi Undri Branch, Pune is 30 June 2024 — 42 months later than 30 December 2020, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)'s builder has filed on MahaRERA, the official one, is 30 June 2024, already 42 months later than the 30 December 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) extended?

According to GharKundli's check of MahaRERA records (updated November 2026), VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)'s builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2021, giving the reason "Due to no sale & poor market condition we were unable to complete the project within the due time."; to 30 June 2024, giving the reason "As we know Covid 19 has impacted all the sectors and real estate is not an exception from them. Many hurdles emerged with the beginning of the pandemic. We faced difficulty as there was a lack of essential raw material and unavailabiilty of manufacturing equipment has halted the construction activity. With imposition of international trade restrictions amid pandemic ,supply lines have been struck short and as a consequence inflation hit high and resulted in increasing the price of inputs required for project. As a result project under construction experienced a delay .So please grant us the…".

What is the RERA number of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) in Sbi Undri Branch, Pune is P52100001309.

Is VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) is registered as P52100001309 and its status is "Lapsed (registration period ended)".

What is the construction status of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

According to GharKundli's check of MahaRERA records (updated November 2026), VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)'s status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) is registered on MahaRERA as P52100001309, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)'s possession date changes?

The latest dates are on VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)'s MahaRERA page (P52100001309). GharKundli's Kundli Watch sends a free WhatsApp update on VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) have?

According to GharKundli's check of MahaRERA records (updated November 2026), VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) has 3 buildings filed: VIVANTA SARTHAK BLDG A- RIDDHI with 6 floors and 32 units; BLDG B - ADITI with 6 floors and 32 units; BLDG C - SIDDHI with 6 floors and 32 units.

How big is the land of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

According to GharKundli's check of MahaRERA records (updated November 2026), VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) stands on 3,486 sq m of land (about 0.9 acres), with 3,481 sq m of sanctioned built-up area and 348 sq m of recreational open space.

Where can I read reviews of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

Google Maps has reviews of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) by VIVANTA SPACES is in Sbi Undri Branch, Pune (pincode 412208), Maharashtra, and is registered on MahaRERA as P52100001309, per GharKundli's check of MahaRERA records.

How many homes are in VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

According to GharKundli's check of MahaRERA records (updated November 2026), VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) has 96 homes in 3 towers registered on MahaRERA, and 35% of them are sold or booked.

When was VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) was registered on MahaRERA on 27 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

No court cases are listed for VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C) on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of VIVANTA SARTHAK PHASE 1 (BUILDING A,B & C)?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIVANTA SPACES.