Possession: Alpha Center is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100003505. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Alpha Center?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Alpha Center has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52100017249)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 90.48% allottees for purpose of extension of RERA registration period of the said project.”

Source: Alpha Center’s extension records on MahaRERA (P52100003505), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Alpha Center

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100003505
Status
Completed
Builder
Hrudev Realty Projects L.L.P
Location
Shankarseth Road, Pune · 411001
Project type
Commercial
Registered on
5 Aug 2017
Completion date at registration
December 2018
Latest completion date
December 2023
Delay so far
60 months
Homes
85
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Alpha Center, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Alpha Center100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Alpha Center every month.

Alpha Center: buildings, flats and land, as filed on MahaRERA

  • Buildings: Alpha Center (11 floors)
  • Land: 2,800 sq m (about 0.7 acres) · sanctioned built-up 3,349 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Alpha Center →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Alpha Center: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Alpha Center

What is the possession date of Alpha Center?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Alpha Center in Shankarseth Road, Pune is 31 December 2023 — 60 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Alpha Center?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Alpha Center's builder has filed on MahaRERA, the official one, is 31 December 2023, already 60 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Alpha Center extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Alpha Center's builder applied to MahaRERA to extend the completion date once: to 31 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 90.48% allottees for purpose of extension of RERA registration period of the said project.".

What is the RERA number of Alpha Center?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Alpha Center in Shankarseth Road, Pune is P52100003505.

Is Alpha Center registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Alpha Center is registered as P52100003505 and its status is "Completed".

What is the construction status of Alpha Center?

According to GharKundli's check of MahaRERA records (updated November 2026), Alpha Center's status on MahaRERA is "Completed". As filed by the builder, slab work on Alpha Center is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Alpha Center have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Alpha Center safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Alpha Center is registered on MahaRERA as P52100003505, its MahaRERA status is "Completed", its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Alpha Center's possession date changes?

The latest dates are on Alpha Center's MahaRERA page (P52100003505). GharKundli's Kundli Watch sends a free WhatsApp update on Alpha Center every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Alpha Center have?

According to GharKundli's check of MahaRERA records (updated November 2026), Alpha Center has one building filed: Alpha Center with 11 floors.

How big is the land of Alpha Center?

According to GharKundli's check of MahaRERA records (updated November 2026), Alpha Center stands on 2,800 sq m of land (about 0.7 acres), with 3,349 sq m of sanctioned built-up area.

Where can I read reviews of Alpha Center?

Google Maps has reviews of Alpha Center written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Alpha Center?

Alpha Center by Hrudev Realty Projects L.L.P is in Shankarseth Road, Pune (pincode 411001), Maharashtra, and is registered on MahaRERA as P52100003505, per GharKundli's check of MahaRERA records.

How many homes are in Alpha Center?

According to GharKundli's check of MahaRERA records (updated November 2026), Alpha Center has 85 homes in 1 tower registered on MahaRERA.

When was Alpha Center registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Alpha Center was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Alpha Center?

No court cases are listed for Alpha Center on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Alpha Center?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Hrudev Realty Projects L.L.P.

Other projects in Pune City

All 73 projects in Ghorpadi (411001) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.