Honeydew Building A
by Candor Group · Shivajinagar, Pune
Possession date of Honeydew Building A: 31 October 2023, moved from 31 July 2018 (63 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100003580. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (October 2023) has passed.
What do you want to know about Honeydew Building A?
How the possession date of Honeydew Building A has moved
31 July 2018
Completion date given when the project was registered
15 January 2021
Extended at the builder's request (MahaRERA application EXT52100005442)
Reason the builder gave MahaRERA:
“REASON FOR DELAY IN COMPLETION OF PROJECT : - Reason for Delay in construction of project is only due to Heavy Recession in Infrastructure and Construction field during last 2-3 years in all over the India We are facing shortage of funds du…” Read the full reason
“REASON FOR DELAY IN COMPLETION OF PROJECT : - Reason for Delay in construction of project is only due to Heavy Recession in Infrastructure and Construction field during last 2-3 years in all over the India We are facing shortage of funds due to unsold flats. We are trying to complete the project at the earliest from contributing Own Finance and Borrowings from outside. And due to Heavy Recession in Infrastructure and Construction field and bad experience for giving finance to Builders directly against mortgage of property, now Bank and Finance Companies also stopped giving direct finance to…”31 October 2023
Extended at the builder's request (MahaRERA application EXT52100013795)
Reason the builder gave MahaRERA:
“SALE OF FLATS AND AMOUNT COLLECTED AND EXPENDITURE MADE:- Till the date of this application , Out of Total 8 Flats only 3 flats are sold due to heavy recession in construction business. Though We had collected Amount of Rs.54,30,000/- again…” Read the full reason
“SALE OF FLATS AND AMOUNT COLLECTED AND EXPENDITURE MADE:- Till the date of this application , Out of Total 8 Flats only 3 flats are sold due to heavy recession in construction business. Though We had collected Amount of Rs.54,30,000/- against sale of 3 Flats ,we had spent approx. Amount of Rs.1 Crore 53 Lacs for the construction of project.. 3> REASON FOR DELAY IN COMPLETION OF PROJECT :- Reason for Delay in construction of project is only due to heavy Recession in infrastructure and Construction field during last 3-4 Years in all over the india We are Facing shortage of funds due to unsold…”
Source: Honeydew Building A’s extension records on MahaRERA (P52100003580), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Honeydew Building A
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100003580
- Status
- Lapsed (registration period ended)
- Builder
- Candor Group
- Location
- Shivajinagar, Pune · 412307
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2017
- Completion date at registration
- July 2018
- Latest completion date
- October 2023
- Delay so far
- 63 months
- Homes
- 8
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Honeydew Building A, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Honeydew building A | 100% | 100% | 95% | 75% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Honeydew Building A every month.
Honeydew Building A: buildings, flats and land, as filed on MahaRERA
- Buildings: Honeydew building A (6 floors)
- Land: 400 sq m (about 0.1 acres) · sanctioned built-up 160 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Honeydew Building A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Honeydew Building A: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Honeydew Building A
What is the possession date of Honeydew Building A?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Honeydew Building A in Shivajinagar, Pune is 31 October 2023 — 63 months later than 31 July 2018, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Honeydew Building A?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Honeydew Building A's builder has filed on MahaRERA, the official one, is 31 October 2023, already 63 months later than the 31 July 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Honeydew Building A extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Honeydew Building A's builder applied to MahaRERA to extend the completion date 2 times: to 15 January 2021, giving the reason "REASON FOR DELAY IN COMPLETION OF PROJECT : - Reason for Delay in construction of project is only due to Heavy Recession in Infrastructure and Construction field during last 2-3 years in all over the India We are facing shortage of funds due to unsold flats. We are trying to complete the project at the earliest from contributing Own Finance and Borrowings from outside. And due to Heavy Recession in Infrastructure and Construction field and bad experience for giving finance to Builders directly against mortgage of property, now Bank and Finance Companies also stopped giving direct finance to…"; to 31 October 2023, giving the reason "SALE OF FLATS AND AMOUNT COLLECTED AND EXPENDITURE MADE:- Till the date of this application , Out of Total 8 Flats only 3 flats are sold due to heavy recession in construction business. Though We had collected Amount of Rs.54,30,000/- against sale of 3 Flats ,we had spent approx. Amount of Rs.1 Crore 53 Lacs for the construction of project.. 3> REASON FOR DELAY IN COMPLETION OF PROJECT :- Reason for Delay in construction of project is only due to heavy Recession in infrastructure and Construction field during last 3-4 Years in all over the india We are Facing shortage of funds due to unsold…".
What is the RERA number of Honeydew Building A?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Honeydew Building A in Shivajinagar, Pune is P52100003580.
Is Honeydew Building A registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Honeydew Building A is registered as P52100003580 and its status is "Lapsed (registration period ended)".
What is the construction status of Honeydew Building A?
According to GharKundli's check of MahaRERA records (updated November 2026), Honeydew Building A's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Honeydew building A is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Honeydew Building A have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Honeydew Building A safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Honeydew Building A is registered on MahaRERA as P52100003580, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 63 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Honeydew Building A's possession date changes?
The latest dates are on Honeydew Building A's MahaRERA page (P52100003580). GharKundli's Kundli Watch sends a free WhatsApp update on Honeydew Building A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Honeydew Building A have?
According to GharKundli's check of MahaRERA records (updated November 2026), Honeydew Building A has one building filed: Honeydew building A with 6 floors.
How big is the land of Honeydew Building A?
According to GharKundli's check of MahaRERA records (updated November 2026), Honeydew Building A stands on 400 sq m of land (about 0.1 acres), with 160 sq m of sanctioned built-up area.
Where can I read reviews of Honeydew Building A?
Google Maps has reviews of Honeydew Building A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Honeydew Building A?
Honeydew Building A by Candor Group is in Shivajinagar, Pune (pincode 412307), Maharashtra, and is registered on MahaRERA as P52100003580, per GharKundli's check of MahaRERA records.
How many homes are in Honeydew Building A?
According to GharKundli's check of MahaRERA records (updated November 2026), Honeydew Building A has 8 homes in 1 tower registered on MahaRERA.
When was Honeydew Building A registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Honeydew Building A was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Honeydew Building A?
No court cases are listed for Honeydew Building A on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Honeydew Building A?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Candor Group.
Check it yourself on MahaRERA
- How to check the possession date of Honeydew Building A
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Shivajinagar
- TRUSPACE PRIMA ALTIORA
- Anand Dham
- Durvankur
- Serenity Springs
- Yash Heights
- Chandrahas
- Mangirish Co-operative Housing Society Ltd
- TEJ ONE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.