Saidatta Datta Vihar

by SAIDATTA ASSOCIATES DEVELOPERS PROMOTERS AND BUILDERS · khadakwasla, Pune 411025Also near I.A.TRegistered on MahaRERA as “DATTA VIHAR”

What’s in the report? →

Possession date of Saidatta Datta Vihar (MahaRERA P52100011311): 30 March 2022, moved from 31 January 2019 (38 months later), and it has already passed. It has 12 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100011311. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100011311, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (March 2022) has passed.

What do you want to know about Saidatta Datta Vihar?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Saidatta Datta Vihar has moved

  1. 31 January 2019

    Completion date given when the project was registered

  2. 31 March 2021

    Extended at the builder's request (MahaRERA application EXT52100002050)

    Reason the builder gave MahaRERA: “DUE TO SCARECITY OF FUNDS UPTILL WE HAVE PROGRESSED THE PROJECT UPTO 60%”
  3. 31 March 2021

    Extended at the builder's request (MahaRERA application EXT52100005782)

    Reason the builder gave MahaRERA: “Due to scarecity of funds project is getting delayed”
  4. 30 March 2022

    Revised completion date on MahaRERA

Source: Saidatta Datta Vihar’s extension records on MahaRERA (P52100011311), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Saidatta Datta Vihar

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100011311
Status
Lapsed (registration period ended)
Builder
SAIDATTA ASSOCIATES DEVELOPERS PROMOTERS AND BUILDERS
Location
khadakwasla, Pune · 411025
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
January 2019
Latest completion date
March 2022
Delay so far
38 months
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Saidatta Datta Vihar, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DATTAVIHAR100%100%50%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Saidatta Datta Vihar every 1–2 months.

Saidatta Datta Vihar: buildings, flats and land, as filed on MahaRERA

  • Buildings: DATTAVIHAR (6 floors)
  • Land: 282 sq m (about 0.1 acres) · sanctioned built-up 710 sq m · recreational space 179 sq m
  • Land, as filed: 570
  • Map: Get directions

The builder’s record and reviews

Saidatta Associates Developers Promoters AND Builders (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Saidatta Datta Vihar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Saidatta Datta Vihar: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Saidatta Datta Vihar

What is the possession date of Saidatta Datta Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Saidatta Datta Vihar in khadakwasla, Pune is 30 March 2022 — 38 months later than 31 January 2019, the date given at registration. That date has already passed.

The date has already moved 38 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Saidatta Datta Vihar?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Saidatta Datta Vihar's builder has filed on MahaRERA, the official one, is 30 March 2022, already 38 months later than the 31 January 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Saidatta Datta Vihar extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Datta Vihar's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2021, giving the reason "DUE TO SCARECITY OF FUNDS UPTILL WE HAVE PROGRESSED THE PROJECT UPTO 60%"; to 31 March 2021, giving the reason "Due to scarecity of funds project is getting delayed".

What is the RERA number of Saidatta Datta Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Saidatta Datta Vihar in khadakwasla, Pune is P52100011311.

Is Saidatta Datta Vihar registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Datta Vihar is registered as P52100011311 and its status is "Lapsed (registration period ended)".

What is the current construction status of Saidatta Datta Vihar? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Datta Vihar's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on DATTAVIHAR is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Saidatta Datta Vihar have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Saidatta Datta Vihar safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Datta Vihar is registered on MahaRERA as P52100011311, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 38 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Saidatta Datta Vihar?

Saidatta Datta Vihar isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Saidatta Datta Vihar?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Saidatta Datta Vihar: gharkundli.com/tools/property-cost-calculator

Has Saidatta Datta Vihar received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Datta Vihar isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 March 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Saidatta Datta Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Datta Vihar's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 March 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Saidatta Datta Vihar uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Saidatta Datta Vihar was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Saidatta Datta Vihar's possession date changes?

The latest dates are on Saidatta Datta Vihar's MahaRERA page (P52100011311). GharKundli's Kundli Watch sends a free WhatsApp update on Saidatta Datta Vihar every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Saidatta Datta Vihar have?

According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Datta Vihar has one building filed: DATTAVIHAR with 6 floors.

How big is the land of Saidatta Datta Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Datta Vihar stands on 282 sq m of land (about 0.1 acres), with 710 sq m of sanctioned built-up area and 179 sq m of recreational open space.

What is the track record of Saidatta Datta Vihar's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Associates Developers Promoters AND Builders (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Saidatta Datta Vihar?

Google Maps has reviews of Saidatta Datta Vihar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Saidatta Datta Vihar?

Saidatta Datta Vihar by SAIDATTA ASSOCIATES DEVELOPERS PROMOTERS AND BUILDERS is in khadakwasla, Pune, pincode 411025 (near I.A.T), Maharashtra, and is registered on MahaRERA as P52100011311, per GharKundli's check of MahaRERA records. Its land is filed as 570. GharKundli lists all 12 MahaRERA projects in I.A.T (411025).

How many flats are in Saidatta Datta Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Datta Vihar has 12 homes in 1 tower registered on MahaRERA.

When was Saidatta Datta Vihar registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Saidatta Datta Vihar was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Does Saidatta Datta Vihar have any legal issues or court cases?

No court cases are listed for Saidatta Datta Vihar on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Saidatta Datta Vihar?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAIDATTA ASSOCIATES DEVELOPERS PROMOTERS AND BUILDERS.

Other projects in I.A.T (411025)

All 12 projects in I.A.T (411025) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.