Rohit Pinnacle
by Rohit Infra · Rahatni, Pune 411017
What’s in the report? →Possession date of Rohit Pinnacle (MahaRERA P52100004032): 28 February 2021, moved from 31 August 2019 (18 months later), and it has already passed. It has 72 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100004032. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100004032, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (February 2021) has passed.
What do you want to know about Rohit Pinnacle?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Rohit Pinnacle has moved
31 August 2019
Completion date given when the project was registered
30 August 2020
Extended at the builder's request (MahaRERA application EXT52100002286)
Reason the builder gave MahaRERA: “Due to the delay in getting all the corrected plan from authority.”
28 February 2021
Revised completion date on MahaRERA
Source: Rohit Pinnacle’s extension records on MahaRERA (P52100004032), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Rohit Pinnacle
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the February 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100004032
- Status
- Lapsed (registration period ended)
- Builder
- Rohit Infra
- Location
- Rahatni, Pune · 411017
- Project type
- Residential / Group Housing
- Registered on
- 7 Aug 2017
- Completion date at registration
- August 2019
- Latest completion date
- February 2021
- Delay so far
- 18 months
- Homes
- 72
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Rohit Pinnacle, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| B | 80% | 0% | 0% | 0% |
| A | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rohit Pinnacle every 1–2 months.
Rohit Pinnacle: buildings, flats and land, as filed on MahaRERA
- Buildings: B (1 floors) · A (13 floors)
- Land: 4,100 sq m (about 1.0 acres) · sanctioned built-up 3,040 sq m · recreational space 400 sq m
- Land, as filed: S No 1P CTS No 6P 2116
- Map: Get directions
The builder’s record and reviews
Rohit Infra (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 6 months late); 2 lapsed. No complaints on MahaRERA.
Read Google reviews of Rohit Pinnacle →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Rohit Pinnacle: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Rohit Pinnacle
What is the possession date of Rohit Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Rohit Pinnacle in Rahatni, Pune is 28 February 2021 — 18 months later than 31 August 2019, the date given at registration. That date has already passed.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Rohit Pinnacle?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Rohit Pinnacle's builder has filed on MahaRERA, the official one, is 28 February 2021, already 18 months later than the 31 August 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Rohit Pinnacle extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Pinnacle's builder applied to MahaRERA to extend the completion date once: to 30 August 2020, giving the reason "Due to the delay in getting all the corrected plan from authority.".
What is the RERA number of Rohit Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Rohit Pinnacle in Rahatni, Pune is P52100004032.
Is Rohit Pinnacle registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Pinnacle is registered as P52100004032 and its status is "Lapsed (registration period ended)".
What is the current construction status of Rohit Pinnacle? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Pinnacle's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Rohit Pinnacle have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Rohit Pinnacle safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Pinnacle is registered on MahaRERA as P52100004032, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Rohit Pinnacle?
Rohit Pinnacle isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Rohit Pinnacle?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Rohit Pinnacle: gharkundli.com/tools/property-cost-calculator
Has Rohit Pinnacle received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Pinnacle isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 28 February 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Rohit Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Pinnacle's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (28 February 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Rohit Pinnacle uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Rohit Pinnacle was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Rohit Pinnacle's possession date changes?
The latest dates are on Rohit Pinnacle's MahaRERA page (P52100004032). GharKundli's Kundli Watch sends a free WhatsApp update on Rohit Pinnacle every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Rohit Pinnacle have?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Pinnacle has 2 buildings filed: B with 1 floors; A with 13 floors.
How big is the land of Rohit Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Pinnacle stands on 4,100 sq m of land (about 1.0 acres), with 3,040 sq m of sanctioned built-up area and 400 sq m of recreational open space.
What is the track record of Rohit Pinnacle's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Infra (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 3 still being built, 1 past the promised date (typically 6 months late); 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Rohit Pinnacle?
Google Maps has reviews of Rohit Pinnacle written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Rohit Pinnacle?
Rohit Pinnacle by Rohit Infra is in Rahatni, Pune, pincode 411017, Maharashtra, and is registered on MahaRERA as P52100004032, per GharKundli's check of MahaRERA records. Its land is filed as S No 1P CTS No 6P 2116. GharKundli lists all 161 MahaRERA projects in Rahatani (411017).
How many flats are in Rohit Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Pinnacle has 72 homes in 2 towers registered on MahaRERA.
When was Rohit Pinnacle registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Rohit Pinnacle was registered on MahaRERA on 7 August 2017. GharKundli did not find a title report on the land on file there.
Does Rohit Pinnacle have any legal issues or court cases?
1 court case is listed for Rohit Pinnacle on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Rohit Pinnacle?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Rohit Infra, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Rohit Pinnacle
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Rahatani (411017)
- Five Oaks
- 15 M Street
- Vrindavan Wing A
- K K Chrysanth
- Harsh Apartment
- Rohit Palms
- Sai Corner
- Chandrabhaga Residency
Other projects by Rohit Infra
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.