KUL Utsav Phase I -Building G

by Kumar Builders · Bund Garden, PuneAlso near Kondhwa Bk, Kondhwa budruk, Katraj

Possession: KUL Utsav Phase I -Building G is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100003489. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about KUL Utsav Phase I -Building G?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KUL Utsav Phase I -Building G has moved

  1. 15 May 2019

    Completion date given when the project was registered

  2. 14 May 2020

    Extended at the builder's request (MahaRERA application EXT52100001775)

    Reason the builder gave MahaRERA:
    “Appointed RCC contractor constantly have low labour strength, he was unable to achieve milestones, after several instructions given by us. Deployed Labours had low skilled/productivity level; thus we were not getting work quality up to the…” Read the full reason“Appointed RCC contractor constantly have low labour strength, he was unable to achieve milestones, after several instructions given by us. Deployed Labours had low skilled/productivity level; thus we were not getting work quality up to the mark. Therefore we rectify the quality for betterment of the project, in the process of rectification and deployment of skilled workers work is delayed.”
  3. 31 March 2022

    Extended at the builder's request (MahaRERA application EXT52100009390)

    Reason the builder gave MahaRERA:
    “Applicant submits that now the construction of this project is at the stage of completion. The external structure of the building is ready. The brickwork, internal and external plastering and internal POP are more than 60 % completed. The w…” Read the full reason“Applicant submits that now the construction of this project is at the stage of completion. The external structure of the building is ready. The brickwork, internal and external plastering and internal POP are more than 60 % completed. The work remaining is finishing tasks of wall plastering, tiles, plumbing, sanitary fitting etc. Applicant submits due to COVID 19 pandemic lockdown was declared in Pune in March’2020. As a result the labours working on the site of this Applicant went back to their native places outside Maharashtra. As a result the construction work on the site of the Applican…”
  4. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT52100012594)

    Reason the builder gave MahaRERA:
    “The Applicant is requesting for extension upto 30/06/2023 and submits that the following factors have caused the subject delay of 9 months:- • Shortage of certain material in the markets due to the supply chain disruptions and scarcity of m…” Read the full reason“The Applicant is requesting for extension upto 30/06/2023 and submits that the following factors have caused the subject delay of 9 months:- • Shortage of certain material in the markets due to the supply chain disruptions and scarcity of materials like metals and semi-conductors • Installation and licence for working of lift is awaited. The application was filed with required fees in Aug’22, however, the licence is still awaited. This has delayed the lift installation completion. • Increase in the materials costs had to lead to stricter payments terms and delivery terms. • The other buildi…”

Source: KUL Utsav Phase I -Building G’s extension records on MahaRERA (P52100003489), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KUL Utsav Phase I -Building G

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100003489
Status
Completed
Builder
Kumar Builders
Location
Bund Garden, Pune · 411048
Project type
Residential / Group Housing
Registered on
5 Aug 2017
Completion date at registration
May 2019
Latest completion date
June 2023
Delay so far
49 months
Homes
64
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of KUL Utsav Phase I -Building G, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Utsav Phase I -Building G70%85%37%20%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KUL Utsav Phase I -Building G every month.

KUL Utsav Phase I -Building G: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of KUL Utsav Phase I -Building G →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KUL Utsav Phase I -Building G: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KUL Utsav Phase I -Building G

What is the possession date of KUL Utsav Phase I -Building G?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KUL Utsav Phase I -Building G in Bund Garden, Pune is 30 June 2023 — 49 months later than 15 May 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for KUL Utsav Phase I -Building G?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KUL Utsav Phase I -Building G's builder has filed on MahaRERA, the official one, is 30 June 2023, already 49 months later than the 15 May 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KUL Utsav Phase I -Building G extended?

According to GharKundli's check of MahaRERA records (updated November 2026), KUL Utsav Phase I -Building G's builder applied to MahaRERA to extend the completion date 3 times: to 14 May 2020, giving the reason "Appointed RCC contractor constantly have low labour strength, he was unable to achieve milestones, after several instructions given by us. Deployed Labours had low skilled/productivity level; thus we were not getting work quality up to the mark. Therefore we rectify the quality for betterment of the project, in the process of rectification and deployment of skilled workers work is delayed."; to 31 March 2022, giving the reason "Applicant submits that now the construction of this project is at the stage of completion. The external structure of the building is ready. The brickwork, internal and external plastering and internal POP are more than 60 % completed. The work remaining is finishing tasks of wall plastering, tiles, plumbing, sanitary fitting etc. Applicant submits due to COVID 19 pandemic lockdown was declared in Pune in March’2020. As a result the labours working on the site of this Applicant went back to their native places outside Maharashtra. As a result the construction work on the site of the Applican…"; to 30 June 2023, giving the reason "The Applicant is requesting for extension upto 30/06/2023 and submits that the following factors have caused the subject delay of 9 months:- • Shortage of certain material in the markets due to the supply chain disruptions and scarcity of materials like metals and semi-conductors • Installation and licence for working of lift is awaited. The application was filed with required fees in Aug’22, however, the licence is still awaited. This has delayed the lift installation completion. • Increase in the materials costs had to lead to stricter payments terms and delivery terms. • The other buildi…".

What is the RERA number of KUL Utsav Phase I -Building G?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KUL Utsav Phase I -Building G in Bund Garden, Pune is P52100003489.

Is KUL Utsav Phase I -Building G registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KUL Utsav Phase I -Building G is registered as P52100003489 and its status is "Completed".

What is the construction status of KUL Utsav Phase I -Building G?

According to GharKundli's check of MahaRERA records (updated November 2026), KUL Utsav Phase I -Building G's status on MahaRERA is "Completed". As filed by the builder, slab work on Utsav Phase I -Building G is 85% done and internal work 37%. GharKundli's full report compares construction progress with the deadline.

Does KUL Utsav Phase I -Building G have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is KUL Utsav Phase I -Building G safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), KUL Utsav Phase I -Building G is registered on MahaRERA as P52100003489, its MahaRERA status is "Completed", its completion date has moved 49 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does KUL Utsav Phase I -Building G have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Kul Utsav Phase I - Building D (P52100007160); KUL Utsav Phase I -Building F (P52100009849). Check that your agreement names the registration of your own wing.

How can I get updates if KUL Utsav Phase I -Building G's possession date changes?

The latest dates are on KUL Utsav Phase I -Building G's MahaRERA page (P52100003489). GharKundli's Kundli Watch sends a free WhatsApp update on KUL Utsav Phase I -Building G every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KUL Utsav Phase I -Building G have?

According to GharKundli's check of MahaRERA records (updated November 2026), KUL Utsav Phase I -Building G has one building filed: Utsav Phase I -Building G with 15 floors.

How big is the land of KUL Utsav Phase I -Building G?

According to GharKundli's check of MahaRERA records (updated November 2026), KUL Utsav Phase I -Building G stands on 652 sq m of land (about 0.2 acres), with 3,797 sq m of sanctioned built-up area.

Where can I read reviews of KUL Utsav Phase I -Building G?

Google Maps has reviews of KUL Utsav Phase I -Building G written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KUL Utsav Phase I -Building G?

KUL Utsav Phase I -Building G by Kumar Builders is in Bund Garden, Pune (pincode 411048), near Kondhwa Bk, Kondhwa budruk, Katraj, Maharashtra, and is registered on MahaRERA as P52100003489, per GharKundli's check of MahaRERA records.

How many homes are in KUL Utsav Phase I -Building G?

According to GharKundli's check of MahaRERA records (updated November 2026), KUL Utsav Phase I -Building G has 64 homes in 1 tower registered on MahaRERA.

When was KUL Utsav Phase I -Building G registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), KUL Utsav Phase I -Building G was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on KUL Utsav Phase I -Building G?

1 court case is listed for KUL Utsav Phase I -Building G on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of KUL Utsav Phase I -Building G?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Kumar Builders, which has 6 other projects registered on MahaRERA.