SAI VILLAGE PHASE 1
by SAI HARIKRUPA GRUHANIRMAN · Yawat, Pune
Possession date of SAI VILLAGE PHASE 1: 30 April 2027, moved from 30 December 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100004944, and currently active. Its completion date has moved from December 2021 to April 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SAI VILLAGE PHASE 1?
How the possession date of SAI VILLAGE PHASE 1 has moved
30 December 2021
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EXT52100011167)
Reason the builder gave MahaRERA: “Due to Covid-19 Pandemic, we are not able to complete our construction within existing completion time limit. Hence, we have obtained the 55.56% Consent for extension of Proposed Date of Completion.”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAI VILLAGE PHASE 1’s extension records on MahaRERA (P52100004944), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAI VILLAGE PHASE 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100004944
- Status
- Registered and active
- Builder
- SAI HARIKRUPA GRUHANIRMAN
- Location
- Yawat, Pune · 412214
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- April 2027
- Delay so far
- 60 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 160
- Sold or booked
- 64%
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SAI VILLAGE PHASE 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 100% | 100% |
| B | 100% | 100% | 100% | 100% |
| C | 100% | 100% | 100% | 100% |
| D | 100% | 100% | 100% | 100% |
| E | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- A: covers 5 floors
- B: covers 5 floors
- C: covers 5 floors
- D: covers 5 floors
- E: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI VILLAGE PHASE 1 every month.
SAI VILLAGE PHASE 1: buildings, flats and land, as filed on MahaRERA
- Buildings: A (6 floors, 32 units) · B (6 floors, 32 units) · C (6 floors, 32 units) · D (6 floors, 32 units) · E (6 floors, 32 units)
- Land: 11,000 sq m (about 2.7 acres) · sanctioned built-up 8,687 sq m · recreational space 1,100 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAI VILLAGE PHASE 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAI VILLAGE PHASE 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAI VILLAGE PHASE 1
What is the possession date of SAI VILLAGE PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAI VILLAGE PHASE 1 in Yawat, Pune is 30 April 2027 — 60 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAI VILLAGE PHASE 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI VILLAGE PHASE 1's builder has filed on MahaRERA, the official one, is 30 April 2027, already 60 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAI VILLAGE PHASE 1 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI VILLAGE PHASE 1's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Due to Covid-19 Pandemic, we are not able to complete our construction within existing completion time limit. Hence, we have obtained the 55.56% Consent for extension of Proposed Date of Completion.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SAI VILLAGE PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAI VILLAGE PHASE 1 in Yawat, Pune is P52100004944.
Is SAI VILLAGE PHASE 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI VILLAGE PHASE 1 is registered as P52100004944 and its status is "Registered and active".
What is the construction status of SAI VILLAGE PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI VILLAGE PHASE 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does SAI VILLAGE PHASE 1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SAI VILLAGE PHASE 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI VILLAGE PHASE 1 is registered on MahaRERA as P52100004944, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAI VILLAGE PHASE 1's possession date changes?
The latest dates are on SAI VILLAGE PHASE 1's MahaRERA page (P52100004944). GharKundli's Kundli Watch sends a free WhatsApp update on SAI VILLAGE PHASE 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAI VILLAGE PHASE 1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI VILLAGE PHASE 1 has 5 buildings filed: A with 6 floors and 32 units; B with 6 floors and 32 units; C with 6 floors and 32 units; D with 6 floors and 32 units; E with 6 floors and 32 units.
How big is the land of SAI VILLAGE PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI VILLAGE PHASE 1 stands on 11,000 sq m of land (about 2.7 acres), with 8,687 sq m of sanctioned built-up area and 1,100 sq m of recreational open space.
Where can I read reviews of SAI VILLAGE PHASE 1?
Google Maps has reviews of SAI VILLAGE PHASE 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAI VILLAGE PHASE 1?
SAI VILLAGE PHASE 1 by SAI HARIKRUPA GRUHANIRMAN is in Yawat, Pune (pincode 412214), Maharashtra, and is registered on MahaRERA as P52100004944, per GharKundli's check of MahaRERA records.
How many homes are in SAI VILLAGE PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI VILLAGE PHASE 1 has 160 homes in 5 towers registered on MahaRERA, and 64% of them are sold or booked.
When was SAI VILLAGE PHASE 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI VILLAGE PHASE 1 was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SAI VILLAGE PHASE 1?
No court cases are listed for SAI VILLAGE PHASE 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SAI VILLAGE PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAI HARIKRUPA GRUHANIRMAN.
Check it yourself on MahaRERA
- How to check the possession date of SAI VILLAGE PHASE 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →