Skip to content
GharKundli

Anandtara Whitefield Residences Phase - I

by ANANDTARA INFRASTRUCTURE · Lonkar Vasti, Pune 411036Also near Keshavnagar, Mundhwa, Amanora Park Town

What’s in the report? →

Possession: Anandtara Whitefield Residences Phase - I (MahaRERA P52100007529) is marked completed on MahaRERA. It has 160 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100007529. Status: Completed.

Source: MahaRERA website — records for P52100007529, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Anandtara Whitefield Residences Phase - I?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Anandtara Whitefield Residences Phase - I has moved

  1. 30 June 2019

    Completion date given when the project was registered

  2. 29 June 2020

    Extended at the builder's request (MahaRERA application EXT52100002435)

    Reason the builder gave MahaRERA:
    “We have received revised layout after making changes in Phase II (Rera register No. P52100018257) owing to such changes in the layout we were obliged to intimate the Department of Environment Clearance and receive revised Environment Cleara…” Read the full reason“We have received revised layout after making changes in Phase II (Rera register No. P52100018257) owing to such changes in the layout we were obliged to intimate the Department of Environment Clearance and receive revised Environment Clearance. Hence, there was a delay in applying for the completion Certificate and Occupancy Certificate. However, it may be noted, we have completed the building construction to the extent of handing over the possession for Occupancy pending such Certification; we are expecting the Certification within Six month starting 30 June 2019.”
  3. 29 December 2020

    Revised completion date on MahaRERA

Source: Anandtara Whitefield Residences Phase - I’s extension records on MahaRERA (P52100007529), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Anandtara Whitefield Residences Phase - I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100007529
Status
Completed
Builder
ANANDTARA INFRASTRUCTURE
Location
Lonkar Vasti, Pune · 411036
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
June 2019
Latest completion date
December 2020
Delay so far
18 months
Homes
160
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Anandtara Whitefield Residences Phase - I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING C100%90%99%99%
BUILDING D100%100%99%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anandtara Whitefield Residences Phase - I every 1–2 months.

Anandtara Whitefield Residences Phase - I: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Anandtara Infrastructure has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 10 months); 3 still being built, 1 past the promised date. No complaints on MahaRERA.

Read Google reviews of Anandtara Whitefield Residences Phase - I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Anandtara Whitefield Residences Phase - I: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Anandtara Whitefield Residences Phase - I

What is the possession date of Anandtara Whitefield Residences Phase - I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Anandtara Whitefield Residences Phase - I in Lonkar Vasti, Pune is 29 December 2020 — 18 months later than 30 June 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Anandtara Whitefield Residences Phase - I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Anandtara Whitefield Residences Phase - I's builder has filed on MahaRERA, the official one, is 29 December 2020, already 18 months later than the 30 June 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Anandtara Whitefield Residences Phase - I extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I's builder applied to MahaRERA to extend the completion date once: to 29 June 2020, giving the reason "We have received revised layout after making changes in Phase II (Rera register No. P52100018257) owing to such changes in the layout we were obliged to intimate the Department of Environment Clearance and receive revised Environment Clearance. Hence, there was a delay in applying for the completion Certificate and Occupancy Certificate. However, it may be noted, we have completed the building construction to the extent of handing over the possession for Occupancy pending such Certification; we are expecting the Certification within Six month starting 30 June 2019.".

What is the RERA number of Anandtara Whitefield Residences Phase - I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Anandtara Whitefield Residences Phase - I in Lonkar Vasti, Pune is P52100007529.

Is Anandtara Whitefield Residences Phase - I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I is registered as P52100007529 and its status is "Completed".

What is the current construction status of Anandtara Whitefield Residences Phase - I? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I's status on MahaRERA is "Completed". As filed by the builder, slab work ranges from 90% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Anandtara Whitefield Residences Phase - I have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Anandtara Whitefield Residences Phase - I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I is registered on MahaRERA as P52100007529, its MahaRERA status is "Completed", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Anandtara Whitefield Residences Phase - I?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Anandtara Whitefield Residences Phase - I?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Anandtara Whitefield Residences Phase - I: gharkundli.com/tools/property-cost-calculator

Has Anandtara Whitefield Residences Phase - I received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Anandtara Whitefield Residences Phase - I completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I is marked completed on MahaRERA, and the completion date filed there is 29 December 2020. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Anandtara Whitefield Residences Phase - I uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Anandtara Whitefield Residences Phase - I was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Anandtara Whitefield Residences Phase - I's possession date changes?

The latest dates are on Anandtara Whitefield Residences Phase - I's MahaRERA page (P52100007529). GharKundli's Kundli Watch sends a free WhatsApp update on Anandtara Whitefield Residences Phase - I every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Anandtara Whitefield Residences Phase - I have?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I has 2 buildings filed: BUILDING C with 12 floors; BUILDING D with 12 floors.

How big is the land of Anandtara Whitefield Residences Phase - I?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I stands on 1,375 sq m of land (about 0.3 acres), with 8,020 sq m of sanctioned built-up area and 752 sq m of recreational open space.

What is the track record of Anandtara Whitefield Residences Phase - I's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Infrastructure has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 10 months); 3 still being built, 1 past the promised date. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Anandtara Whitefield Residences Phase - I?

Google Maps has reviews of Anandtara Whitefield Residences Phase - I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Anandtara Whitefield Residences Phase - I?

Anandtara Whitefield Residences Phase - I by ANANDTARA INFRASTRUCTURE is in Lonkar Vasti, Pune, pincode 411036 (near Keshavnagar, Mundhwa, Amanora Park Town), Maharashtra, and is registered on MahaRERA as P52100007529, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO. 32/3A, SURVEY NO. 32/3B. GharKundli lists all 241 MahaRERA projects in Mundhwa (411036).

How many flats are in Anandtara Whitefield Residences Phase - I?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I has 160 homes in 2 towers registered on MahaRERA.

When was Anandtara Whitefield Residences Phase - I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Anandtara Whitefield Residences Phase - I was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Does Anandtara Whitefield Residences Phase - I have any legal issues or court cases?

No court cases are listed for Anandtara Whitefield Residences Phase - I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Anandtara Whitefield Residences Phase - I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ANANDTARA INFRASTRUCTURE, which has 4 other projects registered on MahaRERA.

Other projects in Haveli

All 241 projects in Mundhwa (411036) →

Other projects by ANANDTARA INFRASTRUCTURE

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.